34-151-25806

Well Details

Well ID: 34-151-25806
Loading map...
Country: United States
State: Ohio
County: Stark
Municipality: Washington Township
Operator Name: ENERVEST OPERATING LLC
Well Pad ID:
Farm/Lease Name: MASON UNIT
License Status: Producing
License Date: 2012-07-20
Spud Date: 2012-09-20
Spud Drilling Contractor:
Final Drill Date: 2012-09-27
Well Total Depth: 5262.00 ft
Configuration: Vertical
Latitude: 40.870000
Longitude: -81.170000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2012-07-20 Proposed Formations:OHIO SHALE THRU CLINTON, Issued Date:7/20/2012, Expired Date:7/20/2014 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2012-09-27
Completion Report Received 2012-11-29
Construction Permit Expires 2014-07-20
Record Last Modified 2017-02-15

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2012-12-12 5036 5110 75
5036 5110 75
5036 5110 75

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2012-10-11 H2O 0 4243 Bbl 0 Superior Well Services

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2012 ENERVEST OPERATING LLC 3085.00 662.00 366
2013 ENERVEST OPERATING LLC 12157.00 1826.00 365
2014 ENERVEST OPERATING LLC 6156.00 902.00 365
2015 ENERVEST OPERATING LLC 4594.00 727.00 365
2016 ENERVEST OPERATING LLC 3936.00 312.00 366
2017 ENERVEST OPERATING LLC 4340.00 207.00 365
2018 ENERVEST OPERATING LLC 2854.00 242.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2012 ENERVEST OPERATING LLC Brine 0 366
2013 ENERVEST OPERATING LLC Brine 988 365
2014 ENERVEST OPERATING LLC Brine 312 365
2015 ENERVEST OPERATING LLC Brine 283 365
2016 ENERVEST OPERATING LLC Brine 9 366
2017 ENERVEST OPERATING LLC Brine 0 365
2018 ENERVEST OPERATING LLC Brine 5 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1508909735a 2012-9-21 0:00: DD No Violations 3.00
0071651266 2018-11-21 Preliminary Restoration No Violations My inspection found the pits have been filled and the land restored around the well and tank battery locations. There are no signs of active erosion at either location. The preliminary restoration is compliant with Ohio Revised Code 1509.072(A). The preliminary restoration is passed. The well is equipped with a pumpjack. The tank battery consists of four steel production tanks, three plastic brine tank, four vertical separator and four meters. The tank battery is shared with wells #151-25807, 25771 and 25858. The well is legibly identified. No compliance issues are cited.
1240155514 2012-09-25 Drill / Deepen / Reopen No Violations Kilbarger #17 rig drilling 7.875 borehole. Current depth is 3,080. Pits are in good working condition and dust suppression is sufficient. Grading site to remove mud.
1348367386 2012-09-22 Drill / Deepen / Reopen No Violations On site for the cementing of surface casing. The 11 borehole was drilled to a depth of 942. Circulation was not established during drilling. 922 of 8.625 casing was set using 400 sacks of cement (100% excess). Universal Well Services ran 60 bbls of fresh water before 30 bbls of gel and flake. Cement had 3/4 pound of flake added. No cement returns. Will run cement bond log tomorrow morning.
1348425094 2012-09-23 Drill / Deepen / Reopen No Violations Cement was not circulated to surface while setting the surface casing string. Appalachian Well Surveys ran cement bond log and found top of cement was at 196 KB. Top of cement inside the 8.625 casing tagged at 890. Kilbarger drilling crew inserted 189 of one inch line down the back side for grouting. Universal Well Services established circulation and grouted the surface casing annular space using 100 sacks of cement. Good cement returns to surface but top of cement fall back. Kilbarger will tag top of cement after 4 hours and top off as needed.
1508909735 2012-09-21 Drill / Deepen / Reopen No Violations I arrived on site to inspect the cementing of conductor casing. The conductor hole was drilled to a total depth of 191 using a 17.5 bit. A total of 179 of 11.75 casing was set (KB). Circulation was established and 300 sacks of cement were pumped downhole with 24 bbl of returns.
2139327151 2012-11-20 Preliminary Restoration No Violations I inspected the Mason 4 (34151258060000) well site on November 20, 2012. My inspection found the access road is in good condition and graveled to the well site. The site has been rough graded and preliminary restoration is due by April 2013. The pits have been solidified and filled.
71651266 2018-11-21 0:00 PL No Violations 0.50

For data sources see[9]