34-151-25840

Well Details

Well ID: 34-151-25840
Loading map...
Country: United States
State: Ohio
County: Stark
Municipality: Marlboro Township
Operator Name: ENERVEST OPERATING LLC
Well Pad ID:
Farm/Lease Name: TESSMER H & M UNIT
License Status: Producing
License Date: 2013-08-08
Spud Date: 2014-09-17
Spud Drilling Contractor: ADVENT DRLG
Final Drill Date: 2014-09-28
Well Total Depth: 7397.00 ft
Configuration: Vertical
Latitude: 40.950000
Longitude: -81.280000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2013-08-08 Proposed Formations:QUEENSTON THRU TREMPEALEAU, Issued Date:8/8/2013, Expired Date:8/8/2015 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2014-09-28
Completion Report Received 2015-03-30
Construction Permit Expires 2015-08-08
Record Last Modified 2017-10-23

For data sources see[2]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2014 ENERVEST OPERATING LLC 3480.00 601.00 66
2015 ENERVEST OPERATING LLC 10054.00 2295.00 365
2016 ENERVEST OPERATING LLC 6413.00 1358.00 366
2017 ENERVEST OPERATING LLC 7167.00 1131.00 365
2018 ENERVEST OPERATING LLC 6958.00 946.00 365

For data sources see[3] [4]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2014 ENERVEST OPERATING LLC Brine 1652 66
2015 ENERVEST OPERATING LLC Brine 2765 365
2016 ENERVEST OPERATING LLC Brine 1334 366
2017 ENERVEST OPERATING LLC Brine 1741 365
2018 ENERVEST OPERATING LLC Brine 1420 365

For data sources see[5] [6]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-741989207 2014-9-25 0:00: DD No Violations 1.50
-850203537 2019-6-3 0:00:0 PL No Violations 0.50
0006940879 2014-09-15 Surface Facility Construction No Violations I was on location to have a pre spud meeting with Advent for the drilling of this well and to check on the status of drilling the pits. The pits have been dug into a solid clay soil with no water infiltration. They will finish digging their working pits and line them before mixing their water based mud to drill the 17.5 diameter surface hole.
0741989207 2014-09-25 Drill / Deepen / Reopen No Violations I was on location to check the status of Advent drilling the well. Currently the depth of the wellbore is 4797 and the rig is currently tripping out of the hole to make a bit change. The pits are in good condition and are not full of fluid. The pits are fenced by orange fencing and there are no violations at this time.
1411404131 2014-09-22 Drill / Deepen / Reopen No Violations I was on location to witness the draining and relining of the working and blow pits for this well. An excavator was removing the solid cement chunks from the working pit and caused a rip in the liner to occur. While moving the cement chunks from the working pit to the blow pit the chunks, when placed in the pit, ripped the liner on the blow pit. The working pit was pumped out, excavated dry and relined. The freshwater mud in the blow pit was tested for chlorides using Hach Quantabs and had 289ppm chlorides in it. The mud and fluid was pumped from the blow pit to the working pit and a load of dust was brought in to solidify the residual mud in the blow put. Once the dust was in place the blow pit was relined and drilling continued. There are no violations at this time.
1572955975 2014-09-29 Drill / Deepen / Reopen No Violations I was on location to check the status of Advent drilling this well. The rig has reached a total depth of 7397 and is currently tripping out of the hole. The well will be open hole logged using Weatherford and the decision to case or plug the hole will be made following the logging. There are no violations at this time.
1820422823 2014-12-05 Preliminary Restoration No Violations I was on location to check the status of preliminary restoration for this well. The dirt work for the location has been completed at this time, but has not been seeded. The dikes around the separator and the tank battery is complete at this time. Preliminary restoration will be passed when the location has been seeded and vegetation established.
1944906505 2014-11-04 Preliminary Restoration No Violations I was on location to check the status of preliminary restoration for this well. Currently a Jerrys bulldozer and backhoe are on location spreading topsoil for restoration. The pumpjack is on the well and is currently producing. The pumpjack and wellhead have all necessary gauges and valves. The tank battery has been installed with a dike and includes a horizontal separator, two 210bbl production tanks and a 50bbl poly brine tank. I will follow back and pass preliminary restoration when dirt work is complete and vegetation has been established.
6940879 2014-9-15 0:00: SC No Violations 2.00

For data sources see[7]

References