Well ID: 34-073-22322 | |
Country: United States | |
State: Ohio | |
County: Hocking | |
Municipality: Green Township | |
Operator Name: KILBARGER INVESTMENTS INC | |
Well Pad ID: | |
Farm/Lease Name: LAWRENCE EVANS | |
License Status: Producing | |
License Date: 2008-01-11 | |
Spud Date: 2008-01-15 | |
Spud Drilling Contractor: KILBARGER DRLG | |
Final Drill Date: 2008-01-31 | |
Well Total Depth: 1190.00 ft | |
Configuration: Vertical | |
Latitude: 39.510000 | |
Longitude: -82.290000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
Original Spud | 1980-07-01 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
Completed | 1980-07-06 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
CO | 1983-02-03 | 1367 R & R OIL & GAS GeoDate 2/3/83 |
OIL WELL | 1983-02-03 | Issued Date 2/3/83 Expired Date 8/2/83 Proposed Purpose OG Was Plug Supervised Who Superivsed Plug and Abandon Date 3/17/83 |
Plugged/Abandoned | 1983-03-17 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
Change of Owner | 2008-01-09 | Operator changed from 1367, R & R OIL & GAS to 1675, KILBARGER INVESTMENTS INC |
APP | 2008-01-11 | Proposed Formations:BEREA/OHIO SHALE, Issued Date:1/11/2008, Expired Date:1/10/2009 6:00:00 AM, Drilling unit acres:80, Proposed Well Type:OG, Proposed Well Class:POOL |
Reached Total Depth | 2008-01-31 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
Completion Report Received | 2008-05-19 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
Construction Permit Expires | 2009-01-10 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
Record Last Modified | 2017-02-15 | OTD: 3222' IN CLINTON-REOPEN TO BEREA |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
2008-09-03 | 970 | 982 | 26 |
2008-09-03 | 3084 | 3098 | 14 |
3084 | 3098 | 14 | |
970 | 982 | 26 | |
970 | 982 | 26 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
Not Treated | 0 | 0 | 0 | NOT FRACED… PERFED UNDER 300 GAL OF 15% HCL ACID | ||
H2O | 0 | 3000 Bbl | 30000 |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2008 | KILBARGER INVESTMENTS INC | 515.00 | 0.00 | 152 |
2009 | KILBARGER INVESTMENTS INC | 232.00 | 0.00 | 365 |
2010 | KILBARGER INVESTMENTS INC | 466.00 | 0.00 | 365 |
2011 | KILBARGER INVESTMENTS INC | 158.00 | 0.00 | 365 |
2013 | KILBARGER INVESTMENTS INC | 0.00 | 0.00 | 365 |
2014 | KILBARGER INVESTMENTS INC | 0.00 | 0.00 | 365 |
2015 | KILBARGER INVESTMENTS INC | 0.00 | 0.00 | 365 |
2016 | KILBARGER INVESTMENTS INC | 0.00 | 0.00 | 365 |
2017 | KILBARGER INVESTMENTS INC | 0.00 | 0.00 | 365 |
2018 | KILBARGER INVESTMENTS INC | 0.00 | 0.00 | 365 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2008 | KILBARGER INVESTMENTS INC | Brine | 0 | 152 |
2009 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2010 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2011 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2013 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2014 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2015 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2016 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2017 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
2018 | KILBARGER INVESTMENTS INC | Brine | 0 | 365 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-744882637 | 2008-1-17 0:00: | DD | No Violations | |
0000DP3133 | Final Restoration | No Violations | Final Restoration done information from Data Point | |
0572788961 | 2008-10-21 | Preliminary Restoration | No Violations | An inspection revealed that the preliminary restoration meets requirements. |
0744882637 | 2008-01-17 | Drill / Deepen / Reopen | No Violations | Checked on drilling rig. Kilbarger Drilling is re-opening this well. |
0835941197 | 2009-04-02 | Production Wells | No Violations | An inspection revealed no earthen dike around the tanks. The tanks do not meet the minimum 50 setback requirement from the well, as one tank was found to be 17 from the well. Also noted was that spacing between tanks do not meet 3 requirement. The lease road will need to be graded when the location dries up. The pumping unit that had been placed on the well has since been removed. The well appears to be strictly a gas well due to configuration. Spoke with well owner regarding the inspection results and found that the tanks are going to be removed. The frac tank will be left to contain a dike and lease graded. |
1688520803 | 2008-04-07 | Production Wells | No Violations | New Lat & Long. |
1743566005 | 2008-01-22 | Drill / Deepen / Reopen | No Violations | Checked on drilling rig. The depth at the time of the inspection was 1086 feet. Kilbarger states that they may drill down to the top of the lime and frac the shale formation. |
572788961 | 2008-10-21 0:00 | PL | No Violations | |
835941197 | 2009-4-2 0:00:0 | PW | No Violations | |
DP3133 | FR | No Violations |
For data sources see[9]