Well ID: 34-111-24374 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.81,"lon":-81.3,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Monroe | |
Municipality: Seneca Township | |
Operator Name: ANTERO RESOURCES CORPORATION | |
Well Pad ID: US-OH-000538 | |
Farm/Lease Name: GARY UNIT | |
License Status: Producing | |
License Date: 2014-05-07 | |
Spud Date: 2013-06-11 | |
Spud Drilling Contractor: PATTERSON DRILLING | |
Final Drill Date: 2013-08-01 | |
Well Total Depth: 17685.00 ft | |
Configuration: Horizontal | |
Latitude: 39.810000 | |
Longitude: -81.300000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2013-04-26 | Proposed Formations:POINT PLEASANT, Issued Date:4/26/2013, Expired Date:4/26/2015 12:00:00 PM, Drilling unit acres:452.533, Proposed Well Type:OG, Proposed Well Class:EDPW |
Reached Total Depth | 2013-08-01 | |
Correction to Well | 2013-08-30 | CORRECTION TO TARGET & SURFACE INFORMATON (FOOTAGE & X,Y COORDINATES) FROM AS DRILLED SURVEY PLAT. UNIT SIZE CHANGED TO 645.286 ACRES. |
Completion Report Received | 2014-01-23 | |
APP | 2014-05-07 | Proposed Formations:POINT PLEASANT, Issued Date:5/7/2014, Expired Date:5/6/2016 12:00:00 PM, Drilling unit acres:645.989, Proposed Well Type:OG, Proposed Well Class:EDPW |
Construction Permit Expires | 2016-05-06 | |
Record Last Modified | 2017-02-15 |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
2014-01-24 | 8877 | 17508 | 0 |
8877 | 17508 | 0 | |
8877 | 17508 | 0 |
For data sources see[3]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 09/16/2013 | 10/09/2013 | 8107 | 11,671,600.0 | 533812 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | Water | Antero Resources | Base Fluid | Water | 7732-18-5 | 100 | 89.8797 | 97,341,100.0 |
LGC-15 | U.S. Well Services, LLC | Gelling Agents | Suspending agent (solid) | 14808-60-7 | 3 | 0.01054 | 11414.7 | |
Guar Gum | 9000-30-0 | 50 | 0.06891 | 74634.4 | ||||
Petroleum Distillates | 64742-47-8 | 60 | 0.06527 | 70683.2 | ||||
Surfactant | 68439-51-0 | 3 | 0.00413 | 4478.06 | ||||
HCL Acid (12.6%-18.0%) | U.S. Well Services, LLC | Bulk Acid | Water | 7732-18-5 | 87.5 | 0.07803 | 84508 | |
Hydrogen Chloride | 7641-01-1 | 18 | 0.01864 | 20186.2 | ||||
Bioclear 2000 | U.S. Well Services, LLC | Anti-Bacterial Agent | 2,2-dibromo-3-nitrilopropionamide | 10222-01-2 | 20 | 0 | 0 | |
Deionized Water | 7732-18-5 | 28 | 0 | 0 | ||||
Sand | U.S. Well Services, LLC | Proppant | Crystalline Silica, quartz | 14808-60-7 | 100 | 9.7782 | 10,589,900.0 | |
AP One | U.S. Well Services, LLC | Gel Breakers | Ammonium Persulfate | 7727-54-0 | 100 | 0.00094 | 1018 | |
WFRA-405 | U.S. Well Services, LLC | Friction Reducer | Anionic Polyacrylamide | Proprietary | 0 | 0.02507 | 27148.4 | |
Ethoxylated alcohol blend | Proprietary | 5 | 0.00313 | 3393.55 | ||||
Petroleum Distillates | 64742-47-8 | 22 | 0.02018 | 21854.4 | ||||
Water | 7732-18-5 | 40 | 0.02507 | 27148.4 | ||||
Crystalline Salt | 12125-02-9 | 5 | 0.00313 | 3393.55 | ||||
SI-1000 | U.S. Well Services, LLC | Scale Inhibitor | Anionic Copolymer | Proprietary | 0 | 0.00425 | 4599.39 | |
Ethylene Glycol | 107-21-1 | 20 | 0.00384 | 4157.47 | ||||
Water | 7732-18-5 | 30 | 0.0032 | 3466.98 | ||||
AI-300 | U.S. Well Services, LLC | Acid Corrosion Inhibitors | Tar bases, quinoline derivs, benzyl chloride-quaternized | 72480-70-7 | 13 | 0.00005000 | 57.4209 | |
Triethyl Phosphate | 78-40-0 | 3 | 0.00001000 | 9.34497 | ||||
Ethylene Glycol | 107-21-1 | 31 | 0.0002 | 214.672 | ||||
Isopropyl Alcohol | 67-63-0 | 3 | 0.00001000 | 7.42156 | ||||
Ethoxylated Nonylphenol | 68412-54-4 | 5 | 0.00001000 | 15.5749 | ||||
2-Butoxyethanol | 111-76-2 | 7 | 0.00005000 | 50.7218 | ||||
N,N-Dimethylformamide | 68-12-2 | 15 | 0.00006000 | 66.353 | ||||
Water | 7732-18-5 | 20 | 0.00002000 | 19.7033 | ||||
Cinnamaldehyde | 104-55-2 | 5 | 0.00005000 | 58.209 |
For data sources see[4]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
2013-10-04 | H2O | 15 | 6193 Bbl | 255960 | US Well Services Inc | STAGE 22
60 SHOTS |
2013-09-30 | H2O | 15 | 6306 Bbl | 257500 | US Well Services Inc | STAGE 10
60 SHOTS |
2013-09-17 | H2O | 15 | 6586 Bbl | 200638 | Superior Well Services | STAGE 5
60 SHOTS |
2013-10-07 | H2O | 15 | 5902 Bbl | 263380 | US Well Services Inc | STAGE 37
60 SHOTS |
2013-09-17 | H2O | 15 | 7147 Bbl | 229080 | US Well Services Inc | STAGE 3
60 SHOTS |
2013-10-05 | H2O | 15 | 5967 Bbl | 256670 | US Well Services Inc | STAGE 27
60 SHOTS |
2013-10-01 | H2O | 15 | 7078 Bbl | 207780 | Superior Well Services | STAGE 13
60 SHOTS |
2013-09-19 | H2O | 15 | 5708 Bbl | 235498 | US Well Services Inc | STAGE 7
60 SHOTS |
2013-09-30 | H2O | 15 | 7110 Bbl | 244740 | US Well Services Inc | STAGE 9
60 SHOTS |
2013-10-07 | H2O | 15 | 6736 Bbl | 246310 | US Well Services Inc | STAGE 38
60 SHOTS |
2013-10-06 | H2O | 15 | 5691 Bbl | 225810 | US Well Services Inc | STAGE 31
60 SHOTS |
2013-10-01 | H2O | 15 | 6230 Bbl | 262130 | US Well Services Inc | STAGE 12
60 SHOTS |
2013-10-04 | H2O | 15 | 6843 Bbl | 235340 | US Well Services Inc | STAGE 26
60 SHOTS |
2013-10-09 | H2O | 15 | 6188 Bbl | 256270 | US Well Services Inc | STAGE 44
60 SHOTS |
2013-10-01 | H2O | 15 | 6302 Bbl | 262170 | US Well Services Inc | STAGE 11
60 SHOTS |
2013-09-17 | H2O | 15 | 6620 Bbl | 130760 | US Well Services Inc | STAGE 4
60 SHOTS |
2013-10-06 | H2O | 15 | 6639 Bbl | 256970 | US Well Services Inc | STAGE 32
60 SHOTS |
2013-10-02 | H2O | 15 | 6073 Bbl | 238040 | US Well Services Inc | STAGE 18
60 SHOTS |
2013-10-05 | H2O | 15 | 6109 Bbl | 261985 | US Well Services Inc | STAGE 41
60 SHOTS |
2013-10-02 | H2O | 15 | 6249 Bbl | 260100 | US Well Services Inc | STAGE 15
60 SHOTS |
2013-10-02 | H2O | 15 | 6193 Bbl | 259800 | US Well Services Inc | STAGE 16
60 SHOTS |
2013-09-30 | H2O | 15 | 6783 Bbl | 262840 | US Well Services Inc | STAGE 8
60 SHOTS |
2013-10-04 | H2O | 15 | 6108 Bbl | 257830 | US Well Services Inc | STAGE 23
60 SHOTS |
2013-10-03 | H2O | 15 | 6193 Bbl | 260150 | US Well Services Inc | STAGE 19
60 SHOTS |
2013-10-03 | H2O | 15 | 6235 Bbl | 248305 | US Well Services Inc | STAGE 20
60 SHOTS |
2013-10-03 | H2O | 15 | 6218 Bbl | 253650 | US Well Services Inc | STAGE 21
60 SHOTS |
2013-10-06 | H2O | 15 | 6055 Bbl | 285245 | US Well Services Inc | STAGE 29
60 SHOTS |
2013-09-17 | ACID | 0 | 6620 Bbl | 130760 | US Well Services Inc | Stage 4 to be completed with 60 perforations shot in the horizontal well bore section. |
2013-10-08 | H2O | 15 | 5869 Bbl | 262500 | US Well Services Inc | STAGE 39
60 SHOTS |
2013-10-07 | H2O | 15 | 6119 Bbl | 258370 | US Well Services Inc | STAGE 34
60 SHOTS |
2013-10-06 | H2O | 15 | 6038 Bbl | 258565 | US Well Services Inc | STAGE 30
60 SHOTS |
2013-10-09 | H2O | 15 | 6216 Bbl | 260895 | US Well Services Inc | STAGE 43
60 SHOTS |
2013-09-16 | H2O | 15 | 6651 Bbl | 232210 | US Well Services Inc | STAGE 1
60 SHOTS |
2013-10-04 | H2O | 15 | 6061 Bbl | 258775 | US Well Services Inc | STAGE 25
60 SHOTS |
2013-09-18 | H2O | 15 | 5995 Bbl | 66318 | US Well Services Inc | STAGE 6
60 SHOTS |
2013-10-04 | H2O | 15 | 6059 Bbl | 257020 | US Well Services Inc | STAGE 24
60 SHOTS |
2013-10-07 | H2O | 15 | 6635 Bbl | 250900 | US Well Services Inc | STAGE 36
60 SHOTS |
2013-10-06 | H2O | 15 | 5986 Bbl | 248150 | US Well Services Inc | STAGE 33
60 SHOTS |
2013-10-05 | H2O | 15 | 6043 Bbl | 262570 | US Well Services Inc | STAGE 28
60 SHOTS |
2013-10-02 | H2O | 15 | 6164 Bbl | 261400 | US Well Services Inc | STAGE 17
60 SHOTS |
2013-10-08 | H2O | 15 | 5871 Bbl | 251530 | US Well Services Inc | STAGE 40
60 SHOTS |
2013-10-07 | H2O | 15 | 6641 Bbl | 232710 | US Well Services Inc | STAGE 35
60 SHOTS |
2013-10-01 | H2O | 15 | 6948 Bbl | 226890 | US Well Services Inc | STAGE 14
60 SHOTS |
2013-09-16 | H2O | 15 | 6615 Bbl | 263850 | US Well Services Inc | STAGE 2
60 SHOTS |
2013-10-08 | H2O | 15 | 6522 Bbl | 149830 | US Well Services Inc | STAGE 42
60 SHOTS |
For data sources see[5]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | ANTERO RESOURCES CORPORATION | 1329318 | 2959 | 67 |
2014 | ANTERO RESOURCES CORPORATION | 2752275 | 721 | 345 |
2015 | ANTERO RESOURCES CORPORATION | 1238199 | 1055 | 365 |
2016 | ANTERO RESOURCES CORPORATION | 734202 | 206 | 363 |
2017 | ANTERO RESOURCES CORPORATION | 573519 | 170 | 365 |
2018 | ANTERO RESOURCES CORPORATION | 461587 | 162 | 365 |
2019 | ANTERO RESOURCES CORPORATION | 103402 | 78 | 90 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | ANTERO RESOURCES CORPORATION | Brine | 12259 | 67 |
2014 | ANTERO RESOURCES CORPORATION | Brine | 51260 | 345 |
2015 | ANTERO RESOURCES CORPORATION | Brine | 10031 | 365 |
2016 | ANTERO RESOURCES CORPORATION | Brine | 6654 | 363 |
2017 | ANTERO RESOURCES CORPORATION | Brine | 3984 | 365 |
2018 | ANTERO RESOURCES CORPORATION | Brine | 3233 | 365 |
2019 | ANTERO RESOURCES CORPORATION | Brine | 623 | 90 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-104973216 | 2014-7-30 0:00: | PL | No Violations | |
-1164136253 | 2013-7-22 0:00: | DD | No Violations | 1.50 |
-1562463184 | 2019-1-29 0:00: | PW | No Violations | 0.10 |
-1852827231 | 2018-3-7 0:00:0 | PW | No Violations | 0.20 |
-1993117978 | 2013-8-14 0:00: | PW | No Violations | |
-2041437847 | 2013-9-24 0:00: | CT | No Violations | 2.80 |
-239972832 | 2013-12-12 0:00 | PW | No Violations | 0.50 |
-248919027 | 2013-6-24 0:00: | DD | No Violations | 1.50 |
-454331525 | 2013-6-13 0:00: | DD | No Violations | 1.00 |
-701613509 | 2013-7-15 0:00: | DD | No Violations | |
-781576551 | 2013-8-14 0:00: | PW | No Violations | |
-782926415 | 2013-7-17 0:00: | DD | No Violations | 2.00 |
0084380566 | 2013-07-01 | Drill / Deepen / Reopen | No Violations | Inspection found the company just finishing testing the BOP. Records were received from the setting of the 13.375 casing string at 2063. |
0104973216 | 2014-07-30 | Preliminary Restoration | No Violations | Status check inspection on the preliminary restoration found the well drilling and stimulation process is now complete and the well is in line and producing with 8- 400 barrel production tanks on site servicing all 6 wells on the drill pad now in production. |
0239972832 | 2013-12-12 | Production Wells | No Violations | Bill Stolarik and I stopped in at the location and inspected the site. Well is in production. Tanks, dike and identifications are in place. |
0248919027 | 2013-06-24 | Drill / Deepen / Reopen | No Violations | Inspection found the current drilling depth to be 174 using a 24 bit and drilling on air with the proposed surface casing string depth to be 400. KB is 24. |
0317777720 | 2013-06-12 | Drill / Deepen / Reopen | No Violations | Notification was received that the said well is to be spudded and the conductor set on this day. I inspected the site and reviewed the permit conditions with the drilling superintendent for Express Energy who is the drilling contractor. I shall Gps the well once the conductor is set. |
0337522129 | 2013-06-16 | Casing String Witnessed | No Violations | On this day I witnessed Allied Cement Services top off the initial conductor job that had settled out. 6 barrels of class A cement were used. |
0454331525 | 2013-06-13 | Drill / Deepen / Reopen | No Violations | Status check inspection found Express Energy drilling the conductor hole. The well was spudded on 06/12/13 and the drilling company is having difficulty drilling the conductor hole due to being on solid bedrock. |
0701613509 | 2013-07-15 | Drill / Deepen / Reopen | No Violations | inspection found the drilling company Patterson Drilling rig 316 rigging up the casing crew and getting ready to run 7071 of 9.625 casing. The casing tally was received and reviewed and the company man will post me this evening of their progress. |
0781576551 | 2013-08-14 | Production Wells | No Violations | The well is in the production testing stages and is being flow tested. The tubing pressure is 5000 psi. I asked the company man on site to place proper well identification on each well head. |
0782926415 | 2013-07-17 | Drill / Deepen / Reopen | No Violations | Inspection and status check of the drilling progress to witness the BOP test, The Blind and Pipe rams along with the Choke Manifold were tested to 5000 psi the annular side was tested to 2500 psi. Records were also received from the 9.625 upper casing upper section cement job, The company will test the casing integrity after drilling through the 2 stage tool and running the drill string to TD near the float collar to 2700 psi. |
0827444911 | 2013-09-17 | Completion Testing | No Violations | Status check on the completion process found Rush Wire line Services perforating the 5th stage to be completed, a solid bridge plug was set at 16,736 and 6 clusters of 10 perforations were shot from 16,721 to 16,555 with the annular pressure being monitored electronically with a transducer. |
0992197433 | 2013-12-13 | Production Wells | No Violations | The well is in production and on line, The company has completed 3 wells on the pad and is currently in the process of drilling 3 more. |
1059096311 | 2013-07-29 | Casing String Witnessed | No Violations | status check inspection on the progress on the running of the 5.5 production casing. The well bore Total drilled depth was 17,688 ant the current casing depth is 12,822. |
1164136253 | 2013-07-22 | Drill / Deepen / Reopen | No Violations | Inspection found the current drilling depth to be 12,689 using a 8.750 drill bit and drilling on oil based mud. The projected well bore total depth is 17,679. |
1261280386 | 2018-03-07 | Production Wells | No Violations | Status check inspection accompanied by ODNR Inspector Tom Thomas to document the well status. The well is equipped with a casing and tubing well head assembly with (2) manually operated valves on the tubing well head and one emergency shut down valve on the tubing tree production flow line. The well head casing flow line is also tied into the production flow line however the valves are in the closed position. The 13.375 and 9.625 casing well head assemblies have flowlines with valves and gauges installed to monitor annular pressure. The 13.375 casing well head pressure gauge reads 100 pounds pressure and the 9.625 casing well head reads 1,000 pounds pressure. On pad total is (6) complete wells supported by (6) gas processing units. Also on location is a production fluid facility consisting of a total of (8) steel construction tanks with a capacity of 400 barrels of fluid each, the tanks are situated inside a polymer lined steel containment dike area. The well lease road entrance is gated and locked with signage posted at the entrance of the well pad and at each well head. The well pad has a stone surface along with the lease road. The well pad perimeter berm is of earthen material and in good repair. |
1371296683 | 2013-06-14 | Casing String Witnessed | No Violations | Witness cementing of casing string Express Energy Services drilled to 90 of 32 hole and ran 90 of new 26 casing and cemented it in place with 500 sacks cement with 45 bbl of good returns.
Note: Driller encountered water 8 below ground level and also they encountered extremely hard drilling@85 they called and we granted them modified setting depth of conductor pipe. |
1372266443 | 2013-06-26 | Casing String Witnessed | No Violations | On 06/25 & 26 I witnessed the running and setting of 392 of 18.625 surface casing with 100% cement excess ran and 75 barrels of good cement returns to surface. The casing was pressure tested to 700 psi which was 500 over lift pressure with no recorded pressure loss. The mix water was tested and showed no chlorides prior to cementing. We had several job delays due to lightening. |
1373074637 | 2013-07-05 | Drill / Deepen / Reopen | No Violations | Notification was received from the company man on site that they have lost the 12.250 cutting head off the hammer bit in the hole at 4300 and are plugging back to 3800 with a kick plug and will deviate around the lost cutting head. |
1375214600 | 2013-07-30 | Casing String Witnessed | No Violations | Status check inspection of the running of the 5.5 production casing, 17,685 of production casing has been ran and set in the well bore with proper centralizer placement along with a casing shoe and float collar ran. The well bore had over 2500 units of 3rd party gas and the company was circulating oil based mud trying to kill the gas pressure in order to start the cementing process. |
1376479224 | 2013-08-14 | Drill / Deepen / Reopen | No Violations | The well bore drilling process is complete and the well is awaiting stimulation, There are 2 other wells on the pad that are in production. |
1380728731 | 2013-10-02 | Completion Testing | No Violations | Inspection of the completion process found the wire line company running in the hole to set a plug at 14,571 and perforate the 16th stage from 14,555 to 14,389 for a total stage length of 197. A status check on the preliminary restoration found that vegetation has been established and erosion and sedimentation control is in place. With a tank production fluid tank battery erected on site with metal containment. |
1383149360 | 2013-10-30 | Production Wells | No Violations | The well is the 3rd well on the drill pad to be completed and is now capable of production, There are 8 400 barrel production tanks on location in use. |
1429716572 | 2013-07-16 | Casing String Witnessed | No Violations | On this day I witnessed the displacement of the bottom section plug below the DV tool which is set at 4710. The plug was displaced with 154 barrels of oil based drilling mud on top of the wiper plug and chased with 340 barrels of KCL. The 2 stage relief tool was dropped and allowed to fall to the seat for a time frame of 30 minutes. Upon the opening of the tool relief ports the hole shall be circulated with KCL for 8 hours by the rig mud pumps allowing the bottom section cement to cure. The top section shall then be cemented. |
1562463184 | 2019-01-29 | Production Wells | No Violations | On this day, I found the pad gated with signage at the entrance. There are (6) producing wells, (6) gas processing units, (4) 400-barrel steel production tanks within steel containment, and an Emergency Shutdown (ESD) button is present at the pad entrance. Concrete barriers surround the perimeter of the wellheads. Each well has identification and annular pressure monitoring devices equipped. The 9.625 inch diameter intermediate casing has a pressure of 60 pounds per square inch (psi), and the 13.375 inch diameter surface casing has a pressure of 80 psi. |
1610460774 | 2013-07-08 | Drill / Deepen / Reopen | No Violations | Status check inspection plug was set at 4300 over a lost 12.250 bit with the top of the plug at 4300. The company is currently drilling at 3616 starting their 6 degree deviation kick around the lost bit and should fall back in at 4825 under the bit. A cement ticket was received from the kick plug. |
1852827231 | 2018-03-07 | Production Wells | No Violations | On this day, I accompanied ODNR Inspector William Stolarik. Please refer to his comments for a detailed report. The well is equipped with annular pressure monitoring devices. Concrete barriers surround the wellheads. The facility is gated with an electronic shutdown button on the right-hand side, prior to the pad. The front left of the pad is equipped with (8) 400 barrel steel tanks within containment and an electronic shutdown button. There are (6) gas processing units along the back of the pad, and a midstream facility behind the gas processing units. |
1993117978 | 2013-08-14 | Production Wells | No Violations | The well is in the production testing stages and is being flow tested. The tubing pressure is 5000 psi. I asked the company man on site to place proper well identification on each well head. |
2041437847 | 2013-09-24 | Completion Testing | No Violations | Inspection and status check of the completion process found the 7 stages of the well bore have been completed and Arrow well services rig is making a cleanout run on the production casing. I met with several of the service company and producing company safety representatives on site and discussed the flow back and clean out procedures, proper well head control is in place and the clean out is to be performed with fresh water with no produced water to be reused eliminating the chance of condensate being introduced to any pump on location. |
2095342462 | 2020-5-22 0:00: | PW | No Violations | 1.00 |
317777720 | 2013-6-12 0:00: | DD | No Violations | 3.00 |
337522129 | 2013-6-16 0:00: | CS | No Violations | 1.00 |
827444911 | 2013-9-17 0:00: | CT | No Violations | 1.20 |
84380566 | 2013-7-1 0:00:0 | DD | No Violations | |
992197433 | 2013-12-13 0:00 | PW | No Violations | 1.00 |