Well Details

Well ID: 34-111-24367
Loading map...
Country: United States
State: Ohio
County: <County>
Municipality:
Operator Name: TRIAD HUNTER LLC
Well Pad ID: US-OH-000561
Farm/Lease Name: ORMET CORP
License Status: Producing
License Date: 2012-12-18
Spud Date: 2013-01-02
Spud Drilling Contractor: WARREN DRLG
Final Drill Date: 2013-01-22
Well Total Depth: 11431.00 ft
Configuration: Horizontal
Latitude: 39.710000
Longitude: -80.830000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2012-12-18 Proposed Formations:MARCELLUS SHALE, Issued Date:12/18/2012, Expired Date:12/18/2014 12:00:00 PM, Drilling unit acres:484, Proposed Well Type:OG, Proposed Well Class:EOUT
Reached Total Depth 2013-01-22
Correction to Well 2013-04-05 UNIT SIZE CHANGED TO 528.30 ACRES. CORRECTION TO TARGET INFORMATION: FOOTAGE & X,Y COORDINATES FROM AS DRILLED SURVEY PLAT.
Completion Report Received 2014-01-03
Construction Permit Expires 2014-12-18
Record Last Modified 2017-02-15

For data sources see[2]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2013-08-15 H2O 8 7617 Bbl 435000 Producers Service Corporation Stage 1- 72 perforations with a bridge plug set at 9973'. The formation was broke prior to starting stimulation.
2013-09-04 H2O 8 7932 Bbl 439000 Producers Service Corporation STAGE 17

72 SHOTS

2013-08-22 H2O 8 8709 Bbl 443900 Producers Service Corporation STAGE 8

72 SHOTS

2013-09-05 H2O 8 7891 Bbl 445700 Producers Service Corporation STAGE 18

72 SHOTS

2013-08-15 H2O 8 7893 Bbl 440000 Producers Service Corporation STAGE 1

72 SHOTS

2013-09-04 H2O 8 7855 Bbl 439300 Producers Service Corporation 16 of 19 stages to be stimulated in the horizontal well bore.
2013-08-21 H2O 8 7943 Bbl 438800 Producers Service Corporation STAGE 6

72 SHOTS

2013-09-03 H2O 8 7840 Bbl 440000 Producers Service Corporation STAGE 14

72 SHOTS

2013-08-21 H2O 8 7578 Bbl 437000 Producers Service Corporation STAGE 5

72 SHOTS

2013-09-04 H2O 8 8001 Bbl 439200 Producers Service Corporation STAGE 15

72 SHOTS

2013-08-19 H2O 8 7914 Bbl 439500 Producers Service Corporation STAGE 3

72 SHOTS

2013-08-23 H2O 8 8223 Bbl 437800 Producers Service Corporation STAGE 9

72 SHOTS

2013-08-24 H2O 8 7933 Bbl 446400 Producers Service Corporation STAGE 10

72 SHOTS

2013-08-16 H2O 8 7818 Bbl 436800 Producers Service Corporation STAGE 2

72 SHOTS

2013-09-03 H2O 8 8428 Bbl 448800 Producers Service Corporation STAGE 13

72 SHOTS

2013-09-05 H2O 8 7593 Gal 442900 Producers Service Corporation STAGE 19

72 SHOTS

2013-08-27 H2O 8 8138 Bbl 441900 Producers Service Corporation STAGE 12

72 SHOTS

2013-08-20 H2O 8 7897 Bbl 431400 Producers Service Corporation STAGE 4

72 SHOTS

2013-08-22 H2O 8 8258 Bbl 442600 Producers Service Corporation STAGE 7

72 SHOTS

2013-08-26 H2O 8 7922 Bbl 451100 Producers Service Corporation STAGE 11

72 SHOTS

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2013 TRIAD HUNTER LLC 0 2070 5
2014 TRIAD HUNTER LLC 861809 44466 271
2015 TRIAD HUNTER LLC 731222 17040 357
2016 TRIAD HUNTER LLC 525360 9965 367
2017 TRIAD HUNTER LLC 430774 5731 365
2018 TRIAD HUNTER LLC 382534 3729 364
2019 TRIAD HUNTER LLC 85537 717 90

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2013 TRIAD HUNTER LLC Brine 0 5
2014 TRIAD HUNTER LLC Brine 16164 271
2015 TRIAD HUNTER LLC Brine 10904 357
2016 TRIAD HUNTER LLC Brine 6492 367
2017 TRIAD HUNTER LLC Brine 6976 365
2018 TRIAD HUNTER LLC Brine 4161 364
2019 TRIAD HUNTER LLC Brine 743 90

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-114181547 2013-8-15 0:00: CT No Violations 3.00
-1186510362 2013-12-12 0:00 CT No Violations 1.00
-1228299868 2016-2-18 0:00: PL No Violations 1.00
-1277909755 2018-11-13 0:00 PW No Violations 0.20
-1491824014 2014-9-9 0:00:0 PW No Violations 8.00
-1538756722 2013-1-11 0:00: DD No Violations
-1958402773 2013-9-4 0:00:0 CT No Violations 1.20
0114181547 2013-08-15 Completion Testing No Violations Inspection to witness the 1st stage to be stimulated in the Marcellus zone, The well was perforated with 72 shots between 9778 and 9925 with a solid composite bridge plug set at 9973. The annular casing pressure is being monitored by the means of a electronic transducer with a pressure relief valve set at 1000 psi and the annular side is plumed into the choke manifold for proper control if needed.
0353530588 2017-08-22 Production Wells No Violations Producing well status check inspection found the well equipped with a casing and tubing well head and a 2 production sales line set up to sell product off the tubing well head. The sales line has a hydraulic Emergency Shut Down with no electrically controlled actuation solenoid. The well head is leaking gas from the B-section between the 9.625 & 13.375. On site was Triad Production Foreman Derik Higgins who was informed to install flow lines and pressure relief valves on all well annulis. Mr. Higgins was informed that the gas was not to dispersed into the atmosphere and a permanent recovery system must be installed. The well head assembly gauge showed 50 psi at surface.
0420259949 2018-04-12 Production Wells No Violations Status check inspection found the well head production valves in the open position with annular pressure monitoring in place. There is activity around the well pad supporting a second pad adjoining the well pad the said well is on. The company has submitted a simultaneous operations plan that indicated they will put a cage over the wells and establish a perimeter around the wells with barricades in place. Both are being followed out. The well produced into a midstream operation on a nearby pad.
1186510362 2013-12-12 Completion Testing No Violations Company is having a contractor named Fesco to hook up flow back equipment up and flare well.
1228299868 2016-02-18 Preliminary Restoration No Violations Preliminary Restoration status check inspection fund the area affected by the initial well pad construction does have vegetation and erosion control established. There is a fresh water impoundment in place adjacent to the drilling pad. A separate production facility is located near the well pad, this facility will service multiple well pads in the direct area owned by the current registered owner (Triad). Documenting the well head - the well head is complete with the tubing production valve in the open position. There is a hydraulic emergency shut down device located in the production tree outlet. The company has annular pressure gauges on all annulis sections of the well head and the company has a authorized representative periodically checking and documenting all annuli pressures. Addressing the production facility- A total of (8) 400 barrel production tanks are located inside a polymer lined metal containment dike area with (2) low pressure vapor recover units also present inside the dike area. A (6) station commercial tank load out facility is located on the production pad along with a naturel gas compressor and gas processing equipment.
1277909755 2018-11-13 Production Wells No Violations On site inspection found 3 wells on the well pad with all 3 being Marcellus shale wells. The wells are equipped with artificial lift technologies and producing off the production tubing. The 5.5 diameter production casing pressure is 175 pounds per square inch (psi). There is a riser pipe on the 9.625 well head section with 1,100 psi present. Proper well identification is posted and there is an additional well pad between the 3 wells and the production facility. The production fluid storage facility has been reduced to (3) 500 barrel tanks situated inside a polymer lined steel containment dike area.
1357140701 2013-01-02 Drill / Deepen / Reopen No Violations The well was spudded and 60 of 20 conductor was set on 12/28/2012. Inspector on site on 01/02/2013 to witness the running and cementing of the surface casing with 510 of 13.375 54.5 Lb casing ran and cemented back to surface with circulation established prior to cementing with 7 BBL cement returns to surface and good lift pressure. Inspector will note the surface casing will be pressure tested upon installation of the BOP. All casing tally and cement job records received.
1357328019 2013-01-04 Drill / Deepen / Reopen No Violations Inspection found the current drilling depth to be 1542 using a 12.250bit with the next casing string to be 9.625 set at 2700.
1357567119 2013-01-07 Drill / Deepen / Reopen No Violations Inspection found the company currently in the process of setting their BOP on the 9.625 casing with will be tested. 2718 of 9.625 casing was ran and cemented back to surface on 01/06/13 with 30% cement excess ran and 37 BBL cement returns to surface. All records received.
1358261096 2013-01-15 Drill / Deepen / Reopen No Violations Inspection of the drilling process found the current drilling depth to be 8262, which is 1200 into the Horizontal section. The proposed TD is 11478.
1358679973 2013-01-18 Drill / Deepen / Reopen No Violations Inspector received a call from the company man on site with notification that the well bore total drilling depth has been reached @ 11,431 and that they would be running production casing and should be cementing on 01/20/13.
1358729746 2013-01-20 Drill / Deepen / Reopen No Violations Inspector spoke with the drilling coordinator on site over the phone for a status update on the running of the production casing. Operator stated that they had 3356 of 5.5 casing in the hole and were running at a rate of 500 per hour and should be ready to cement late this evening.
1358977083 2013-01-23 Drill / Deepen / Reopen No Violations Status check inspection on the completion of the well bore. The well Total depth drilled was found to be 11,431. Records indicate that 11,428 of 20 pound 5.5 production casing was set in the well bore with records received on the cementing job and casing tally. The well drilling process is complete and the drilling rig is rigging down. Inspector Pat Shreve accompanied me on this day.
1386938855 2013-12-12 Completion Testing No Violations Status check inspection found the well has had the completion plugs drilled out and tubing has been run and set in the well bore, Contractors are on site and hooked up to begin the testing of the well today. On a pass through visit on 12/09/13 I witness the 500 barrel portable storage tanks to be used in the completion had no grounding wirers, I addressed this verbally with the company man on site and the issue has been taken care of.
1491824014 2014-09-09 Production Wells No Violations The southeast meeting was held at the site. The well is a producing well with a large Texas well head. We looked at the process from the well head to the midstream line. Facility is in compliance with 1509 and 1501:9-9-05.
1538756722 2013-01-11 Drill / Deepen / Reopen No Violations Status update inspection found the current drilling depth to be 4640 and building the Horizontal curve at a 9 degree angel using a 8.750 bit.
1725133559 2014-09-09 Preliminary Restoration No Violations On the day of my inspection accompanied by ODNR staff and Production Supervisor Rodney Boron, I witnessed that the well was equipped with Cameron casing and tubing wellheads along with a Christmas tree valve assembly and a sand trap controlled manually to a 300bbl frac tank in containment. Production equipment included a GPS Unit, a compressor unit, dehydrator unit, and a fuel skid. Tank battery consisted of 8-500bbl tanks and 2 let down towers all within containment. Also on site were 4 combustors and a pig launcher. The site passed preliminary restoration according to ORC 1509.072A.
1958402773 2013-09-04 Completion Testing No Violations Status check on the stimulation process found Producers Frac service stimulation the 17th stage to be completed, A solid bridge plug was set at 7408 and 72 perforations shot between 7377 and 7191. The well was treated with 2500 gallons of 7.5% HCL.
353530588 2017-8-22 0:00: PW No Violations
420259949 2018-4-12 0:00: PW No Violations 0.30

For data sources see[8]

References