34-155-23487

Well Details

Well ID: 34-155-23487
Loading map...
Country: United States
State: Ohio
County: <County>
Municipality:
Operator Name: PIN OAK ENERGY PARTNERS LLC
Well Pad ID:
Farm/Lease Name: SPAIN
License Status: Producing
License Date: 1992-09-22
Spud Date: 1992-11-28
Spud Drilling Contractor: [[JL COATS [COATS-GOFF]]]
Final Drill Date: 1992-12-09
Well Total Depth: 5079.00 ft
Configuration: Directional
Latitude: 41.250000
Longitude: -80.820000

For data sources see[1]

Well History

Well Status Well Status Date Comment
CO 1992-09-22 2816 P & S ENERGY INC GeoDate 9/22/92
Oil and Gas 1992-09-22 Issued Date 9/22/92 Expired Date 9/22/93 Acres 0041530 Tool Type RTAF Proposed Formation CLINTON Proposed Depth 05079 Proposed Drill Depth 05079
Original Spud 1992-11-28 CHG. FTG, XY 2-6-93
Completed 1992-12-09 CHG. FTG, XY 2-6-93
Reached Total Depth 1992-12-09 CHG. FTG, XY 2-6-93
Completion Report Received 1993-05-05 CHG. FTG, XY 2-6-93
Construction Permit Expires 1993-09-22 CHG. FTG, XY 2-6-93
Change of Owner 2019-02-26 Operator changed from 2816, P & S ENERGY INC to 9722, PIN OAK ENERGY PARTNERS LLC
Record Last Modified 2019-02-26 CHG. FTG, XY 2-6-93

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
1997-06-29 4824 4960 0
4824 4960 0
2006-09-11 4850 4914 77
4850 4914 77
4824 4960 0

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 0 122000 Gal 80000 FRAC W/122M GAL H20 & 80M# SAND

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
1992 P & S ENERGY INC 0.00 0.00 365
1993 P & S ENERGY INC 41738.00 285.00 227
1994 P & S ENERGY INC 55439.00 192.00 365
1995 P & S ENERGY INC 39224.00 0.00 365
1996 P & S ENERGY INC 33497.00 13.00 365
1997 P & S ENERGY INC 27500.00 58.00 365
1998 P & S ENERGY INC 25902.00 0.00 365
1999 P & S ENERGY INC 23114.00 0.00 365
2000 P & S ENERGY INC 18911.00 61.00 365
2001 P & S ENERGY INC 16630.00 0.00 365
2002 P & S ENERGY INC 15357.00 0.00 365
2003 P & S ENERGY INC 15795.00 0.00 365
2004 P & S ENERGY INC 12453.00 49.00 365
2005 P & S ENERGY INC 10912.00 0.00 365
2006 P & S ENERGY INC 9387.00 0.00 365
2007 P & S ENERGY INC 10257.00 0.00 365
2008 P & S ENERGY INC 9861.00 0.00 365
2009 P & S ENERGY INC 9518.00 0.00 365
2010 P & S ENERGY INC 10596.00 0.00 365
2011 P & S ENERGY INC 9275.00 0.00 365
2012 P & S ENERGY INC 10515.00 0.00 366
2013 P & S ENERGY INC 9896.00 0.00 365
2014 P & S ENERGY INC 8846.00 0.00 365
2015 P & S ENERGY INC 8250.00 0.00 365
2016 P & S ENERGY INC 6891.00 49.00 365
2017 P & S ENERGY INC 6890.00 0.00 365
2018 P & S ENERGY INC 7315.00 0.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
1992 P & S ENERGY INC Brine 900 365
1993 P & S ENERGY INC Brine 13000 227
1994 P & S ENERGY INC Brine 70 365
1995 P & S ENERGY INC Brine 63 365
1996 P & S ENERGY INC Brine 0 365
1997 P & S ENERGY INC Brine 105 365
1998 P & S ENERGY INC Brine 0 365
1999 P & S ENERGY INC Brine 0 365
2000 P & S ENERGY INC Brine 0 365
2001 P & S ENERGY INC Brine 0 365
2002 P & S ENERGY INC Brine 0 365
2003 P & S ENERGY INC Brine 0 365
2004 P & S ENERGY INC Brine 40 365
2005 P & S ENERGY INC Brine 0 365
2006 P & S ENERGY INC Brine 0 365
2007 P & S ENERGY INC Brine 0 365
2008 P & S ENERGY INC Brine 0 365
2009 P & S ENERGY INC Brine 0 365
2010 P & S ENERGY INC Brine 0 365
2011 P & S ENERGY INC Brine 52 365
2012 P & S ENERGY INC Brine 0 366
2013 P & S ENERGY INC Brine 69 365
2014 P & S ENERGY INC Brine 21 365
2015 P & S ENERGY INC Brine 0 365
2016 P & S ENERGY INC Brine 0 365
2017 P & S ENERGY INC Brine 0 365
2018 P & S ENERGY INC Brine 0 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1421372677 2014-9-23 0:00: UP No Violations 0.50
0909200872 2004-02-25 Preliminary Restoration No Violations Restoration approved .
1421372677 2014-09-23 UrbanProduction Wells No Violations I was on location for a status check. During my inspection, I found the well in production equipped with a plunger lift unit. The tank battery consisted of two, 210 barrel and a 100 production tanks, a 50 barrel brine tank, and three separators. A dike surrounded the production equipment. Identification signs were posted at the well and tank battery. Bull plugs were installed on the load lines. A locked, chain link fence surrounded the production equipment. The lease road was in stable condition. The well was placed into production prior to House Bill 278.
1485781708 2017-01-23 UrbanProduction Wells No Violations

-3580, and 2-3324. The access road is shared with permit 2-3550.

The equipment on site consists of:



1687086070 2020-9-10 0:00: UP No Violations
909200872 2004-2-25 0:00: PL No Violations

For data sources see[9]