Well Details

Well ID: 34-089-26171
Loading map...
Country: United States
State: Ohio
County: <County>
Municipality:
Operator Name: McDONALD DALE E
Well Pad ID:
Farm/Lease Name: WEEKLEY
License Status: Producing
License Date: 2015-09-29
Spud Date: 2015-11-18
Spud Drilling Contractor:
Final Drill Date:
Well Total Depth:
Configuration: Vertical
Latitude: 40.020000
Longitude: -82.380000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2015-09-29 Proposed Formations:BEREA, Issued Date:9/29/2015, Expired Date:9/28/2017 12:00:00 PM, Drilling unit acres:76.65, Proposed Well Type:OG, Proposed Well Class:
Construction Permit Expires 2017-09-28
Record Last Modified 2017-10-23

For data sources see[2]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2016 McDONALD DALE E 0.00 30.00 365
2017 McDONALD DALE E 0.00 0.00 0
2018 McDONALD DALE E 0.00 0.00 365

For data sources see[3] [4]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2016 McDONALD DALE E Brine 0 365
2017 McDONALD DALE E Brine 0 0
2018 McDONALD DALE E Brine 0 365

For data sources see[5] [6]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1089589319 2020-4-22 0:00: PL No Violations 0.50
-1151347039 2017-5-22 0:00: PL No Violations 0.50
-1367244798 2016-6-17 0:00: DD No Violations
-1375573559 2016-2-5 0:00:0 AM No Violations
-1386157754 2017-5-8 0:00:0 PL No Violations
-1423450791 2015-12-17 0:00 CS No Violations
-1484427056 2016-5-11 0:00: DD No Violations
-1576412030 2016-7-12 0:00: DD No Violations
-192416292 2020-8-3 0:00:0 PW No Violations 0.50
-1973294519 2020-8-31 0:00: PL No Violations 0.50
-875867900 2016-4-11 0:00: DD No Violations
-921083097 2016-3-11 0:00: DD No Violations
0381990376 2016-02-05 Drill / Deepen / Reopen No Violations Inspect location to check pit water again. A layer of ice was observed in the pit. The ice was broken in order to obtain water sample. Water was field tested with Quantab titrator. The field test result was approximately 235 PPM Chlorides. Time of inspection: 9:00 AM. Weather: 22*F, Sunny
0495028342 2015-11-30 Drill / Deepen / Reopen No Violations An inspection of drilling operations revealed no activity. The well has been spudded. The pit did not have a liner. The well owner will be advised to install a liner in the pit. Time of inspection: 2:00 PM. Weather: 42*F, Overcast
0660783096 2016-02-24 Drill / Deepen / Reopen No Violations Inspect drilling operations. No activity. Check pit due to large rainfall event this day. Fluid level ok. Time of inspection: 3:30 PM. Weather: 61*F, Overcast
0875867900 2016-04-11 Drill / Deepen / Reopen No Violations Inspect location as a status check. No activity during inspection. Pit level ok. Time of inspection: 10:00 AM. Weather: 52*F, Rain
0914907230 2015-10-22 Drill / Deepen / Reopen No Violations Inspect location. Jeremy McDonald has moved in his cable tool rig. The well has not been spudded. No activity during inspection. Time of inspection: 9:20 AM. Weather: 56*F, Sunny
0921083097 2016-03-11 Drill / Deepen / Reopen No Violations Inspect drilling operations. No activity. Check fluid level in pit. Pit ok. Time of inspection: 3:40 PM. Weather: 58*F, Sunny
1151347039 2017-05-22 Preliminary Restoration No Violations This inspection was conducted as a compliance notice follow-up. The inspection revealed that the pit has not been closed as of this date. I received a phone call this morning from Mike McDonald informing me that the pit has not been closed. Mr. McDonald was advised to work on having the pit closed the following week. Time of inspection: 11:15 AM. Weather: 63*F, Partly cloudy
1367244798 2016-06-17 Drill / Deepen / Reopen No Violations Inspect drilling operations. No activity during inspection. The well was shot with nitro gel on 6/1/2016. The stimulation was not witnessed. No violations during inspection. Time of inspection: 10:35 AM. Weather: 72*F, Partly cloudy
1375573559 2016-02-05 Administrative Inspection No Violations A phone call was placed to Dale E. McDonald (Jeremy McDonald) at 2:33 PM and was advised to monitor fluid level in pit. It was suggested that water be pumped out to keep fluid at a safe level. Jeremy stated that they would do that and would prevent pit from overflowing. Jeremy informed me that drilling operations are ongoing. The well has been drilled but they are waiting to shoot the well. Once the well is shot it will be cleaned out.
1386157754 2017-05-08 Preliminary Restoration Violations Noted This inspection was conducted as a status check. The drilling rig was set up on the well during the inspection. The well was not in production at the time of inspection. The well was shut-in with a swage and valve. The inspection revealed that the drilling pit has not been closed as of this inspection. The pit will need to be closed within 10 days. According to ORC 1509.072 (A) the drilling pit shall be closed within two months after the date upon which the drilling of a well is completed. Once the pit has been closed work will need to begin on finishing the rest of the preliminary restoration. Time of inspection: 11:05 AM. Weather: 52*F, Sunny
1423450791 2015-12-17 Casing String Witnessed No Violations I witnessed the cementing of the 5.5 surface casing for Dale E. McDonald on Jeremy McDonalds cable tool rig. Jeremy and Mike McDonald were on location. Cemenco was contracted to cement casing. Cemenco broke circulation and good cement returns were observed. Cement dropped approximately 3 feet. A basket was not used. The ticket was received. Time of inspection: 2:30 PM.
1454935267 2016-02-04 Drill / Deepen / Reopen No Violations Inspect drilling operations. No personnel on location during inspection. The rig was still on location. The 5.5 had a swage and valve on it. During the inspection oil was observed on the pit water and just outside of the pit. It appears that a recent large rainfall event has allowed oil/water to breach pit bank. The amount of oil outside of the dike would approximately be less than a gallon. The pit water was field tested with a Quantab titrator. The field test revealed a 5.0 reading which equals approximately 224 PPM Chlorides. This is below EPA Secondary Drinking Water standards of 250 PPM Chlorides. The pit was properly lined during inspection. Photos were taken of pit. The well owner will be notified and advised to prevent fluids from escaping pit. The inspection also revealed cement has dropped on the backside of the 5.5 further than the three feet mentioned in the previous inspection. Cement will need to be added and filled to surface. Time of inspection: 11:30 AM. Weather: 32*F, Overcast
1456321612 2016-02-22 Drill / Deepen / Reopen No Violations Inspect drilling operations. No activity during inspection. Drilling operations are ongoing. Pit level ok. Will continue to monitor. Time of inspection: 8:30 AM. Weather: 32*F, Partly cloudy
1461081714 2016-04-18 Administrative Inspection No Violations A voice mail message was left for Dale E. McDonald (Jeremy McDonald) at 10:30 AM regarding cement drop on the backside of the casing. Jeremy was advised to fill up backside of casing with concrete before the well is shot.
1464193546 2016-05-18 Drill / Deepen / Reopen No Violations Inspect drilling operations. No activity during inspection. Pit ok. A phone call was placed to Jeremy McDonald regarding filling up backside of casing. Jeremy stated that he has been adding clay instead of concrete to prevent bridging. Jeremy said it would be finished before well is shot. Time of inspection: 10:20 AM. Weather: 54*F, Sunny
1484427056 2016-05-11 Drill / Deepen / Reopen No Violations Inspect location. No activity during inspection. Pit ok. Time of inspection: 3:00 PM. Weather: 68*F, Partly cloudy
1495719618 2017-05-25 Preliminary Restoration No Violations This inspection was conducted as a compliance notice follow-up. The closure of the pit has begun but was not finished during inspection. Jeremy McDonald left a voicemail at 5:17 PM on 5/24/17 indicating that the pit would be completely closed in by the following week. Time of inspection: 9:30 AM. Weather: 61*F, Light rain
1496321656 2017-06-01 Preliminary Restoration No Violations Inspect location as a compliance notice follow-up. The pit has not been completely closed in. The company will be advised to continue working on closing it in. Time of inspection: 8:45 AM.
1576412030 2016-07-12 Drill / Deepen / Reopen No Violations Inspect location as a status check. The rig was still on the well. No activity during inspection. No violations observed. Time of inspection: 9:35 AM. Weather: 77*F, Sunny
1586474084 2017-06-15 Preliminary Restoration No Violations This inspection was conducted as a follow-up. The inspection revealed that the pit has been closed. The company will be advised to work on the remainder of the restoration. Time of inspection: 8:45 AM.
1691125761 2016-10-14 Drill / Deepen / Reopen No Violations Inspect location. No personnel during inspection on location. The drilling rig is still on well. The well had a 5 inch x 2 inch swage and valve on it. A gauge on the casing showed 5 pounds of gas pressure. The pit has not been closed yet. Jeremy McDonald will be advised to close the pit as soon as possible. Time of inspection: 11:00 AM. Weather: 47*F, Sunny
381990376 2016-2-5 0:00:0 DD No Violations
495028342 2015-11-30 0:00 DD No Violations
660783096 2016-2-24 0:00: DD No Violations
914907230 2015-10-22 0:00 DD No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1386157754 US-OH-111461 2017-05-25 NONE3 Failure to close drilling pits within two months