37-003-22115

Well Details

Well ID: 37-003-22115
Loading map...
Country: United States
State: Pennsylvania
County: Allegheny
Municipality: Plum Borough
Operator Name: PENNECO OIL CO INC
Well Pad ID:
Farm/Lease Name: BROOKE 1
License Status:
Spud Date:
Permit Date: 2010-04-02
Well Type: OIL
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.485611
Longitude: -79.713417

For data sources see[1][2][3]

Well History

Date Event
2010-04-02 New Permit Application
2010-04-20 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 PENNECO OIL CO INC 4,136.00 214 198.60 214 0.00 0
2011 PENNECO OIL CO INC 5,875.00 365 250.40 365 0.00 0
2012 PENNECO OIL CO INC 4,151.00 366 124.73 366 0.00 0
2013 PENNECO OIL CO INC 1,915.00 365 0.00 0 0.00 0
2014 PENNECO OIL CO INC 2,316.00 365 102.72 365 0.00 0
2015 PENNECO OIL CO INC 3,063.21 365 190.73 61 0.00 0
2016 PENNECO OIL CO INC 3,018.10 366 103.45 30 0.00 0
2017 PENNECO OIL CO INC 2,689.00 365 104.21 365 0.00 0
2018 PENNECO OIL CO INC 1,098.79 304 81.46 31 0.00 0
2019 PENNECO OIL CO INC 2,490.34 365 1,066.43 31 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 PENNECO OIL CO INC Fracing Fluid Waste 1,360.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2010 PENNECO OIL CO INC Produced Fluid 30.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2010 PENNECO OIL CO INC Drilling Fluid Waste 3,351.71 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 PENNECO OIL CO INC Produced Fluid 16.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2017 PENNECO OIL CO INC Produced Fluid 13.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2017 PENNECO OIL CO INC Produced Fluid 27.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273
2018 PENNECO OIL CO INC Produced Fluid 26.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 PENNECO OIL CO INC Produced Fluid 33.33 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1877589 Primary Facility 2010-04-15 Routine/Complete Inspection No Violations Noted On April 15th, 2010 I conducted a routine inspection of the above site. Site construction was taking place at the time of the inspection. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site.
1882817 Primary Facility 2010-04-20 Drilling/Alteration No Violations Noted DAVE HILL RIG SET UP AND DRILLING @ 85'. SITE AND PIT OK.
1882864 Primary Facility 2010-04-19 Drilling/Alteration No Violations Noted SITE CONSTRUCTED. PIT IS NOT LINED. E&S CONTROLS IN PLACE.
1883330 Primary Facility 2010-04-30 Routine/Complete Inspection No Violations Noted On April 30th, 2010 I conducted a routine inspection of the above site. Drilling had been completed. The frac pit had been constructed and was being filled. The drilling pits appeared to be in good codition. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uniform 70% vegetative cover is reached.
1884488 Primary Facility 2010-04-28 Drilling/Alteration No Violations Noted DRILLING COMPLETE. SITE, AND E&S, OK.
1884497 Primary Facility 2010-04-28 Complaint Inspection No Violations Noted COMPLAINT #271010 FOR ODORS. NO ODORS AT THIS SITE.
1884512 Primary Facility 2010-04-30 Drilling/Alteration No Violations Noted
1884571 Primary Facility 2010-04-22 Drilling/Alteration No Violations Noted DRILLING AT 1859'. SITE, PIT, E&S, AND ACCESS, OK.
1894964 Primary Facility 2010-05-13 Drilling/Alteration No Violations Noted WELL FRACED, RODS AND TUBING IN.SITE NOT RESTORED.
1895044 Primary Facility 2010-06-15 Drilling/Alteration No Violations Noted THE DRILLING IS COMPLETE. THERE IS NO JACK BUT TUBING AND RODS ARE IN.OIL TANK IS SET AND DIKED.SITE IS GRADED BUT NOT SEEDED
1904610 Primary Facility 2010-07-09 Routine/Complete Inspection No Violations Noted On July 9th, 2010 I conducted a routine inspection of the above site. Drilling had been completed and the well was in production. The pits have been closed and filled. The tanks were in place and a dike constructed around them. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site. The site was graded, seeded, and mulched. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uniform 70% vegetative cover is reached.
1912629 Primary Facility 2010-08-02 Routine/Complete Inspection No Violations Noted WELL COMPLETE. JACK IS HOOKED UP. SITE IS RESTORED.
1927314 Primary Facility 2010-10-05 Routine/Complete Inspection No Violations Noted OIL AND GAS WELL. JACK IS OPERATING. SITE RESTORED. TANK WITH A VAPOR FILTER. ALL EQUIPTMENT FENCED.
1947177 Primary Facility 2011-01-07 Routine/Complete Inspection No Violations Noted OIL & GAS WELL. TANKS WITH VAPOR FILTERS. EQUIPTMENT FENCED AND LOCKED. SITE AND ACCESS STONED.
2054286 Primary Facility 2012-03-13 Routine/Complete Inspection No Violations Noted THIS OIL AND GAS WELL IS IN GOOD CONDITION.

For data sources see[7]

References