Well ID: 34-167-29721 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.56,"lon":-81.5,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Washington | |
Municipality: Adams Township | |
Operator Name: UTICA RESOURCE OPERATING LLC | |
Well Pad ID: US-OH-000672 | |
Farm/Lease Name: GARVIN | |
License Status: Plugged Back | |
License Date: 2013-04-17 | |
Spud Date: 2013-05-07 | |
Spud Drilling Contractor: | |
Final Drill Date: | |
Well Total Depth: | |
Configuration: Vertical | |
Latitude: 39.560000 | |
Longitude: -81.500000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2013-03-12 | Proposed Formations:POINT PLEASANT, Issued Date:3/12/2013, Expired Date:3/12/2015 12:00:00 PM, Drilling unit acres:517, Proposed Well Type:OG, Proposed Well Class:EDPW |
APP | 2013-04-17 | Proposed Formations:TRENTON-BLACK RIVER, Issued Date:4/17/2013, Expired Date:4/17/2015 12:00:00 PM, Drilling unit acres:517, Proposed Well Type:ST, Proposed Well Class:STRT |
Plugged Back | 2013-05-23 | |
Construction Permit Expires | 2015-04-17 | |
Change of Owner | 2018-05-04 | Operator changed from 8595, PDC ENERGY INC to 10114, UTICA RESOURCE OPERATING LLC |
Record Last Modified | 2018-05-04 |
For data sources see[2]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 07/31/2013 | 08/10/2013 | 0 | 6,297,030.0 | 0 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | 15% HCl, Slickwater, WF120, YF120 | Schlumberger | Corrosion Inhibitor, Bactericide (Myacide GA25), Scale Inhibitor, Surfactant , Acid, Breaker, Gelling Agent, Friction Reducer, Crosslinker, Iron Contr | Polymer of 2-acrylamido-2-methylpropanesulfonic
acid sodium salt and methyl acrylate |
136793-29-8 | 0.00654 | 0.00087 | 0 |
Dicoco dimethyl quaternary ammonium chloride | 61789-77-3 | 0.0032 | 0.00043 | 0 | ||||
Phenolic resin | 9003-35-4 | 0.19177 | 0.02556 | 0 | ||||
Magnesium silicate hydrate (talc) | 14807-96-6 | 0.00008000 | 0.00001000 | 0 | ||||
Fatty acids, tall-oil | 61790-12-3 | 0.00068 | 0.00009000 | 0 | ||||
Potassium borate | 1332-77-0 | 0.1629 | 0.02171 | 0 | ||||
Water (Including Mix Water Supplied by Client)* | NA | 0 | 86.6735 | 0 | ||||
Alkenes, C>10 a- | 64743-02-8 | 0.00012 | 0.00002000 | 0 | ||||
Potassium hydroxide | 1310-58-3 | 0.06035 | 0.00804 | 0 | ||||
Sodium erythorbate | 6381-77-7 | 0.00142 | 0.00019 | 0 | ||||
Tetrasodium ethylenediaminetetraacetate | 64-02-8 | 0.00013 | 0.00002000 | 0 | ||||
Siloxanes and Silicones, di-Me,
reaction products with silica |
67762-90-7 | 0.00001000 | 0 | 0 | ||||
Urea | 57-13-6 | 0.00402 | 0.00054 | 0 | ||||
Dimethyl siloxanes and silicones | 63148-62-9 | 0.00006000 | 0.00001000 | 0 | ||||
Polyethylene glycol monohexyl ether | 31726-34-8 | 0.07293 | 0.00972 | 0 | ||||
Propan-2-ol | 67-63-0 | 0.00064 | 0.00009000 | 0 | ||||
Dodecamethylcyclohexasiloxane | 540-97-6 | 0 | 0 | 0 | ||||
Guar gum | 9000-30-0 | 0.68349 | 0.09109 | 0 | ||||
Diammonium peroxidisulphate | 7727-54-0 | 0.0271 | 0.00361 | 0 | ||||
poly(tetrafluoroethylene) | 9002-84-0 | 0.00003000 | 0 | 0 | ||||
Hydrogen chloride | 7647-01-0 | 0.35883 | 0.04782 | 0 | ||||
Ammonium sulfate | 7783-20-2 | 0.05767 | 0.00769 | 0 | ||||
Octamethylcyclotetrasiloxane | 556-67-2 | 0.00001000 | 0 | 0 | ||||
Non-crystalline silica | 7631-86-9 | 0.00244 | 0.00033 | 0 | ||||
Glutaraldehyde | 111-30-8 | 0.04282 | 0.00571 | 0 | ||||
Prop-2-yn-1-ol | 107-19-7 | 0.00017 | 0.00002000 | 0 | ||||
Alcohols, C14-15, ethoxylated (7EO) | 68951-67-7 | 0.00026 | 0.00003000 | 0 | ||||
Vinylidene chloride/methylacrylate copolymer | 25038-72-6 | 0.00269 | 0.00036 | 0 | ||||
Trisodium ortho phosphate | 7601-54-9 | 0.00386 | 0.00051 | 0 | ||||
Ethanol, 2,2',2-nitrilotris-,
1,1',1-tris(dihydrogen phosphate), sodium salt |
68171-29-9 | 0.00877 | 0.00117 | 0 | ||||
Glycerol | 56-81-5 | 0.05312 | 0.00708 | 0 | ||||
Acrylamide, 2-acrylamido-2-methylpropanesulfonic
acid, sodium salt polymer |
38193-60-1 | 0.06102 | 0.00813 | 0 | ||||
Crystalline silica | 14808-60-7 | 98.2359 | 13.0914 | 0 | ||||
Ethane-1,2-diol | 107-21-1 | 0.0011 | 0.00015 | 0 | ||||
Methanol | 67-56-1 | 0.00092 | 0.00012 | 0 | ||||
Sodium sulfate | 7757-82-6 | 0.02493 | 0.00332 | 0 | ||||
Sodium hydroxide | 1310-73-2 | 0.00001000 | 0 | 0 | ||||
Thiourea, polymer with formaldehyde and 1-phenylethanone | 68527-49-1 | 0.00056 | 0.00007000 | 0 | ||||
Decamethyl cyclopentasiloxane | 541-02-6 | 0 | 0 | 0 |
For data sources see[3]
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | PDC ENERGY INC | Brine | 11525 | 84 |
2014 | PDC ENERGY INC | Brine | 17801 | 286 |
2015 | PDC ENERGY INC | Brine | 4961 | 347 |
2016 | PDC ENERGY INC | Brine | 2687 | 311 |
2017 | PDC ENERGY INC | Brine | 2659 | 345 |
2018 | UTICA RESOURCE OPERATING LLC | Brine | 1096 | 273 |
2019 | UTICA RESOURCE OPERATING LLC | Brine | 320 | 90 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1109395974 | 2014-7-14 0:00: | PL | No Violations | 0.50 |
-1148946949 | 2013-5-8 0:00:0 | DD | No Violations | 9.00 |
-1308184235 | 2013-8-26 0:00: | DD | No Violations | 2.00 |
-1609620486 | 2013-12-13 0:00 | AM | No Violations | 0.30 |
-1622109285 | 2013-4-11 0:00: | DD | No Violations | 2.50 |
-1665097544 | 2013-7-31 0:00: | DD | No Violations | 1.50 |
-1773851228 | 2013-5-31 0:00: | AM | No Violations | 0.50 |
-2024051832 | 2013-6-17 0:00: | DD | No Violations | 1.50 |
-31782615 | 2015-6-22 0:00: | PW | No Violations | 0.50 |
-384235053 | 2013-5-29 0:00: | DD | No Violations | 3.50 |
-392223383 | 2014-7-14 0:00: | PL | No Violations | 1.00 |
-494573884 | 2016-1-26 0:00: | PW | No Violations | 0.50 |
-970301995 | 2013-6-3 0:00:0 | DD | No Violations | 4.50 |
0031782615 | 2015-06-22 | Production Wells | No Violations | Upon inspection, it was observed that this well is currently producing. The well is equipped with a standard production tree and is producing on the 5.5 production casing as well as the 2.875 tubing. Gauges on the well read 366 psi on the tubing and 507 psi on the casing. The tank battery consists of 6 400 bbl production tanks and 3 large mechanical separators. There is also 3 flow control separators on location as well as a large degassing tower. There is a metal, poly lined containment dike around the tank battery. Legible and correct ID information is present on the tanks as well as the entry to the lease road. No violations were observed. |
0384235053 | 2013-05-29 | Drill / Deepen / Reopen | No Violations | Total depth at the time of inspection was 11559 ft. The inclination was 89.66 degrees. The azimuth was 1.94 radians (349.2 degrees). Spoke with consultant on site. |
0392223383 | 2014-07-14 | Preliminary Restoration | No Violations | Upon inspection, it was observed that a vegetative cover has been established throughout the limits of disturbance for this pad location. Any and all drilling equipment has been removed from the location, and any and all pits used for drilling activities have been filled. This satisfies the requirements for the preliminary restoration. Accompanied on this inspection by DOGRM Engineer Jason Simmerman, and DOGRM Engineering Technicians Andy Thomas and Anthony Carson. |
0428449238 | 2013-05-15 | Drill / Deepen / Reopen | No Violations | Conducted status check on this drilling rig. Total depth was 4815 ft. I collected paperwork from the previous cement job, and spoke with Mr. David Gray on site. |
0433926896 | 2017-11-27 | Production Wells | No Violations | The inspection this day found that the well is producing using a plunger lift system. The valves are open on the wellhead and gas could be heard flowing through the well at the time of inspection. The tank battery for this well is equipped with six (6) 410 barrel tanks with identification posted near the tank battery. There are no issues to report and the well is in production. |
0494573884 | 2016-01-26 | Production Wells | No Violations | Upon inspection, it was observed that this well is currently in production. Pressure on the production tubing read 285 psi. No violations noted. I was accompanied on this inspection by DOGRM Emergency Response Coordinator Nathan Lane. |
0674151958 | 2013-05-09 | Drill / Deepen / Reopen | No Violations | Witnessed second half of surface cement job with Inspector Andy Thomas. Circulation established, good returns, pipe raised out of hole 8 feet and unable to set back down. 420 of 20 surface casing was set in 458 of 24 borehole. |
0950932751 | 2013-05-31 | Drill / Deepen / Reopen | No Violations | Received phone call from Mr. Larry Howell at 11:20 pm and he notified me of a drilling mud spill that came out of the flare line. When I arrived on site, crews were already cleaning up the mess. The majority of the drilling mud collected on the drilling pad in the stone. There is a plastic liner under the stone. All contaminated stone was collected and put in a dumpster of residual waste, and hauled to an EPA approved landfill. There was a mist of drilling mud that sprayed the grass outside of the drilling pad in an area 25 ft. long by 15 ft. wide. I spoke with Mr. Vaughn Staple about remedial work on this area. I gave him the options of either removing all contaminated materials and replacing them with clean materials or bio-remediation in place which means tilling the area up and adding lime and fertilizer or manure and working that into the soil. I checked with the consulting mud engineer and the drilling mud is 100% bio-degradable. |
0970301995 | 2013-06-03 | Drill / Deepen / Reopen | No Violations | Inspected remedial work after the drilling mud spill. All contaminated soil had been removed and properly disposed of. Fresh soil had been put in its place. Spoke with consultant on site. He also gave me paperwork for the 5.5 in. casing that they had ran and cemented. |
1109395974 | 2014-07-14 | Preliminary Restoration | No Violations | Upon inspection, it was observed that a vegetative cover has been established throughout the limits of disturbance for this pad location. Any and all drilling equipment has been removed from the location, and any and all pits used for drilling activities have been filled. This satisfies the requirements for the preliminary restoration. Accompanied on this inspection by DOGRM Engineer Jason Simmerman, and DOGRM Engineering Technicians Andy Thomas and Anthony Carson. |
1148946949 | 2013-05-08 | Drill / Deepen / Reopen | No Violations | Witnessed cementing of the surface casing. Good circulation and good returns were achieved. Universal did the cementing work. Pipe floated up out of the hole 8 ft. Bottom of pipe is at 420 ft. |
1308184235 | 2013-08-26 | Drill / Deepen / Reopen | No Violations | Observed coiled tubing unit getting set up to drill plugs out with the accompaniment of Mr. Rick Cisler and Mr. Kenny Brown. Spoke with company man from PDC and from Spartan coiled tubing services. They showed us the tools they will be using and gave us a run-down of how the job will be conducted. |
1334184211 | 2013-08-05 | Drill / Deepen / Reopen | No Violations | Witnessed the perforation and the fracing of one stage. Observed a sample of cross-link gel used as a carrier for proppant. Accompanied on inspection by permitting geologist Rick Cisler, Kenny Brown, and intern Andrew Destocki. |
1368117385 | 2013-05-08 | Drill / Deepen / Reopen | No Violations | Witnessed first half of surface cement job with Inspector Andy Thomas. Circulation established, good returns, pipe raised out of hole 8 feet and unable to set back down. 420 of 20 surface casing was set in 458 of 24 borehole. |
1370263209 | 2013-05-22 | Drill / Deepen / Reopen | No Violations | Stratigraphic test hole had been plugged back. Top of cement should be around 6950. Received paperwork and spoke with Mr. Dave Grey. |
1370434370 | 2013-05-23 | Administrative Inspection | No Violations | Received phone call from Dave Grey at 1:24 pm. He stated that the cement plug for the stratigraphic test hole had falled 200, and he will be placing 200 of cement on top of it to achieve a proper plug. |
1411053385 | 2013-06-11 | Drill / Deepen / Reopen | No Violations | I checked the remediated area outside of the drilling pad. It had been seeded and strawed. A crew was there smoothing the stone on the pad out. Well had a new well head installed on it. |
1559913119 | 2013-04-15 | Drill / Deepen / Reopen | No Violations | Witnessed the topping off of the conductor cement job. Conductor hole drilling crew was de-mobilizing and getting off of location very quickly after that. |
1609620486 | 2013-12-13 | Administrative Inspection | No Violations | Received phone call from Mr. Tony Long from PDC energy at 9:57 am. He stated that an oil trucker didnt get one of the valves completely shut on one of the production tanks and it released 10-15 barrels of oil into the containment around the production tanks. Their containment dike is lined and no oil escaped it. They will have it sucked out as soon as possible. I recommended him calling the EPA and notifying them of the spill but also making sure to tell them that is was completely contained. |
1622109285 | 2013-04-11 | Drill / Deepen / Reopen | No Violations | Met with Mr. Don Kreager at the site. He was waiting on surveyers to plot where the well stake went. They were also in the process of getting the conductor rig ready to drill in the conductor. |
1665097544 | 2013-07-31 | Drill / Deepen / Reopen | No Violations | Checked on site to see how close they were fracing. Pump trucks, blenders, and support vehicles were in place. Mega tanks were being filled with water and several 500 barrel tanks were being filled. Spoke with Don Kreager via cell phone and he stated that they were going to try and frac the next day. |
1773851228 | 2013-05-31 | Administrative Inspection | No Violations | I received a phone call at 12:55 pm from Randall Ferguson from PDCs Denver office in regards to the spill from the night before. He stated that there was a 10 barrel loss and that they removed all contaminated soil, disposed of it properly and replaced it with fresh soil. |
2024051832 | 2013-06-17 | Drill / Deepen / Reopen | No Violations | Company was performing pressure test on 5.5 in. casing. They pressured up to 5000 psi. Spoke with Mr. Blake Roush on site. I also looked at the above ground containment that will be used to store fluid for well stimulation. |
428449238 | 2013-5-15 0:00: | DD | No Violations | 1.00 |
433926896 | 2017-11-27 0:00 | PW | No Violations | |
674151958 | 2013-5-9 0:00:0 | DD | No Violations | 4.90 |
950932751 | 2013-5-31 0:00: | DD | No Violations | 4.50 |
For data sources see[6]