37-003-22308

Well Details

Well ID: 37-003-22308
Loading map...
Country: United States
State: Pennsylvania
County: Allegheny
Municipality: Frazer Township
Operator Name: RANGE RESOURCES APPALACHIA LLC
Well Pad ID:
Farm/Lease Name: GULICK UNIT 4H
License Status:
Spud Date:
Permit Date: 2014-09-15
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.617786
Longitude: -79.803469

For data sources see[1][2][3]

Well History

Date Event
2014-09-15 New Permit Application

For data sources see[4]



Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2379667 Primary Facility 2015-06-02 Routine/Complete Inspection No Violations Noted On 6/02/15, I inspected the Gulick Unit and made the following observations:
2379807 Primary Facility 2015-06-05 Follow-up Inspection No Violations Noted On 6/5/15, I inspected the Gulick site as a follow up to the 6/2/15 inspection of the site and made the following observations:
2379990 Primary Facility 2015-06-09 Follow-up Inspection No Violations Noted On 6/9/15, I inspected the Gulick site as a follow up to previous inspections of the site on 6/2/15 & 6/5/15 and made the following observations:
2380926 Primary Facility 2015-06-16 Incident- Response to Accident or Event No Violations Noted On 6/16/15, I inspected the Gulick site in response to an operator reported incident and made the following observations:
2381810 Primary Facility 2015-06-19 Follow-up Inspection No Violations Noted On 6/19/15, I inspected the Gulick site as a follow up to a prior incident inspection and made the following observations:
2390614 Primary Facility 2015-07-17 Preoperation Inspection No Violations Noted On 7/16/15, I inspected the Gulick site for its preoperation inspection and made the following observations:
2395019 Primary Facility 2015-07-28 Follow-up Inspection No Violations Noted On 7/28/15, I inspected the Gulick site as a follow up to a previous inspection and made the following observations:
2414934 Primary Facility 2015-10-02 Routine/Complete Inspection No Violations Noted On 10/2/15, I performed a routine inspection for the Gulick site as a follow up to previous inspections and made the following observations:
2484601 Primary Facility 2016-01-04 Routine/Partial Inspection No Violations Noted On 1/4/16, I performed a routine partial inspection at the Gulick site and made the following observations:

•Landslides/slumps along the access road have not been remediated but have do not seem to have gotten worse. No violation. •A small drilling rig and associated equipment was on site at the time of inspection.

2485989 Primary Facility 2016-01-22 Incident- Response to Accident or Event In Compliance with Policy On 1/22/16, I performed an incident inspection at the Gulick site in response to a spill report received that morning and made the following observations:

•Per the operator a hose disconnected/was not connected properly while transferring reuse water between from a truck to a storage tank allowing roughly 50 gallons to spill out of containment and onto ice on the pad. Of the 50 gallons spilled roughly half was reported to have been immediately removed via vacuum truck before the ice was melted. The remaining amount was to be removed once the pad thawed (pad surface was hard frozen at the time of inspection).

2486298 Primary Facility 2016-04-07 Compliance Evaluation No Violations Noted On 4/7/16, I performed a compliance evaluation inspection at the Gulick site in response to a spill report received 1/22/16 and made the following observations:

•Visual inspection indicated that the spill was fully remediated; vegetation near location of spill was not visibly impacted. •The operator provided receipts from Weavertown Environmental detailing materials removed and disposed. •The containment and storage tanks where the spill occurred had been removed at the time of the inspection.

2514395 Primary Facility 2016-04-19 Routine/Partial Inspection No Violations Noted On 4/19/16, I performed a routine partial inspection at the Gulick site in response to an operator request for review of a minor modification and made the following observations:

•The operator reported that the landowner was requesting access to a vegetated slope below the well pad and needed a pipe and gravel crossing be added to an existing roadside culvert to allow access. This request was approved as a minor modification. •The vegetation cut slope north of the site entrance continues to be sparse with a number of small slumps present. No violation. •Two erosion channels along the access road have been repaired with rock linings. No violation.

For data sources see[5]