Well Details

Well ID: 34-127-22679
Loading map...
Country: United States
State: Ohio
County: Perry
Municipality: Jackson Township
Operator Name: BELL OIL
Well Pad ID:
Farm/Lease Name: BELL ROBERT E
License Status: Final Restoration
License Date: 1967-04-13
Spud Date: 1967-04-11
Spud Drilling Contractor:
Final Drill Date: 1967-05-11
Well Total Depth: 2958.00 ft
Configuration: Vertical
Latitude: 39.670000
Longitude: -82.330000

For data sources see[1]

Well History

Well Status Well Status Date Comment
Original Spud 1967-04-11
Completed 1967-05-11
Reached Total Depth 1967-05-11
Plugged/Abandoned 2015-12-16
Record Last Modified 2017-08-04

For data sources see[2]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 0 1365 Bbl 205000

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
1985 BELL OIL 2942.00 90.00 365
1986 BELL OIL 960.00 60.00 182
1987 BELL OIL 625.00 92.00 365
1989 BELL OIL 1000.00 64.00 365
1990 BELL OIL 73.00 61.00 365
1993 BELL OIL 561.00 13.00 365
1994 BELL OIL 685.00 28.00 365
1995 BELL OIL 100.00 40.00 365
1996 BELL OIL 624.00 39.00 365
1997 BELL OIL 612.00 12.00 365
1998 BELL OIL 1696.00 0.00 365
1999 BELL OIL 1134.00 25.00 365
2000 BELL OIL 319.00 8.00 365
2001 BELL OIL 0.00 0.00 365
2002 BELL OIL 3.00 12.00 365
2003 BELL OIL 0.00 0.00 365
2004 BELL OIL 0.00 0.00 365
2005 BELL OIL 0.00 0.00 365
2006 BELL OIL 0.00 0.00 365
2007 BELL OIL 0.00 0.00 365
2008 BELL OIL 0.00 0.00 365
2009 BELL OIL 0.00 0.00 365
2010 BELL OIL 0.00 0.00 365
2011 BELL OIL 0.00 0.00 365
2012 BELL OIL 0.00 0.00 366
2013 BELL OIL 0.00 0.00 365
2014 BELL OIL 0.00 0.00 365
2015 BELL OIL 0.00 0.00 0

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
1985 BELL OIL Brine 85 365
1986 BELL OIL Brine 30 182
1987 BELL OIL Brine 50 365
1989 BELL OIL Brine 51 365
1990 BELL OIL Brine 0 365
1993 BELL OIL Brine 0 365
1994 BELL OIL Brine 0 365
1995 BELL OIL Brine 40 365
1996 BELL OIL Brine 0 365
1997 BELL OIL Brine 0 365
1998 BELL OIL Brine 0 365
1999 BELL OIL Brine 0 365
2000 BELL OIL Brine 0 365
2001 BELL OIL Brine 0 365
2002 BELL OIL Brine 0 365
2003 BELL OIL Brine 0 365
2004 BELL OIL Brine 0 365
2005 BELL OIL Brine 0 365
2006 BELL OIL Brine 0 365
2007 BELL OIL Brine 0 365
2008 BELL OIL Brine 0 365
2009 BELL OIL Brine 0 365
2010 BELL OIL Brine 0 365
2011 BELL OIL Brine 0 365
2012 BELL OIL Brine 0 366
2013 BELL OIL Brine 0 365
2014 BELL OIL Brine 0 365
2015 BELL OIL Brine 0 0

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1563549192 2016-1-21 0:00: FR No Violations 1.00
-2132690394 2015-12-10 0:00 PB No Violations 8.00
-816237369 2016-10-28 0:00 FR No Violations 1.00
0816237369 2016-10-28 Final Restoration No Violations The final restoration meets 1509.072B.
1449098486 2015-12-02 Plug / Plug Back No Violations My inspection today is to witness Bell Oil plug a cable tool drilled well. This well is equipped with 8.625 inch surface casing and 4.5 production casing. Bell oil is also the owner of this well. There is 6 tons of prepared clay on location. They shoveled 3 tons of clay for the bottom plug. The rig pulled up on the 4.5 inch casing so they could remove the clamp and the 4.5 inch casing broke. It is estimated to be about 3 joints down where the break is. They pulled out the 4.5 inch casing to determine where the break is. A collar separated 3 joints down. Then they will go down hole, in the morning, with their dye tool to grip the top of the 4.5 inch casing.
1449522934 2015-12-07 Plug / Plug Back No Violations My inspection today is to witness Bell Oil continue plugging their Clinton well. The 4.5 inch casing parted at the coupling last Wednesday. Bell Oil made a threaded nipple to put on the end of a joint in an attempt to thread the nipple on to the remaining 4.5 inch casing still in the hole. I witnessed Bell Oil put the nipple on the joint and begin to trip the 4.5 inch casing back in the whole until they have reached the top of the parted 4.5 inch casing. Bell Oil successfully attached to the parted 4.5 inch casing. Then they lowered tools down to 2,000 ft. where telegraph was received and the 4.5 inch casing was ripped.
1449606054 2015-12-08 Plug / Plug Back No Violations During the time of my inspection Bell Oil pulled a joint to make sure the 4.5 inch casing was free from where they ripped yesterday. The first joint pulled really hard. There was a cave in on the 4.5 inch casing so Bell Oil slowly pulled 4 more joints until the pipe was free. They started to shovel clay and oil came to surface. So they waited and tried to wash more clay down hole. The oil came up again. So we will resume again tomorrow and attempt to finish plugging the well.
1449776857 2015-12-09 Plug / Plug Back No Violations During the time of my inspection today I witnessed Bell Oil shovel the remaining 3 tons of clay down the 4.5 inch casing to finish off the bottom plug. After finishing the bottom part of the plug the 4.5 inch casing was pulled.
1450207141 2015-12-15 Plug / Plug Back No Violations During the time of my inspection Bell Oil removed 4 joints of the 8.625 inch surface casing. That was all they could recover the 5th joint parted. When the 8.625 inch casing was pulled and parted it pinched off the pipe at the part. Bell Oil had a tool that they ran down hole to open up the pinched section that was parted to keep from creating an unwanted bridge within the remaining 8.625 inch casing. Continuing on Bell Oil shoveled 4 tons of clay. They let that settle and shovel more clay in tomorrow to bring the clay to surface.
1450283120 2015-12-16 Plug / Plug Back No Violations During the time of my inspection I witnessed Bell Oil cut the conductor casing down 4 feet under surface grade. Bell Oil shoveled 1 ton of clay to get the clay to surface and flush with the top of the conductor. A steel plate with the permit number was place on top of the conductor. The top of the well was buried leaving the top of the conductor 4 feet underground.
1563549192 2016-01-21 Final Restoration No Violations My inspection today is to check on the final restoration of the well site. This well was plugged December 16th, 2015. There is still a 100 bbl. tank on location that was used in the plugging of the well. This site has not met final restoration requirements. I will return on a later date to check final restoration status.
2132690394 2015-12-10 Plug / Plug Back No Violations During my inspection today Bell oil was on location with an additional 6 tons of clay. Bell oil lowered a 7 inch concrete bridge plug into the base of the 8.625 inch surface casing seat. Then 6 tons of clay were shoveled into the well.

For data sources see[8]