34-111-24494

Well Details

Well ID: 34-111-24494
Loading map...
Country: United States
State: Ohio
County: Monroe
Municipality: Seneca Township
Operator Name: ANTERO RESOURCES CORPORATION
Well Pad ID: US-OH-001063
Farm/Lease Name: LORADITCH UNIT
License Status: Producing
License Date: 2015-01-20
Spud Date: 2014-09-15
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2015-02-24
Well Total Depth: 17331.00 ft
Configuration: Horizontal
Latitude: 39.830000
Longitude: -81.260000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-06-16 Proposed Formations:POINT PLEASANT, Issued Date:6/16/2014, Expired Date:6/15/2016 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
APP 2014-11-10 Proposed Formations:POINT PLEASANT, Issued Date:11/10/2014, Expired Date:11/9/2016 12:00:00 PM, Drilling unit acres:659.424, Proposed Well Type:OG, Proposed Well Class:POOL
APP 2015-01-20 Proposed Formations:POINT PLEASANT, Issued Date:1/20/2015, Expired Date:1/19/2017 12:00:00 PM, Drilling unit acres:659.424, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2015-02-24
Correction to Well 2015-04-24 CHANGE IN TARGET & TAKE-POINT INFORMATION (FOOTAGES & COORDINATES) FROM AS DRILLED SURVEY PLAT. UNIT SIZE INCREASED.
Completion Report Received 2015-11-13
Construction Permit Expires 2017-01-19
Record Last Modified 2017-10-23

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2015-11-16 8626 17243 0
8626 17243 0
8626 17243 0

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 04/26/2015 06/18/2015 8464 12,701,100.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Ferrotrol 300L Baker Hughes Iron Control MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0021802 2563.37
Scaletrol 720 Baker Hughes Scale Inhibitor MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0150208 17661.1
GW-3 Baker Hughes Gelling Agent MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0389437 45789
GW-3LDF Baker Hughes Gelling Agent MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.005494 6459.75
FRW-18 Baker Hughes Friction Reducer MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0691998 81363.4
Water Operator Carrier Water 7732-18-5 100 90.0387 105,899,000.0
CI-39 Baker Hughes Corrosion Inhibitor MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0006807 800.4
HCl, 10.1 - 15% Baker Hughes Acidizing MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.327064 384553
Sand, White, 40/70 Baker Hughes Proppant MSDS and Non-MSDS Ingredients Listed Below N/A 0 4.46594 5,250,940.0
Sand, White, 100 mesh Baker Hughes Proppant MSDS and Non-MSDS Ingredients Listed Below N/A 0 1.25914 1,480,470.0
Alpha 1427 Baker Hughes Biocide MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.008893 10456.3
Sand, White, 20/40 Baker Hughes Proppant MSDS and Non-MSDS Ingredients Listed Below N/A 0 3.73971 4,397,060.0
Ingredients in Additive(s) (MSDS and non-MSDS) Baker Hughes See Trade Name(s) List Sodium Chloride 7647-14-5 5 0.003609 4244.78
Guar Gum 9000-30-0 100 0.0422266 49664.8
Oxyalkylated Fatty Acid 61791-002 40 0.0002722 320.16
Glutaraldehyde 111-30-8 30 0.0026671 3136.88
Tar Bases, Quinoline Derivs., Benzyl Chloride-Quaternized 72480-70-7 30 0.0002042 240.12
1-butoxy-2-propanol 5131-66-8 5 0.0002746 322.988
Aldehyde 104-55-2 30 0.0002042 240.12
Ethylene Glycol 107-21-1 45 0.0067572 7947.51
Mineral Oil 8042-47-5 70 0.0038446 4521.82
Isotridecanol, ethoxylated 9043-30-5 5 0.0002746 322.988
Sulfurized polyolefin 68037-13-8 5 0.00003400 40.02
2-Propenoic, Polymer with Sodium Phosphinate, Sodium Salt 71050-62-9 20 0.0030032 3532.22
Petroleum Distillates 64742-47-8 30 0.0016477 1937.93
Quaternary Ammonium Compound 68424-85-1 5 0.0004785 562.832
Crystalline Silica (Quartz) 14808-60-7 100 9.46176 11,128,500.0
Formic Acid 64-18-6 30 0.0002042 240.12
Polyaklylene 7756-94-7 1 0.00000680 8.004
Oleamide DEA 93-83-4 2 0.0013836 1627.27
Paraffinic Petroleum Distillate 64742-55-8 30 0.0016477 1937.93
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.0013836 1627.27
Polyoxythylene Sorbitan Monooleate 9005-65-6 0.5 0.0003459 406.817
Crystalline Silica: Quartz 14808-60-7 5 0.0002746 322.988
Citric Acid 77-92-9 60 0.0013077 1538.02
Didecyl Dimethyl Ammonium Chloride 7173-51-5 10 0.000889 1045.63
Poly (acrylamide-co-acrylic acid) partial sodium salt 62649-23-4 30 0.0207533 24409
2-butoxy-1-propanol 15821-83-7 0.1 0.00000550 6.45975
Water 7732-18-5 95 0.331567 389973
Isopropanol 67-63-0 5 0.00003400 40.02
Potassium Acetate 127-08-2 0.5 0.00000340 4.002
Potassium Chloride 7447-40-7 1 0.0001502 176.611
Ammonium Chloride 12125-02-9 3 0.0020753 2440.9
Sorbitan Monooleate 1338-43-8 0.5 0.0003459 406.817
Hydrochloric Acid 7647-01-0 15 0.0490438 57683
Hemicellulase Enzyme Concentrate 9025-56-3 5 0.0006313 742.481
Ethanol 64-17-5 5 0.0004445 522.813
Calcium Chloride 10043-52-4 5 0.0007508 883.056
Hydrotreated Light Distillate 64742-47-8 30 0.0207533 24409
Potassium Iodide 7681-11-0 2 0.00001360 16.008

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2015-06-18 H2O 15 6092 Bbl 223993 BAKER-HUGHES STAGE 49/49

36 SHOTS

2015-05-11 H2O 15 6483 Bbl 238862 BAKER-HUGHES STAGE 1/49

36 SHOTS STAGES 2-48 SEE IMAGES

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2015 ANTERO RESOURCES CORPORATION 2064683 47 153
2016 ANTERO RESOURCES CORPORATION 2177378 51 366
2017 ANTERO RESOURCES CORPORATION 846886 164 364
2018 ANTERO RESOURCES CORPORATION 554771 213 363
2019 ANTERO RESOURCES CORPORATION 90089 69 90

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2015 ANTERO RESOURCES CORPORATION Brine 28521 153
2016 ANTERO RESOURCES CORPORATION Brine 20761 366
2017 ANTERO RESOURCES CORPORATION Brine 7997 364
2018 ANTERO RESOURCES CORPORATION Brine 5838 363
2019 ANTERO RESOURCES CORPORATION Brine 1043 90

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1028932448 2015-2-24 0:00: DD No Violations 1.50
-1128438036 2015-2-3 0:00:0 DD No Violations 3.00
-1438525445 2015-2-11 0:00: DD No Violations 2.00
-1604591490 2018-3-7 0:00:0 PW No Violations 0.20
-1733321021 2018-3-7 0:00:0 PW No Violations 0.20
-178828843 2019-1-14 0:00: PW No Violations 0.30
-705108963 2015-2-12 0:00: DD No Violations 2.30
-967130156 2015-2-9 0:00:0 DD No Violations 2.00
-968533127 2020-6-30 0:00: PW No Violations 0.40
0178828843 2019-01-14 Production Wells No Violations On this day, I spoke with Antero Company Representative Jayson Lukes during the inspection. The producing wells on the pad (permit numbers 4489, 4490, 4492, 4494) are being prepped per Anteros SIMOPS plan that was submitted and reviewed by the ODNR DOGRM, before Stalnaker Energy rigs-up for the plug and abandonment of permit numbers 4491 and 4493. TekSolv is currently onsite setting the back pressure valve. The producing wells have been blown down, are having back pressure valves installed in the tubing hangers, steel cages placed over the wellheads, LEL monitors in place, and concrete Jersey barriers spotted around the perimeter of the wellheads. It will be noted that a 2-way check valve will not be placed in the tubing, as the SIMOPS plan originally stated. I spoke with Jayson Lukes and ODNR Inspector Ken Frye about the amendment to the plan.
0705108963 2015-02-12 Drill / Deepen / Reopen No Violations Status check inspection on the current drilling process found Patterson Drilling rig 343 on location drilling the horizontal wellbore section at a current depth of 10,342 in the directional azimuth of 330 degrees at 90.92 degrees using 15.5# drilling mud with a current influx of 2,169 units of gas.
0967130156 2015-02-09 Drill / Deepen / Reopen No Violations My inspection today finds the well has been drilled to a depth of 9235. The top drive is broke down. Drilling will resume as soon as the top drive is repaired.
1028932448 2015-02-24 Drill / Deepen / Reopen No Violations Status check inspection on the drilling progress found Patterson Drilling rig 343 has recently completed the drilling of the 8.5 production borehole to a measured depth of 17,331 in the directional azimuth of 331.73 degrees with a true vertical depth of 8,326 at the casing shoe. 17,355 of 5.5 23# -P-
1128438036 2015-02-03 Drill / Deepen / Reopen No Violations I am onsite to witness part of the blow out preventer (BOP) testing. The annular section of the BOP did not pass and is being rebuilt. The testing services are being provided by Gas Field Resources. The company representative was instructed to email copies of the test as soon as available.
1330479029 2014-09-18 Casing String Witnessed No Violations Status check inspection found Rocky Mountain drillings top hole rig has drilled a 32 x 80 conductor borehole and set 80 of 26 conductor in place with a variance granted by the Division to set 80 of conductor due to being in solid limestone bedrock at 60 freshwater was also encountered at 27. Allied cement services are on location and cementing the casing using 228 sacks of class A-2% calcium .25 pps flake with 30% open hole excess ran and 46.5 barrels of fresh water used for cement displacement with good cement returns to surface. The hole was spudded on 09/15/14.
1416440338 2014-11-19 Casing String Witnessed No Violations 11/19/2014 Dallas Morris rig # 24 is now on the hole and has drilled a 24x 397 surface casing borehole on air and ran 376 of 18.625 -87.50# J-55 casing with a Texas style guide shoe and float collar ran along with proper centralizer placement demonstrated. Allied Cement services are on location to cement the casing using 737 sacks of class A-2% calcium .25 pps flake along with 100% open hole excess cement used with circulation established prior to cementing and 25 bbl of 6% gel ran ahead of the cement and the casing pressure tested to 500 psi over displacement lift pressure upon the landing of the cement plug and good cement returns witnessed to surface. The cement weight was verified and the mix water tested showing no chlorides.
1416868294 2014-11-24 Drill / Deepen / Reopen No Violations Status check inspection on the current drilling process found Dallas Morris rig # 24 on location picking up the 12.250 bottom hole drilling assembly to begin running in the hole with the drill string to drill the 12.250 2nd intermediate well bore section on air.
1423484050 2015-02-08 Drill / Deepen / Reopen No Violations Status check inspection on the drilling process found Patterson Drilling rig 343 on location drilling the 8.750 production borehole at a depth of 8,685 in the directional azimuth of 337.82 using 13.8# mud weight with a viscosity of 77, the 3rp party gas units are at 2452. The projected well bore total drilling depth will be 17,450.
1430484733 2015-02-15 Drill / Deepen / Reopen No Violations Status check inspection on the current drilling process found Patterson drilling rig 343 on the hole drilling the 8.750 production borehole at a depth of 12,963 in the directional azimuth of 327.19 degrees and inclination of 90.65 degrees with a true vertical well bore depth of 8,404 carrying a 15.1# mud weight. The drilling rig has adequate containment and the perimeter drainage system valves are in the closed position during drilling operations.
1434475612 2015-06-16 Completion Testing No Violations Status check inspection on the well stimulation process found Baker Hughes pressure pumping service on location stimulating stage 43 of 49 to be completed with the annular pressure being monitored electronically. Allied Horizontal wireline service is on location and has perforated the stage (43) with a solid completion plug set at 9,851 and 60 perforations shot in 10 clusters of 6 shots utilizing a shoot on the fly method of 38 a minute travel speed between the depths of 9,813 and 9,682 in the horizontal well bore section.
1436453808 2015-07-09 Completion Testing No Violations Status check inspection on the well completion process found Fortis Well Service on location drilling out the completion plugs at a current depth of 14,985 with Cudd Services providing well control during the drill out process. The rig and all support equipment is located on containment and Myers well service is on location recovering surface water created from the recent rain fall event.
1438525445 2015-02-11 Drill / Deepen / Reopen No Violations My inspection today finds the rig is circulating the well at 30 strokes (3 barrels) per minute. Gas levels have been minimized and the Pason system is reading 60 units of gas. The company representative Matt Manderfield stated that the mud will be built up to 15.1 pounds per gallon before controlled drilling will resume.
1604591490 2018-03-07 Production Wells No Violations On site inspection accompanied by ODNR Inspector Tom Thomas. On this day the well was observed to be production off the production tree with (2) manual production valves present along with a single (ESD) Emergency Shut Down valve. The ESD has remote shut down buttons located at the well pad entrance along with the production facility and the gas processing units. The well is equipped with steel lines on the 13.375 and 9.625 casing well heads with valves and gauges present to monitor annular pressures. The 13.375 well head section was observed to have 0 pounds pressure on it at surface and the 9.625 section was observed to have 50 pounds on it at surface. In conversation with Anteros Production Supervisor Doug Stebbins all annular pressures are being monitored and evaluated. The well pad has an earthen berm established. The production fluid facility is located on a adjoining site pad and consists of (8) steel construction tanks of 400 barrels fluid capacity each. The tanks are situated inside a polymer lined steel containment dike area.
1733321021 2018-03-07 Production Wells No Violations On this day, I accompanied ODNR Inspector William Stolarik. Please refer to his comments for a detailed report. The well is equipped with annular pressure monitoring devices. Concrete barriers surround the wellheads. The facility is gated with an electronic shutdown button on the left-hand side, prior to the pad. The back of the pad is equipped with (8) 400 barrel steel tanks within containment. There are (4) gas processing units along the front right side of the pad, and a midstream facility along the back right side.
2089784016 2015-11-09 Preliminary Restoration No Violations Preliminary Restoration status check inspecting found the affected area by the well pad construction has properly been restored with vegetation and erosion control in place. Addressing the well head- The well drilling and completion process is now complete and the well is on line and producing along with 3 other wells on the pad. Supporting the well is a gas processing unit and 8-400 barrel production tanks located in a polymer lined metal containment dike area. Proper well identification is posted at the well head.

For data sources see[10]

References