34-163-20337

Well Details

Well ID: 34-163-20337
Loading map...
Country: United States
State: Ohio
County: Vinton
Municipality: Knox Township
Operator Name: CLEARWATER OPERATIONS LLC
Well Pad ID:
Farm/Lease Name: TEDRICK (SWIW #12)
License Status: Active Injection
License Date: 2011-08-30
Spud Date: 1975-11-01
Spud Drilling Contractor: GRIM DRILLING
Final Drill Date: 1967-06-16
Well Total Depth: 1271.00 ft
Configuration: Vertical
Latitude: 39.220000
Longitude: -82.310000

For data sources see[1]

Well History

Well Status Well Status Date Comment
CO 1801-01-02 566 GRIM PAUL A
Completed 1967-06-16 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Reached Total Depth 1967-06-16 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Original Spud 1976-06-06 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Completion Report Received 1981-04-24 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Annulus Pressure Monitoring Approved 1986-07-22 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Change of Owner 2001-11-21 Operator changed from 566, GRIM PAUL A to 5755, CHIEFTAIN ENERGY CORP.
Change of Owner 2011-04-29 Operator changed from 5755, CHIEFTAIN ENERGY CORP to 6227, HOUGHTON INVESTMENTS, L.L.C.
APP 2011-08-30 Proposed Formations:OHIO SHALE THRU BASS ISLAND, Issued Date:8/30/2011, Expired Date:8/29/2013 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:SWD, Proposed Well Class:SWIW
First Injection 2012-01-01 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Construction Permit Expires 2013-08-29 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Last Compliance Report 2014-08-04 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET
Change of Owner 2016-08-01 Operator changed from 6227, HOUGHTON INVESTMENTS LLC to 7077, D T ATHA INC
Change of Owner 2018-07-31 Operator changed from 7077, RIVER VALLEY ENERGY INC to 10184, CLEARWATER OPERATIONS LLC
Record Last Modified 2018-07-31 CHG. OWN. OP. WELL #, CONV. TO WTRFLOOD 10-8-75 - DEEPEN AND CONVERT TO SWIW - 8/30/2011 -TET

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2000-04-11 1232 1238 7
1232 1238 7
1232 1238 7

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 0 977 Bbl 18500
0 0 0 FRAC WITH 977 BBLS FRESH H2O, 38,900 LBS 20/40 SAND AND 100 GALS MUD ACID
ACID 0 100 Gal 0 MUD

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
1984 GRIM PAUL A 0.00 276.00 365
1985 GRIM PAUL A 0.00 418.00 365
1986 GRIM PAUL A 0.00 293.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
1984 GRIM PAUL A Brine 0 365
1985 GRIM PAUL A Brine 1401 365
1986 GRIM PAUL A Brine 1953 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1038682241 2004-1-15 0:00: ER No Violations
-1042540026 2014-4-28 0:00: SW No Violations 2.50
-1058884883 2009-9-1 0:00:0 ER No Violations
-1063031098 2010-10-21 0:00 ER No Violations 1.00
-1080793138 2004-6-10 0:00: ER No Violations
-1122870582 2017-4-10 0:00: SW No Violations 1.00
-1149464795 2013-9-12 0:00: SW No Violations 2.00
-1162154503 2019-6-19 0:00: SW No Violations 2.00
-1174726617 2012-4-26 0:00: SW No Violations
-1181857479 2003-10-30 0:00 ER No Violations
-1193392527 2012-4-26 0:00: SW No Violations 2.50
-1195009222 2009-6-30 0:00: ER No Violations
-1196714965 2014-3-10 0:00: SW No Violations 3.00
-1222876937 2009-9-15 0:00: ER No Violations
-1232474814 2012-8-2 0:00:0 SW No Violations 2.00
-1249453608 2017-2-27 0:00: SW No Violations 1.00
-1288387450 2008-5-27 0:00: ER No Violations
-131909280 2015-3-12 0:00: SW No Violations 2.00
-1333763465 2014-6-4 0:00:0 SW No Violations 11.50
-1338083959 2018-7-3 0:00:0 SW No Violations 1.50
-1364616455 2014-5-21 0:00: SW No Violations 3.00
-1383799929 2008-2-21 0:00: ER No Violations
-1422765526 2003-6-3 0:00:0 ER No Violations
-1424323782 2018-1-3 0:00:0 SW No Violations 1.00
-1452296759 2009-9-1 0:00:0 ER No Violations
-1479381009 2014-7-3 0:00:0 SC No Violations 1.50
-1512530707 2011-3-30 0:00: ER No Violations
-1523123372 2016-7-29 0:00: SW No Violations 1.00
-1579783816 2011-11-18 0:00 SW No Violations
-1585943499 2016-6-9 0:00:0 SW No Violations 1.00
-1667154934 2008-9-11 0:00: ER No Violations
-167633997 2005-6-8 0:00:0 ER No Violations
-1738176433 2019-8-1 0:00:0 SW No Violations 5.90
-1741013806 2009-9-4 0:00:0 ER No Violations
-1794875532 2009-9-23 0:00: PW No Violations
-1888683854 2014-7-23 0:00: SW No Violations 2.00
-1935888185 2013-7-17 0:00: SW No Violations 2.00
-1951319815 2009-12-9 0:00: ER No Violations
-2014838629 2012-8-16 0:00: SW No Violations 1.00
-2015614522 2011-11-7 0:00: AM No Violations
-2092717665 2016-10-12 0:00 SW No Violations 1.00
-2094033275 2013-7-29 0:00: SW No Violations 2.00
-2106705098 2006-7-12 0:00: ER No Violations
-2147145560 2003-4-21 0:00: ER No Violations
-259118605 2020-9-1 0:00:0 SW No Violations 1.50
-293615225 2010-1-21 0:00: ER No Violations
-336553682 2014-6-25 0:00: SC No Violations 2.00
-366171833 2014-3-28 0:00: AM No Violations
-375042358 2009-9-1 0:00:0 ER No Violations
-384310658 2019-1-10 0:00: SW No Violations 3.00
-451787081 2013-9-6 0:00:0 SW No Violations 3.00
-469254951 2009-6-15 0:00: ER No Violations
-477401197 2013-8-5 0:00:0 SW No Violations 1.00
-501981403 2012-6-14 0:00: ER No Violations 1.00
-609064011 2017-7-14 0:00: SW No Violations 1.00
-625584207 2014-4-1 0:00:0 SW No Violations 0.70
-66776984 2018-10-2 0:00: SW No Violations 1.20
-667952648 2005-10-20 0:00 ER No Violations
-680293888 2007-1-18 0:00: ER No Violations
-786874872 2007-7-3 0:00:0 ER No Violations
-806132834 2010-9-22 0:00: ER No Violations 1.00
-93166846 2014-6-19 0:00: SW No Violations 2.50
-950959704 2013-9-12 0:00: SW No Violations 2.50
-977940882 2018-5-17 0:00: SW No Violations 1.50
-986000932 2015-10-19 0:00 SW No Violations 1.00
-988439737 2010-9-17 0:00: ER No Violations
-989541874 2007-4-19 0:00: ER No Violations
-992851747 2013-1-24 0:00: SW No Violations 1.50
0000001103 2002-06-05 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance. Done a mini test on well, well did not pass test, all other violations not corrected. Done several test on well, always lost approx. 10 lbs. In 5 minutes. Company is planning on retesting well before I show up. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
0000UIC195 1987-05-08 Enhanced Recovery Project No Violations 1501:9-3-07 (E)
0000UIC294 1986-12-09 Enhanced Recovery Project No Violations 1509.072 (A)
0000UIC331 1986-12-09 Enhanced Recovery Project No Violations 1509.22(A)(B)(C)
0000UIC332 1986-12-09 Enhanced Recovery Project No Violations 1501:9-3-04 (A)
0000UIC333 1986-12-09 Enhanced Recovery Project No Violations 1501:9-3-05 (B (7)
0000UIC600 1989-01-17 Enhanced Recovery Project No Violations 1509.22 (A)(B)(C) Storage & Disposal
0000UIC601 1989-01-17 Enhanced Recovery Project No Violations 1501:9-5-06 Prevent cont. & Poll
0000UIC602 1989-01-17 Enhanced Recovery Project No Violations 1501:9-5-09 (B)(7) const.facility
0000UIC665 1989-05-02 Enhanced Recovery Project No Violations ACTION noncom 1509.22 (A)(1)(2) Storage & Disposal
0000UIC666 1989-05-02 Enhanced Recovery Project No Violations ACTION noncom 1501;9-5-06 Poll. & contaminatio
0000UIC667 1989-05-02 Enhanced Recovery Project No Violations ACTION noncom 1501:9-5-09 (A) (6) constr. & conv. swiw
0000UIC706 1989-06-13 Enhanced Recovery Project No Violations 1501:9-5-10 (E) Delinquent Qtly Rpt.
0000UIC740 1989-08-01 Enhanced Recovery Project No Violations 1509:22 (1)(2) storage & disposal
0000UIC741 1989-08-01 Enhanced Recovery Project No Violations 1501:9-3-04 (A) prevent poll & cont.
0001269i10 2001-01-17 Enhanced Recovery Project Violations Noted An inspection revealed that there is no ID at the well or at the storage tank . Unable to check the annulus pressure on well , unable to open 1/4 valve. REQUEST THE COMPANY NOTIFY THE INSPECTOR FOR MONTHLY M.I.T. TEST.
000UIC1257 1992-05-05 Enhanced Recovery Project No Violations 1501: 9-5-7 (E) (F) QUARTERLY REPORTS
0015489688 2009-06-29 Enhanced Recovery Project No Violations A follow-up inspection revealed that cleanup has been performed. Lime, seed and mulch observed around the location. The contaminated soil(s) at top of the hill will need to be removed from the location.
0066776984 2018-10-02 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure and annulus pressure. The containment dike is free of fluids. Identification is posted at the well and facility.
0074219010 2013-11-06 Salt Water Injection Well No Violations Knox service rig currently set up on well. Pulled packer and tubing from well (1205). Rig up tubing with bit and power swivel with mud pump. Excavated a pit and lined the pit with plastic. Shale has caved in . Clean out well bore. Currently drilling out the shale at 1900 feet. Plan to drill back to the Bass Island formation.
0093166846 2014-06-19 Salt Water Injection Well No Violations The surface facility, including the containment dike, tanks and filter has been disassembled and moved to the top of the hill near the existing production tanks and lease road entrance. The containment dike site has been reclaimed and graded. The injection line will need to be extended to the new surface facility. The injection tubing master valve is closed.
01269i1019 2002-05-06 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, company has not complied with NOV, Doug Kitchen has been notified of this violation in person, written and by phone. Company has not done a M.I.T. test as of date.
01269i1313 2002-08-20 Enhanced Recovery Project No Violations Follow-up on NOV, No-Complinace, M.I.T. was doneonce on well and failed, company has not prepared well for testing. There is ID at the well head and No ID at the storage tank. Request a Chiefs Order be issued to plug well.
0131909280 2015-03-12 Salt Water Injection Well No Violations Compliance notice follow up. Witnessed monthly mini test at 200 psi for 15 minutes with no loss in pressure.
0162022739 2013-03-07 Salt Water Injection Well No Violations Containment dike is free of brine. Submersible injection pump located in the 210 barrel fiberglass tank has been replaced. Dike sump pump is plumbed into the 210 barrel steel tank with-in dike.
0167633997 2005-06-08 Enhanced Recovery Project No Violations No violations.
0279693739 2009-06-11 Enhanced Recovery Project Violations Noted An inspection revealed old oil, bare area(s) and stressed vegetation. Beginning at the well location oil and bare area measured 10 (width) and 30 (length) before extending over the hill. Stressed vegetation/thick brush along the edge of hill showed signs of pressure release as, old oil was observed along the tops. Following the path of stressed vegetation and bare area(s) lead directly to a nerby creek. At this location, the area consisted of bare ground, stressed vegetation and oil stained ground. Walked approximately 1500 of creek downstream and observed no crude oil. The total length of impact below hill was approximately 170 and width ranging from 15-50. Two sources for the release were found to be 1/4 valve with gauge broke off on the injection side of well. Lastly, a 2 black platic line from storage tank location to injection side may have leaked. Approximately 5 feet behind well next to line oil was observed. Spoke with Paul Grims employee, Mr. Paul Thompson whom states that this incident occurred last month. He states that the line broke and someone broke off gauge. Mr. Thompson was instructed to remove all contaminated material. Due to the terrain over the hillside, to include several trees and slope, potential erosion problems may occur from the operation of heavy equipment. Therefore, Bioremediation was suggested for this area. The estimated amount of oil released is unknown at this time, as rainfall events have occurred over the past month. Below hillside, the area consisted of mostly bare area with a few oil stains on ground surface. Unable to test injection side at this time. No pressure observed on the annulus.
0293615225 2010-01-21 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The dike containing a horizontal tank has reached maximum fluid capacity. The observed fluid consists of oil sheen and brine. High Range Quantabs revealed 7 units. A dike has not been built for the 210 bbl tank located inside Paul Grims shop. Called Mr. Doug Kitchen at 12:57pm and instructed him to remove fluid inside the dike by 1/19/2010.
0314287443 2012-08-28 Salt Water Injection Well No Violations No violations were found at the time of inspection.
0325824842 2002-03-04 Enhanced Recovery Project Violations Noted FOLLOW UP TO NOV # 1269i842 An inspection of the well revealed No ID at the well or storage tanks, pressure on the injection and annulus sides of well still 0 after the last 3 inspections. Need ID at the well and tanks, and a M.I.T. test done on well. If test is not preformed by co 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
0336553682 2014-06-25 Surface Facility Construction No Violations Reviewed the new containment dike dimensions with Lee Atha. Proposed containment dike is 40 by 30 by 3 with two 210 barrel tanks. Dike capacity with tanks is 559.423 barrels.
0354308989 2009-10-15 Administrative Inspection No Violations Made attempt to visit with Mr. Paul Grim at his shop. He was not available. Informed two employees, Mr. Paul Thompson and Mr. Burt Grim that a dike will be required for the 210 bbl tank inside Pauls shop. More lime, seed and fertilizer needed at the shop for Phillips and Perry tank locations. The chloride levels outside and inside the dike are high. An attempt to also contact Mr. Doug Kitchen on his cell phone at 3:00 pm was not successful. No answer and unable to leave voice mail message.
0366171833 2014-03-28 Administrative Inspection No Violations 3-28-14 at 10:35 am Follow up phone call with Lee Atha. We discussed the remediation plan for the well and the extension request that need submitted.
0375042358 2009-09-01 Enhanced Recovery Project Violations Noted An inspection was conducted with Mr. Jeff Fry, UIC Field Supervisor, West Region Supervisor. During the inspection, it was noted that fluid was being discharged from a 4 PVC pipe directly onto concrete slab and draining down slope into an earthen pit containing 1 horizontal tank approx 150 bbl. At location, salt crystals were observed on concrete. Another section of PVC pipe was observed in pit, but not connected to discharge pipe. The pit was found to contain 3/4 of oil on surface and measured 41 (length) x 16 and 22 (widths). High Range Quantabs utilized at discharge point exceeded 6545 ppm(mg/L) Cl-. A 4 oz container was utilized to measure discharge rate. The container was filled in 10 seconds. The storage tank for the ERP consists of a 200 bbl tank placed on concrete slab inside Mr. Paul Grims shop. Currently, no containment exists for the tank. At this location, the pump was found to be leaking continuously. The fluid from this leak then enters two floor drains that tie into the PVC pipe outside shop. Report continued on next page.
0376884252 2012-05-30 Salt Water Injection Well No Violations Witnessed injection line test.
0384310658 2019-01-10 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pump, injection pressure and annulus pressure. Identification is posted. The containment dike is free of fluids.
0396594231 2014-08-20 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection line, annulus pressure and injection pressure. Identification posted on tank.
0430645978 2016-02-23 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection line, injection pressure and annulus pressure. Identification posted on the tank and well. Containment dike is free of fluids.
0451787081 2013-09-06 Salt Water Injection Well No Violations Witnessed acid stimulation of the well. Producers Service pump truck. Pumped 300 gallons paraffin inhibitor and 300 gallons 15 % HCL. Currently installing a new steel injection line from the containment dike to the injection tubing.
0469254951 2009-06-15 Enhanced Recovery Project No Violations Paul Grims employee, Mr. Paul Thompson, unlocked the shop so that inspection of 210 bbl storage tank (inside shop on concrete floor) could be performed. Old oil observed on concrete floor from leaking pump. Mulch applied to location. The tank does not contain a dike. Mr. Thompson is repairing the pump. An inspection of the well site and related cleanup was also performed with Mr. Thompson. Mr. Thompson was given instructions pertaining to the required cleanup.
0477401197 2013-08-05 Salt Water Injection Well No Violations Soil on dike wall and all surrounding bare areas have seed and straw applied. Vegetative growth has not established.
0501981403 2012-06-14 Enhanced Recovery Project No Violations Test port on injection line needs moved from filter housing to the well head. Talked to Mr. Lee Atha about this via telephone. Good identification was observed at the tank battery.
0539748129 2019-04-29 Salt Water Injection Well Violations Noted Our records indicate that the Division has not received the Salt Water Injection Well Annual Report (Form 204) that was due on April 15th for 2018, Please submit the Form 204 to the Division by 5/29/2019.
0571989164 2014-07-01 Surface Facility Construction No Violations 30 mill containment liner is on site. Excavation equipment is on site. Injection line is being extended to the new surface facility.
0583729826 2015-03-11 Salt Water Injection Well Violations Noted Inspected the containment dike, tank, flow meter, injection pressure and annulus pressure. The containment dike was free of water. The annulus pressure had a slight vacuum then zero pressure. I called and told Lee Atha that the annulus will need to be tested. The test is scheduled for 3-12-15.
0609064011 2017-07-14 Salt Water Injection Well No Violations Quarterly UIC inspection. The annulus pressure was 3 PSI, the injection tubing was 24 PSI. Legible identification was posted. No violations noted.
0625584207 2014-04-01 Salt Water Injection Well No Violations Compliance Notice # 1196714965 Follow-up. Injection tubing is stacked at the well site. The wellhead is laying on top of the tubing. The production casing is equipped with a swedge and a valve (valve is closed). The injection line from the containment dike has a closed valve and is not connected to the well. Well is incapable of injecting fluids. The containment dike is not liquid tight due to a slip down slope from the dike.
0667952648 2005-10-20 Enhanced Recovery Project Violations Noted FAILURE TO SUBMIT ANNUAL ENHANCED RECOVERY INJECTION WELL REPORT FOR 2004
0677716441 2010-03-17 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The previously noted violations at the well and storage tank locations still exist. The well is not equipped with a 1/4 fitting on injection side, and no pressure on annulus or mini-test performed. Brine and oil still exist at horizontal tank location. Containment for the 210 bbl tank inside Mr. Paul Grims shop has not been constructed.
0680293888 2007-01-18 Enhanced Recovery Project No Violations The previously noted violations have been resolved.
0760489283 2012-01-17 Salt Water Injection Well No Violations Accompanied Jon Scott on inspection of new tank battery liner that is being installed. Also accompanied by Inspector Kip Thompson and company representative Lee Atha.
0772395642 2009-09-01 Enhanced Recovery Project No Violations FOLLOW UP TO NOV # -1452296759 FOLLOW UP TO NOV # -375042358 An inspection was conducted with Mr. Jeff Fry, UIC Field Supervisor, West Region Supervisor. During the inspection, it was noted that fluid was being discharged from a 4 PVC pipe directly onto concrete slab and draining down slope into an earthen pit c
0786874872 2007-07-03 Enhanced Recovery Project No Violations No violations were noted.
0806132834 2010-09-22 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. No action has been taken to construct an earthen or concrete dike for the 210 bbl tank inside Mr. Paul Grims shop. Currently, there is no containment for this tank. On 8/19/2010, a Compliance Agreement with Chieftain Energy required 30 days to peform mini-test and install 1/4 fitting on injection side of well. To date, this test has not been performed.
0827881296 2009-09-01 Enhanced Recovery Project No Violations 9/1/2009 Inspection Continued: Oil and brine were observed on concrete inside shop and found to exit opposite side of discharge area, due to runoff and lack of containment. A bare area was observed along foundation and has traveled to area containing stressed trees and vegetation. A fitting on backside of tank observed leaking. Called Mr. Doug Kitchen at 11:24 am at his office and spoke with secretary whom, stated that he is unavailable due to a meeting. Left message for him to return call asap. Called and left message on Mr. Doug Kitchens cell phone at 11:26 am with more detail. Called Mr. Ron Mcbride, Chieftain Energy Contractor, on his cell phone at 11:30 am. Mr. Paul Grims employees arrived on-site at 11:56 am after being flagged down while driving by location. They were informed of inspection results and state unaware of the problem. Attempt was made to stop leak. Asked how long they would need to perform cleanup, Mr. Paul Thompson states that it could be done by end of the week. No annulus or injection pressure observed, 1/4 valve needed at well and no locks or bull plugs observed.
0919441220 2004-05-19 Enhanced Recovery Project No Violations Follow-up on ORDER, well still incapable of injecting, MIT test has not been done, notified UIC Section in Columbus Office.
0922874988 2013-07-16 Production Wells Violations Noted Compliance notice follow-up, I was accompanied by Andrew Thomas. We found pollution and contamination at the tank battery. A called was made to remove the oil from the dike to Chieftain Energy. The work is scheduled for 07/17/13.
0924145246 2014-05-22 Salt Water Injection Well No Violations Knox Energy is on site using compressed air to attempt to remove a blockage. The blockage is in the injection zone. The well has large volume of fluid and is not letting the well unload. Some success was had by added soap to the water thus lighting the weight of the water. This allowed them to achieve some success, but they have not gotten down to the blockage today.
0945942037 2012-01-17 Surface Facility Construction No Violations Lee Atha is constructing the new dike. 4 of sand has been placed under the 30 mil liner. The liner has been un rolled and has been placed over part of the dike. 4 of sand has been placed on top of the liner where the tanks will be placed. Lee is now going to install the 4 fiberglass tanks and then complete the dike wall. The liner is one piece that will be folded back toward the tanks for the final dike construction. Injection well is not in use during the construction phase of the project.
0950959704 2013-09-12 Salt Water Injection Well No Violations Installed a 2 3/8 8 round upset steel line from the containment dike to the injection well. The line is buried 3 feet deep. Line test passed with no loss in pressure. Inspected the containment dike, tanks, injection line, annulus pressure, and injection pressure. Containment dike is free of water. Accompanied by Inspector Kip Thompson.
0970661669 2011-01-10 Enhanced Recovery Project No Violations Witnessed the welding of 5 sleeve around outside of casing, due to the corrosion of outside section of above ground casing prior to mini-test. The well passed the required mini-test. Recommended to Mr. Ron McBride with Chieftain Energy to replace 1.5 black plastic injection line with more durable line, which is routed from Paul Grims, crosses road and routed over hillside to location. Snow cover at time of inspection.
0977940882 2018-05-17 Salt Water Injection Well No Violations Meet with Lee Atha on location to review the new submersible injection pump that is installed in the 210 bbl tank.
0986000932 2015-10-19 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection line, injection pressure and annulus pressure. Identification posted at the dike and well site. Dike was free of fluids. Annulus pressure had slight vacuum then zero psi.
0988439737 2010-09-17 Enhanced Recovery Project No Violations A follow-up inspection revealed that the 200 bbl horizontal tank location next to Mr. Paul Grims shop has been abandoned. The tank and pit was emptied, tank removed, and location filled in with dirt. An earthen or concrete dike is still required for 200 bbl tank located inside Mr. Grims shop. A 1/4 line routed to this tank on top of concrete floor now contains a separate crack inside the shop from a dozer. Oil was observed on ground surface. Outside the shop, the line is cracked approximately 5 before entering shop. The company has been reminded on several occassions to repair and/or replace. Note: the second 200 bbl horizontal tank located along right side of access road into Mr. Grims shop contains a slow leak at bottom due to corrosion. The tank is equipped with an earthen dike.
0989541874 2007-04-19 Enhanced Recovery Project No Violations No violations were noted.
0992851747 2013-01-24 Salt Water Injection Well No Violations FOLLOW UP TO NOV # 1359044339 An inspection of the tank battery revealed no violations. Good identification was observed at the tank battery and the well. The annulus pressure on the well was 0. I called Mr. Lee Atha at 11:20 on the day of inspection and notified him of the problem and told him that the annulus pressure needs to be above 0 and a mini-test needs to be conducted. I also told him that when he remedies the problem to call me so that I can be present. This message was left on his voicemail. Accompanied on inspection by Justin Smith.
1031033405 2014-07-02 Surface Facility Construction No Violations Containment dike dimensions are 31 feet by 20 feet by 3 feet. A layer of sand was installed then the 30 mill plastic liner and another layer of sand was installed on top of the liner. One 210 barrel fiberglass tank is being installed with-in the containment dike. The injection tubing master valve is shut in due to the facility being moved and the injection line being extended. Collected GPS on the Well, tank, and access road entrance.
1038682241 2004-01-15 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, well still idle and incapable of injecting brine.
1042540026 2014-04-28 Salt Water Injection Well No Violations Compliance Notice # 1196714965 Follow up Inspection. No equipment has been moved on site. Well is equipped with a swedge and a valve. Injection line is not connected to the well. Tubing is stacked on ground at the well site. A tree has fallen across the access road.
1058884883 2009-09-01 Enhanced Recovery Project No Violations FOLLOW UP TO NOV # 1513264415 FOLLOW UP TO NOV # 1253130998 An inspection was conducted with Mr. Jeff Fry, UIC Field Supervisor, West Region Supervisor. During the inspection, it was noted that fluid was being discharged from a 4 PVC pipe directly onto concrete slab and draining down slope into an earthen pit c
1063031098 2010-10-21 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. No action taken to construct earthen or concrete dike for 210 bbl inside Paul Grims shop; perform mini-test; and install 1/4 injection fitting. A section of 1.25 black plastic line inside the shop and routed from a 100 bbl Phillips tank to 210 bbl tank has leaked oil onto concrete floor. A backhoe previously parked inside shop for oil spill cleanup procedures drove over the line. The valve at 100 bbl remains closed, but residual oil has flowed into floor drain and discharged outside via 4 PVC pipe onto a concrete slab. This location contains an old pump no longer used for facility. Note: same location for discharge from leaking pump (active) inside shop in 2009. The 200 bbl horizontal tank below this location has been removed and area remediated. Vegetative growth now observed.
1080793138 2004-06-10 Enhanced Recovery Project No Violations Non-compliance, met with JoeHoerst, Dave Hodges, and Doug Kitchen and his attorney to review violations at well site.
1087987045 2004-06-21 Enhanced Recovery Project No Violations Follow-up In-Compliance, done a MIT test, well passed test.
1097237954 2004-09-28 Enhanced Recovery Project No Violations Met with Doug Kitchen and Joe Hoerst, Doug said work was not done.
1100191631 2013-01-25 Enhanced Recovery Project No Violations I accompanied Andy Thomas on the inspection of this well.
1103 2002-6-5 0:00:0 ER No Violations
1122870582 2017-04-10 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pump, injection pressure and annulus pressure. Identification is posted at the tank and well. There is a tri plex injection pump installed in the containment dike. I called and talked to Lee Atha. Lee informed me that the new pump is not on line right now. They are still using the submersible pump in the brine tank. We discussed the need to connect the murphy switch to the new pump prior to operation.
1127764262 2011-08-04 Enhanced Recovery Project No Violations Injection well is disconnected from injection lines. Lee Atha told me that they plan to drill the well deeper. Location has been prepared for drill rig.
1149464795 2013-09-12 Salt Water Injection Well No Violations I accompanied Jon Scott for a line test. The test was held for 15 minutes at 412 PSI. No loss in pressure the test passed.
1151488857 2020-5-6 0:00:0 SW No Violations
1174726617 2012-04-26 Salt Water Injection Well Violations Noted Well is connected for injection. Injection line doesnt have a tee and 1/4 fitting for gauge at wellhead. I talked to Lee Atha and he will install a 1/4 valve for me. I checked the injection line pressure at a valve inside the tank dike. Injection is on vacuum. Dike is free of water. Injection pump is submersible and located with-in tank. No identification at tank or well. Lee Atha said he is working with some stencils and will get the identification installed soon.
1181857479 2003-10-30 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, company has a service rig on the well, it appears the tubing and packer has been moved, a M.I.T. test has not been done as of date. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
1190067569 2003-07-02 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, well still idle, MIT test has not been done. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
1193392527 2012-04-26 Salt Water Injection Well No Violations Performed status check on well and tank battery with Inspector Jon Scott. Met with company man Lee Atha and discussed this well and several others that his company owns.
1195009222 2009-06-30 Enhanced Recovery Project No Violations A follow-up inspection was conducted with Mr. Robert Stonerock, Oil & Gas South Region District Supervisor. An inspection revealed a majority of the cleanup has been performed. Contaminated soil(s) will be moved to Paul Grims shop and remediated.
1196714965 2014-03-10 Salt Water Injection Well Violations Noted Injection tubing is stacked at the well site. The wellhead is laying on top of the tubing. The production casing is equipped with a swedge and a valve (valve is closed). The injection line from the containment dike has a closed valve and is not connected to the well. Well is incapable of injecting fluids. The containment dike is not liquid tight due to a slip down slope from the dike. The dike must be repaired prior to injection operations. 1501:9-3-07 (K) Any well which is or becomes incapable of injecting fluids shall be plugged in accordance with sections 1509.13 and 1509.15 of the Revised Code. Submit all remedial plans to the UIC Section for review with-in 30 days.
1221644061 2012-02-06 Salt Water Injection Well No Violations Accompanied Inspector Jon Scott on an inspection of the tank battery liner.
1222876937 2009-09-15 Enhanced Recovery Project No Violations A follow-up inspection with Mr. Robert Stonerock, Oil & Gas South Region Supervisor, revealed non-compliance. Myself along with Mr. Stonerock met with Mr. Paul Grim at his shop at 3:15 pm. Advised Mr. Grim of the existing violations at his shop in Vinton County. Mr. Stonerock stated to Mr. Grim that the DMRM is aware of the possible transfer of wells from Chieftain Energy to Paul Grim. More importantly, we want him to know of the existing violations such as, Permit No. 705, McGlaughlin SWIW #6. I referred to the three (3) options that had been suggested to Chieftain Energy, in order to achieve compliance with concrete dike. Mr. Grim informed that pump no longer leaking and bare areas exist at shop. Mr. Grim replied by stating that at least they would not have to mow. Informed that tanks and earthen dikes are leaking and to add organic material (horse manure, lime, seed and mulch to location(s).
1232474814 2012-08-02 Salt Water Injection Well No Violations Conducted inspection on building across Harkins Chapel Road from the well. Building still owned by Paul Grim. Fluid was leaking from old injection pump. It was steadily dripping from a 2 inch line on the intake side of the pump that had been cut. It was dripping at a rate of about 1 drip per second. Fluid had ran to the outside of the building on two sides. I called Paul Grims cell phone and had left a message. I also called Paul Thompson, but wasnt able to leave a message due to the fact that his voicemail wasnt set up. Met with Paul Grim on the 13th of August, and discussed with him what the issue was. He agreed to send somebody out there immediately to remediate.
1249453608 2017-02-27 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure and annulus pressure. Identification posted at the well and tank. The containment dike is free of fluids.
1253130998 2009-09-01 Enhanced Recovery Project Violations Noted An inspection was conducted with Mr. Jeff Fry, UIC Field Supervisor, West Region Supervisor. During the inspection, it was noted that fluid was being discharged from a 4 PVC pipe directly onto concrete slab and draining down slope into an earthen pit containing 1 horizontal tank approx 150 bbl. At location, salt crystals were observed on concrete. Another section of PVC pipe was observed in pit, but not connected to discharge pipe. The pit was found to contain 3/4 of oil on surface and measured 41 (length) x 16 and 22 (widths). High Range Quantabs utilized at discharge point exceeded 6545 ppm(mg/L) Cl-. A 4 oz container was utilized to measure discharge rate. The container was filled in 10 seconds. The storage tank for the ERP consists of a 200 bbl tank placed on concrete slab inside Mr. Paul Grims shop. Currently, no containment exists for the tank. At this location, the pump was found to be leaking continuously. The fluid from this leak then enters two floor drains that tie into the PVC pipe outside shop. Report continued on next page. Remove all contaminated material from impacted locations to include area inside shop containing 200 bbl tank. Earthen dike containing horizontal tank shall meet current standards for containment to include 30 mil liner. Provide facility plans to Mr. Tom
1255747329 2003-03-25 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, well still idle, company has not done MIT test. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
1266341495 2010-01-29 Administrative Inspection No Violations A follow-up inspection revealed non-compliance. Fluid still remains inside the pit at horizontal tank location. The fluid has been pumped since the last inspection. A water mark observed on the tank measured approx 2-3 to remaining fluid. A collapsable hose has been placed inside a 100 bbl tank. The tank appears to be full at this time. High Range Quantab Locations: Path from end of hose to location at bottom of hill showed 6.2 and 8.0 units. Below tank battery location (Phillips side) and above hose was 5.8 and 6.6 units. Contacted Mr. Doug Kitchen at 11:58 am. A message was left on his cell phone regarding this inspection.
1269i10 2001-1-17 0:00: ER No Violations
1269i10025 2002-04-25 Enhanced Recovery Project No Violations Follo-up on NOV, Non-Compliance, company has not done a MIT test on the well and has not put ID at the well or storage tank. Called and talked to Doug Kitchen, he said he needed more time, I told him to notify Joe Hoerst in Jackson, Joe told him he had until May 3, 2002 to have all the violations corrected or court case would be filed.
1269i100258475 2002-4-25 0:00: ER No Violations
1269i1019 2002-5-6 0:00:0 ER No Violations
1269i1313 2002-8-20 0:00: ER No Violations
1269i84256 2002-03-04 Enhanced Recovery Project No Violations An inspection of the well revealed No ID at the well or storage tanks, pressure on the injection and annulus sides of well still 0 after the last 3 inspections. Need ID at the well and tanks, and a M.I.T. test done on well. If test is not preformed by compliance date a Chiefs Order will be issued to stop operating well.
1269i84256911 2002-3-4 0:00:0 ER No Violations
1269i90557 2002-03-26 Enhanced Recovery Project No Violations Follow-up Non-Compliance, met with Doug Kitchen to look over violations.
1269i90557364 2002-3-26 0:00: ER No Violations
1275296804 2011-11-09 Drill / Deepen / Reopen No Violations Checked status of deepening of well. Original depth was 1279. Depth at time of inspection was 2491. Accompanied by Jon Scott.
1285898365 2010-09-13 Enhanced Recovery Project No Violations A follow-up inspection of horizontal tank location next to Paul Grims shop and 210 bbl tank (vertical) inside the shop revealed non-compliance. Mr. Doug Kitchen agreed to a Compliance Schedule on 8/19/2010, in which the P&C and fluid inside the dike at horizontal tank location would be removed within 2 weeks.
1288387450 2008-05-27 Enhanced Recovery Project No Violations No violations were noted.
1300434503 2005-01-06 Enhanced Recovery Project No Violations Follow-up on NOV, In-Compliance.
1306855726 2011-05-05 Enhanced Recovery Project No Violations Witnessed mini test. Annulus filled with 5 gallons fresh water and one cup inhibitor. Pumped 225 gallons down tubing to see what rate it took at 380 psi. Annulus tested at 390 psi with no drop in pressure in 15 minutes.
1314214076 2011-08-04 Surface Facility Construction No Violations Request received from UIC section to inspect ERP well site for drill deeper and conversion to SWIW. There is one water well with-in 2000 feet Well log # 431790, GPS N 39.222228/ W 082.321431. There are no surface bodies of water with-in close proximity. Injection well is located in a wooded area.
1320947333 2011-11-09 Drill / Deepen / Reopen No Violations Drilling deeper to convert to SWIW. Currently at 2494.
1329413811 2009-09-11 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance.
1333763465 2014-06-04 Salt Water Injection Well No Violations Knox Energy, Producers Services and Appalachian Well Surveys on site. The well was perforated at 1978-1968 5 shots, 1998-2008 6 shots, 2028-2052 13 shots, 2072-2082 6 shots, 2158-2176 10 shots, 2192-2198 4 shots, 2208-2216 5 shots, 2230-2240 6 shots, 2250-2268 10 shots, 2544-2556 7 shots. The tubing was shot off at 1240. The packer was ran in to a depth of 1196-1192. The packer had 12,000 pounds pulled on it. Producers ran acid thru the bottom perforations. They also ran inhibiter. The test pressure was 440 PSI for 15 minutes. The well lost 19 PSI. The max loss was 22 PSI, the test passed.
1338083959 2018-07-03 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure and annulus pressure. Identification is posted at the well and tank. The containment dike is free of fluids.
1359044339 2013-01-24 Salt Water Injection Well Violations Noted An inspection of the tank battery revealed no violations. Good identification was observed at the tank battery and the well. The annulus pressure on the well was 0. I called Mr. Lee Atha at 11:20 on the day of inspection and notified him of the problem and told him that the annulus pressure needs to be above 0 and a mini-test needs to be conducted. I also told him that when he remedies the problem to call me so that I can be present. This message was left on his voicemail. Accompanied on inspection by Justin Smith.
1364616455 2014-05-21 Salt Water Injection Well No Violations Compliance Notice # 1196714965 Follow up. Berry Well Service has moved in service equipment to drill out the obstruction in the open hole portion of the well.
1369923823 2013-05-20 Salt Water Injection Well No Violations Inspected injection pressure, annulus pressure, containment dike and tanks.
1374078366 2013-07-17 Salt Water Injection Well No Violations UIC injection well inspection, The site is clean and the dike is free of water. No violations.
1375201044 2013-07-29 Surface Facility Construction No Violations Containment dike liner has been covered with soil. A new injection pump has been installed with-in the containment dike.
1383799929 2008-02-21 Enhanced Recovery Project No Violations No violations were noted.
1383916810 2013-11-07 Salt Water Injection Well No Violations Drilling out shale. Lost circulation at 1967 feet. Extracted tubing and bit back into casing. Currently evaluating down hole conditions prior to proceeding.
1384865931 2013-11-12 Salt Water Injection Well No Violations Service rig is down and moved off location. Tubing is on the ground at the wellhead. A 4 by 2 swedge with valve has been installed on the wellhead. Pit is closed. Site is graded. Talked with Lee Atha about the well and what their plans are to get the well back in use. They are currently reviewing their options and have not determined which course of action to take.
1387315067 2006-10-03 Enhanced Recovery Project No Violations An inspection of the well revealed that identification would be needed at the storage tank.
1392949827 2019-4-29 0:00: SW No Violations 1.70
1393441301 2014-02-26 Salt Water Injection Well No Violations Injection tubing is stacked at the well site. The wellhead is laying on top of the tubing. The production casing is equipped with a swedge and a valve (valve is closed). The injection line from the containment dike has a closed valve and is not connected to the well. Containment dike is free of water and the identification is posted on the tank. I called and discussed the well status with Tom Atha. Tom told me that the plan is to drill out the open hole portion below the casing and cement tubing in place. I asked for a time line as to when this will take place.
1396975648 2014-04-07 Administrative Inspection No Violations South West Region supervisor Dan Goins told me issue an extension on Compliance Notice # 1196714965 until the first week of May (5-9-14) after a meeting he had with Tom Tomastik and Bob Worstall.
1399919038 2014-05-12 Salt Water Injection Well No Violations Compliance Notice # 1196714965 Follow up Inspection. No equipment has been moved on site. Well is equipped with a swedge and a valve. Injection line is not connected to the well. Tubing is stacked on ground at the well site. A tree has fallen across the access road. The fiberglass 210 barrel tank in the containment dike is overflowing water into the containment dike. (High end Quantab showed 280 ppm Cl) The containment dike sump pump is pumping the water back to the 210 tank (the tank is full). I called Lee Atha and told him that the tank is overflowing. Lee said that he will send out a truck to pump out the tank and dike and take the water to another injection well for disposal. I asked Lee when the service work was scheduled to begin drilling out the injection zone. I reminded Lee that the Compliance Notice was extended to 5-9-14. Lee said that he will call me back.
1400585262 2014-05-19 Administrative Inspection No Violations Compliance Notice # 1196714965 follow up. Received a phone call from Lee Atha that Knox Energy will be moving a rig and equipment to the well on 5-20-14. They plan to start drilling out on 5-21-14.
1400866131 2014-05-23 Salt Water Injection Well No Violations Knox Energy is drilling out a cave in. They are drilling on air, using a power swivel. They are adding soap to help unload the hole. They have reached 1918 today and will resume drilling on 5/27/14.
1401212627 2014-05-27 Salt Water Injection Well No Violations Knox Energy is on site drilling out cave in. They are using a power swivel and they are drilling on air. They a=have added soap to aid in keeping circulation. They have reached 2030. They lost circulation and have pulled on joint of tubing out. This allowed them to regain circulation. The drilling is going slowly due to not be able to keep circulation.
1403022503 2014-06-17 Administrative Inspection No Violations Compliance Notice # 1196714965 Follow up Phone call. Talked to Lee Atha about the containment dike. Lee said that they are moving the containment dike to the flat area near the production tank battery. The original containment dike will be reclaimed. They plan on using the two 210 barrel tanks and extending the injection line. The excavation is scheduled for the first part of July.
1406128917 2014-07-23 Surface Facility Construction No Violations Injection well line test. Tested at 398 psi for 15 minutes with no loss.
1410791201 2014-09-15 Salt Water Injection Well No Violations Inspected the containment dike, tank, annulus pressure and injection pressure. Identification is posted on the well and in the containment dike. Well site has been seeded and mulched. I called Lee Atha and left a message regarding the annulus pressure being low. I told Lee to call and schedule an annulus test.
1412263202 2014-10-02 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure and annulus pressure. Identification posted on tank and well.
1422765526 2003-06-03 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, well has not passed MIT test for injecting brine, well still idle and not capable of injecting brine at this time. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
1424323782 2018-01-03 Salt Water Injection Well No Violations I witnessed a mechanical integrity test for this well. The test pressure was 265 psi for 15 minutes with no loss in pressure.
1425245253 2009-10-09 Enhanced Recovery Project Violations Noted A follow-up inspection revealed non-compliance. The 210 bbl tank located inside the Mr. Paul Grims shop will require an earthen or concrete dike with a plan to be sent to Mr. Tom Tomastik. A 1 black plastic line from Phillips tank routed 210 bbl tank inside shop is cut before entering building. Flagged location for company. C&P still remains at horizontal tank location. The 210 bbl tank located in Mr. Paul Grims shop will require an earthen or concrete dike. Construct earthen or concrete dike for the tank. Plans are to be submitted to Mr. Tom Tomastik for review. The second horizontal tank (near the road) is leaking an
1452296759 2009-09-01 Enhanced Recovery Project No Violations FOLLOW UP TO NOV # -375042358 An inspection was conducted with Mr. Jeff Fry, UIC Field Supervisor, West Region Supervisor. During the inspection, it was noted that fluid was being discharged from a 4 PVC pipe directly onto concrete slab and draining down slope into an earthen pit c
1467042412 2004-07-29 Enhanced Recovery Project Violations Noted An isnpection of the well revealed no ID at the well, unable to check water pump, locked up in building. Lease rd eroding, needs graded.
1479381009 2014-07-03 Surface Facility Construction No Violations Containment dike has been lined with a limestone berm material. Currently working on installing the injection line.
1512530707 2011-03-30 Enhanced Recovery Project Violations Noted No identification at well. Well must have identification(1509:9-9-05(A)(10): Well owner, lease name, well number, permit number, county, emergency telephone number. Annulus has zero pressure. Schedule a mechanical integrity test with Inspector Jon Scott 740-624-4963.
1513264415 2009-09-01 Enhanced Recovery Project No Violations FOLLOW UP TO NOV # 1253130998 An inspection was conducted with Mr. Jeff Fry, UIC Field Supervisor, West Region Supervisor. During the inspection, it was noted that fluid was being discharged from a 4 PVC pipe directly onto concrete slab and draining down slope into an earthen pit c
1518867239 2013-07-16 Salt Water Injection Well No Violations The well and the tank battery are kept in good order. There is no pollution and contamination. There is no fluid in the containment dike. Good identification was observed at the well and the tank battery. Accompanied by Inspector Kip Thompson.
1521920272 2014-03-10 Salt Water Injection Well No Violations FOLLOW UP TO NOV # -1196714965 Injection tubing is stacked at the well site. The wellhead is laying on top of the tubing. The production casing is equipped with a swedge and a valve (valve is closed). The injection line from the containment dike has a closed valve and is not connected to the well. Well is incapable of injecting fluids. The containment dike is not liquid tight due to a slip down slope from the dike. The dike must be repaired prior to injection operations. 1501:9-3-07 (K) Any well which is or becomes incapable of injecting fluids shall be plugged in accordance with sections 1509.13 and 1509.15 of the Revised Code. Submit all remedial plans to the UIC Section for review with-in 30 days.
1523123372 2016-07-29 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure and annulus pressure. Identification posted at the tank and well site. The containment dike is free of fluids.
1526054372 2018-05-08 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pump, injection pressure and annulus pressure. Identification posted. The containment dike is free of fluids.
15489688 2009-6-29 0:00: ER No Violations
1557599074 2015-08-10 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pump, injection pressure and annulus pressure. Assisted UIC section Geologist in measuring the containment dike.
1563903873 2019-7-23 0:00: SW No Violations 1.50
1565445651 2016-12-09 Salt Water Injection Well No Violations Mechanical integrity test. Tested annulus at 380 psi , at 5 minutes 380 psi, at 15 minutes 375 psi. Test passed. Injection tubing pressure was 35 psi during the test.
1565808126 2019-8-12 0:00: SW No Violations 2.50
1574363513 2019-11-13 0:00 SW No Violations 0.90
1579783816 2011-11-18 Salt Water Injection Well No Violations Install rebuilt R-4 packer and tubing at 1205. Fill annulus with fresh water and inhibitor. Test at 410 psi for 15 minutes. No loss after 15 minutes. Reduce Annulus pressure to 200 psi.
1583325834 2020-3-3 0:00:0 SW No Violations 3.00
1585943499 2016-06-09 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection line, injection pressure and annulus pressure. Identification posted at the well and facility. Containment dike is free of fluids.
1587152376 2020-4-14 0:00: SW No Violations 3.00
1618538742 2012-02-06 Surface Facility Construction No Violations Constructed dike 70 feet by 37 feet by 2 feet 2 inches high. Lined dike with 30 mil plastic liner. 4 inch layer of sand under liner and 4 inch layer of sand inside liner. Accompanied by Andy Thomas MRI.
162022739 2013-3-7 0:00:0 SW No Violations 2.20
1640069670 2008-12-22 Enhanced Recovery Project No Violations An inspection revealed no violations. Note: Winter conditions at time of the inspection.
1667154934 2008-09-11 Enhanced Recovery Project No Violations An inspection revealed no violations.
1696963412 2004-01-18 Enhanced Recovery Project No Violations Spoke with Doug Kitchen, he wants to test well later in week, need to talk to Tom Tomastik before testing well.
1730997460 2012-08-02 Salt Water Injection Well No Violations No violations were noted at the time of inspection. Accompanied by inspector Morgan Button.
1741013806 2009-09-04 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The earthen pit has been pumped, but contamination and pollution still exists.
1777128457 2001-01-17 Enhanced Recovery Project Violations Noted FOLLOW UP TO NOV # 1269i10 An inspection revealed that there is no ID at the well or at the storage tank . Unable to check the annulus pressure on well , unable to open 1/4 valve. REQUEST THE COMPANY NOTIFY THE INSPECTOR FOR MONTHLY M.I.T. TEST. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
1794875532 2009-09-23 Production Wells No Violations An inspection revealed non-compliance. It was noted that progress has been made with cleanup since last inspection. Contamination and pollution issues still exist at horizontal tank location next to Paul Grims shop. This location shows signs of torn liner at top of earthen dike. Inside the dike evidence of liner was also observed covered below sand. Note: Paul Grims employees have been performing cleanup.
1812623776 2010-02-12 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. Oil and brine still exist at the horizontal tank location next to Paul Grims shop. Containment for the 210 bbl tank located inside Mr. Grims shop has not been constructed.
1835217021 2009-11-16 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The dike around horizontal tank needs pumped, and dike provided for 210 bbl tank inside shop.
1842141160 2007-11-01 Enhanced Recovery Project No Violations No violations were noted.
1845071477 2015-06-09 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure, and annulus pressure. Containment dike is free of fluids.
1885633757 2004-10-07 Enhanced Recovery Project No Violations Follow-up on NOV, non-compliance, violations not corrected, spoke with Doug Kitchen on the phone, he is hoping Paul Grim will take over well.
1888683854 2014-07-23 Salt Water Injection Well No Violations Inspected the containment dike, injection pump, injection line, annulus pressure and injection pressure. Lee Atha installed a new needle valve on the injection tubing. The master valve is closed due to the relocation of the surface facility and the extension of the injection line.
1891904129 2010-07-08 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. Multiple violations still exist at the well and storage tank location. No action has been taken by the company to achieve compliance. Note: To date, a Paul Grim employee has made attempts to address horizontal tank location (outside shop), which contained maximum dike capacity of fluid consisting of brine and oil. However, the location still requires more work to address fluid level and the removal of pollution and contamination.
1907292643 2010-12-28 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The well owner will be performing a mini-test and will install 1/4 fitting for the injection side of well. An attempt had been made by company to place pressure on annulus but found leak on casing the size of pencil lead at surface (not witnessed). Mr. Ron McBride states that a welder will be utilized to patch leak. Housekeeping needed inside Paul Grims shop and dike does not exist for tank at this location.
1935888185 2013-07-17 Salt Water Injection Well No Violations Paul Grimms employees are on site cleaning the oil that was stored in a dike next to a 210 barrel horizontal tank. I witnessed several spots of oil that have surfaced where recent grading work has been done. I believe when the tanks were removed oil was spilled and covered up. I have contacted Paul Grimm to inform him of the need to clean up this area also.
1951319815 2009-12-09 Enhanced Recovery Project No Violations A follow-up inspection revealed that violations still exist at well and tank battery location. No pressure observed on annular side of well and 1/4 fitting still needed on the injection side. Vegetative growth observed at well site from remediation project. The 210 bbl tank inside Paul Grims shop still needs an earthen or concrete dike. A 1 black plastic line remains cut and still needs repaired. The earthen dike around horizontal tank next to Paul Grims shop has reached maximum fluid capacity and will need to be pumped. Made attempt to call Paul Grim at 1:28 pm, no answer.
1966090868 2009-06-24 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. Mr. Paul Grim is working towards achieving compliance. The compliance deadline was extended to 6/26/2009, due to a broken track on dozer.
2003883480 2017-12-11 Salt Water Injection Well No Violations My inspection revealed the salt water injection well had 4 psi on the annulus and 32 psi on the injection tubing. The dike was free of fluids. I contacted well owner River Valley Energy to have then add more pressure to the annulus and also to freshen up the identification at the wellhead.
2011572839 2009-10-16 Enhanced Recovery Project No Violations A follow-up inspection to Notice of Violation was conducted with Mr. Robert Stonerock, South Region Oil & Gas Supervisor. The inspection revealed that cleanup is not acceptable and will require more work.
2014838629 2012-08-16 Salt Water Injection Well No Violations Checked on building across the road from injection well (Paul Grims old shop). Contaminated soil on the sides of the building had been worked up and manure had also been worked into it. Drip had been stopped. Issue has been remediated.
2015614522 2011-11-07 Administrative Inspection No Violations Received phone call from Lee Atha Re: moving rig on site today.
2024770428 2014-04-01 Administrative Inspection No Violations Received an email dated 3-31-14 from Tom Atha regarding the scope of work that Bill Mitton is to do to get the well in compliance. Tom stated that they can do the work some time in May. I responded to Tom that I need an actual date for an extension request and that I will be sending the request to my supervisor for approval.
2040992729 2009-03-03 Enhanced Recovery Project No Violations An inspection revealed no annulus pressure at this time. The storage tanks located in the shop will need to be checked during the next inspection. Chieftain Energy will be contacted regarding this inspection.
2052117095 2014-05-12 Administrative Inspection No Violations Compliance Notice # 1196714965 follow up phone call. Lee Atha called me and told me that he talked to Bill Mitton (Knox Energy) and Bill told him that this week is to wet to move the equipment in and that they plan to move equipment in on the week of May 19th, 2014.
2055475690 2010-03-01 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The status remains unchanged since the last inspection.
2061347165 2010-05-12 Enhanced Recovery Project No Violations A follow-up inspection revealed non-compliance. The horizontal tank location still contains brine and oil in the dike. The fluid has recently been pumped down, but level remains high and will again need to be addressed. No containment has been constructed for the 210 bbl tank inside Mr. Paul Grims shop. To date, a mini-test has not been performed on this well.
2061541806 2010-02-22 Enhanced Recovery Project No Violations Mr. Ron McBride, Chieftain Energy Contractor, called this morning at 9:24 am with questions pertaining to compliance issues on Chieftain Energy wells. Mr. McBride was informed that deadlines for NOVs and Compliance Schedule from 7/14/2009 have been exceeded. Mr. McBride was informed that P&C still exists at horizontal tank location at Paul Grims shop. He states the work should have been completed. A follow-up call placed to Mr. Doug Kitchen on 1/29/2010 was referenced in which, Mr. Kitchen had been informed the pit was still full of brine and oil. As previously instructed, I again explained that if you elect not to place positive pressure on annulus, contact me to witness the monthly mini-test. To date there is no pressure and have not been contacted for testing. An unrelated ERP in Hocking County with similar deficiency also mentioned in conversation. Mr. McBride states possible AD test would performed on unrelated producing well in Hocking County.
2081845278 2014-03-27 Administrative Inspection No Violations 3-27-14 Follow up phone call at 3:04 pm with Bill Mitton (Knox Energy) Bill out lined the plans for remediation of the injection well and the approximate time frame of May 2014. I told Bill to have Tom Atha submit an extension request and I will forward it to my supervisor for review.
2092717665 2016-10-12 Salt Water Injection Well No Violations Inspected the containment dike, tank, injection pressure and annulus pressure. The containment dike is free of fluids. Identification is posted at the facility and the well.
2094033275 2013-07-29 Salt Water Injection Well No Violations Inspected the containment dike, tanks, injection pump, injection line, injection pressure, and annulus pressure. Identification is posted at the well and on the tank. A wet area 12 down slope of the containment dike is approximately 6 by 1.5. A high range Quantab was used to check for chlorides. The Quantab showed 6.6 (2051 ppm Cl). I called Lee Atha and we discussed the wet area. Lee said that some earth work had been done recently and that he is unaware of any leaks. The containment dike was free of fluid during the inspection. Lee is going to bio remediate the wet area.
2106705098 2006-07-12 Enhanced Recovery Project Violations Noted An inspection was conducted at the facility owned by Chieftain Energy Corp on 7/12/2006. During the inspection, it was noted that the ID located at the well needs to be placed in a visible location. It was also documented that the lease road was starting to erode. The storage tanks for this facility could not be accessed, due to the building being locked.
2143310847 2013-02-28 Salt Water Injection Well Violations Noted Inspected containment dike, injection pressure and annulus pressure. Accompanied by Kip Thompson MRI 2. Containment dike was inspected prior to inspecting the injection well. While walking back toward the containment area on the way out, the 210 barrel fiberglass tank with-in the containment dike was observed to be overflowing. I called Lee Atha and he responded to the location with-in a half hour. Lee shut off the production in the field and stopped the flow of brine to the tank. The cause of the tank overflowing was a defective submersible brine pump with-in the 210 barrel tank. The pump will be replaced. Approximately 50 barrels of brine overflowed into the containment dike. I instructed Lee to fix the pump and remove the brine out of the dike and into a tank.
2147145560 2003-04-21 Enhanced Recovery Project No Violations Follow-up on NOV, Non-Compliance, well has not passed a MIT test to date, and company has shut well down. 1/12/04 to date company has not complied with NOV and corrected violations, turned over to management.
2147157139 2011-11-02 Salt Water Injection Well No Violations Well site has been built for drill rig. Have permit to drill deeper and convert from ERP well to SWIW. Tubing has been pulled from well. Well consists of 4.5 casing with 4.5 by 2 swedge , 2 valve (closed).
279693739 2009-6-11 0:00: ER No Violations
314287443 2012-8-28 0:00: SW No Violations 1.00
325824842 2002-3-4 0:00:0 ER No Violations
354308989 2009-10-15 0:00 AM No Violations
376884252 2012-5-30 0:00: SW No Violations 1.50
396594231 2014-8-20 0:00: SW No Violations 2.50
430645978 2016-2-23 0:00: SW No Violations 1.50
539748129 2019-4-29 0:00: SW No Violations
571989164 2014-7-1 0:00:0 SC No Violations 2.50
583729826 2015-3-11 0:00: SW No Violations 1.50
637081880 2019-11-6 0:00: SW No Violations 2.00
677716441 2010-3-17 0:00: ER No Violations
74219010 2013-11-6 0:00: SW No Violations 4.00
760489283 2012-1-17 0:00: SW No Violations 2.00
772395642 2009-9-1 0:00:0 ER No Violations
827881296 2009-9-1 0:00:0 ER No Violations
919441220 2004-5-19 0:00: ER No Violations
922874988 2013-7-16 0:00: PW No Violations 2.00
924145246 2014-5-22 0:00: SW No Violations 11.00
945942037 2012-1-17 0:00: SC No Violations
970661669 2011-1-10 0:00: ER No Violations 4.00
iTOMK00010 2001-01-17 Enhanced Recovery Project Violations Noted
iTOMK000103 2001-1-17 0:00: ER No Violations
UIC1257 1992-5-5 0:00:0 ER No Violations
UIC195 1987-5-8 0:00:0 ER No Violations
UIC294 1986-12-9 0:00: ER No Violations
UIC331 1986-12-9 0:00: ER No Violations
UIC332 1986-12-9 0:00: ER No Violations
UIC333 1986-12-9 0:00: ER No Violations
UIC600 1989-1-17 0:00: ER No Violations
UIC601 1989-1-17 0:00: ER No Violations
UIC602 1989-1-17 0:00: ER No Violations
UIC665 1989-5-2 0:00:0 ER No Violations
UIC666 1989-5-2 0:00:0 ER No Violations
UIC667 1989-5-2 0:00:0 ER No Violations
UIC706 1989-6-13 0:00: ER No Violations
UIC740 1989-8-1 0:00:0 ER No Violations
UIC741 1989-8-1 0:00:0 ER No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
0001269i10 US-OH-107232 2001-01-19 Violation of injection tubing/fitting requirements
0001269i10 US-OH-107233 2001-01-19 Insufficient/No identification
0279693739 US-OH-122909 2009-06-29 Pollution/Contamination
0325824842 US-OH-123417 2002-03-04 Failure to monitor pressures or volumes/failure to file
0325824842 US-OH-123418 2002-03-04 Insufficient/No identification
0375042358 US-OH-123953 2009-09-16 Equipment pressure rated below operating pressure
0375042358 US-OH-123954 2009-09-16 No SPCC dike/or failure to keep dike free of water or oil
0375042358 US-OH-123955 2009-09-16 Unlawful method of storage or disposal of brine or other wastes
0375042358 US-OH-123956 2009-09-16 Failure to keep SPCC dike/pit free of brine and other wastes
0375042358 US-OH-123957 2009-09-16 Unlawful use of pit for temporary storage of brine or other wastes
0375042358 US-OH-123958 2009-09-16 Use of pit of dike for ultimate disposal of brine or other wastes
0375042358 US-OH-123959 2009-09-16 Storage facilities contamination (permit before 6/1/82)
0375042358 US-OH-123960 2009-09-16 Failure to conduct or pass mech. integrity test
0375042358 US-OH-123961 2009-09-16 Failure to monitor annulus pressure
0375042358 US-OH-123962 2009-09-16 Mechanical failure/contamination
0375042358 US-OH-123963 2009-09-16 Change of E.R. procedures without approval
0539748129 US-OH-125907 2019-05-09 Failure to file salt water injection annual report
0583729826 US-OH-126556 2015-03-26 Failure to monitor annulus pressure
0667952648 US-OH-127563 2005-10-20 Failure to monitor pressures or volumes/failure to file
0922874988 US-OH-130547 2014-03-20 Well operation causing pollution and contamination
1174726617 US-OH-104616 2012-05-01 Failure to legibly identify well
1174726617 US-OH-104617 2012-05-01 Violation of injection tubing/fitting requirements
1196714965 US-OH-105156 2014-07-09 Contamination at surface facility (permit after 6-1-82)
1196714965 US-OH-105157 2014-07-09 Well shall be plugged
1253130998 US-OH-106811 2009-09-16 Leaking brine pipeline
1253130998 US-OH-106812 2009-09-16 Failure to have required locks, bull plugs
1253130998 US-OH-106813 2009-09-16 Unlawful method of storage or disposal of brine or other wastes
1253130998 US-OH-106814 2009-09-16 Failure to keep SPCC dike/pit free of brine and other wastes
1253130998 US-OH-106815 2009-09-16 Unlawful use of pit for temporary storage of brine or other wastes
1253130998 US-OH-106816 2009-09-16 Use of pit of dike for ultimate disposal of brine or other wastes
1253130998 US-OH-106817 2009-09-16 Pollution/Contamination
1253130998 US-OH-106818 2009-09-16 Violation of inj. tubing/fitting requirements (permit before 6/1/82)
1253130998 US-OH-106819 2009-09-16 Storage facilities contamination (permit before 6/1/82)
1253130998 US-OH-106820 2009-09-16 Failure to conduct or pass mech. integrity test
1253130998 US-OH-106821 2009-09-16 Failure to monitor annulus pressure
1253130998 US-OH-106822 2009-09-16 Mechanical failure/contamination
1253130998 US-OH-106823 2009-09-16 Change of E.R. procedures without approval
1253130998 US-OH-106824 2009-09-16 General Safety
1253130998 US-OH-106825 2009-09-16 Equipment pressure rated below operating pressure
1253130998 US-OH-106826 2009-09-16 No SPCC dike/or failure to keep dike free of water or oil
1359044339 US-OH-110424 2013-01-25 Failure to monitor annulus pressure
1425245253 US-OH-112385 2009-10-29 Inadequate pipeline strength
1425245253 US-OH-112386 2009-10-29 Equipment pressure rated below operating pressure
1425245253 US-OH-112387 2009-10-29 No SPCC dike/or failure to keep dike free of water or oil
1425245253 US-OH-112388 2009-10-29 Unlawful method of storage or disposal of brine or other wastes
1425245253 US-OH-112389 2009-10-29 Failure to keep SPCC dike/pit free of brine and other wastes
1425245253 US-OH-112390 2009-10-28 Pollution/Contamination
1425245253 US-OH-112391 2009-10-28 Storage facilities contamination (permit before 6/1/82)
1467042412 US-OH-113475 2004-08-02 Violation of injection tubing/fitting requirements
1467042412 US-OH-113476 2004-08-02 Insufficient/No identification
1512530707 US-OH-114325 2011-04-06 Failure to monitor annulus pressure
1512530707 US-OH-114326 2011-04-06 Failure to legibly identify well
1777128457 US-OH-117707 2001-01-19 Violation of injection tubing/fitting requirements
1777128457 US-OH-117708 2001-01-19 Insufficient/No identification
2106705098 US-OH-121539 2006-07-23 Insufficient/No identification
2143310847 US-OH-122013 2013-03-07 Contamination at surface facility (permit after 6-1-82)
iTOMK00010 US-OH-131646 Violation of injection tubing/fitting requirements