Well ID: 37-005-30252 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.779442,"lon":-79.589461,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Armstrong | |
Municipality: North Buffalo Township | |
Operator Name: MDS ENERGY DEV LLC | |
Well Pad ID: | |
Farm/Lease Name: RANDY J GRANTZ | |
License Status: Active | |
Spud Date: 2009-03-02 | |
Permit Date: 2009-02-20 | |
Well Type: GAS | |
Unconventional Well: N | |
Configuration: Vertical Well | |
Conservation: No | |
Latitude: 40.779442 | |
Longitude: -79.589461 |
Date | Event |
---|---|
2009-02-20 | New Permit Application |
2009-03-02 | Performed Spud Operation |
2009-03-04 | Drilling Completion |
2009-09-10 | Newly Drilled |
2011-06-28 | New Permit Application |
2013-06-07 | New Permit Application |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2010 | MDS ENERGY LTD | 6,418.00 | 258 | 0.00 | 0 | 0.00 | 0 |
2011 | MDS ENERGY LTD | 2,045.00 | 230 | 0.00 | 0 | 0.00 | 0 |
2012 | MDS ENERGY LTD | 1,481.00 | 293 | 0.00 | 0 | 0.00 | 0 |
2013 | MDS ENERGY LTD | 834.00 | 132 | 0.00 | 0 | 0.00 | 0 |
2014 | MDS ENERGY LTD | 4,901.00 | 116 | 0.00 | 0 | 0.00 | 0 |
2015 | MDS ENERGY DEV LLC | 6,692.00 | 364 | 0.00 | 0 | 0.00 | 0 |
2016 | MDS ENERGY DEV LLC | 4,033.00 | 334 | 0.00 | 0 | 0.00 | 0 |
2017 | MDS ENERGY DEV LLC | 3,758.00 | 352 | 0.00 | 0 | 0.00 | 0 |
2018 | MDS ENERGY DEV LLC | 3,110.00 | 308 | 0.00 | 0 | 0.00 | 0 |
2019 | MDS ENERGY DEV LLC | 2,716.00 | 325 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2014 | MDS ENERGY LTD | Fracing Fluid Waste | 630.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0095443 |
2014 | MDS ENERGY LTD | Fracing Fluid Waste | 630 Bbl | CENT WASTE TRT FAC NPDES | PA0095443 |
2014 | MDS ENERGY LTD | Produced Fluid | 162 Bbl | CENT WASTE TRT FAC NPDES | PA0095443 |
2014 | MDS ENERGY LTD | Produced Fluid | 162.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0095443 |
2015 | MDS ENERGY DEV LLC | Produced Fluid | 26 Bbl | CENT WASTE TRT FAC NPDES | PA0095273 |
2015 | MDS ENERGY DEV LLC | Produced Fluid | 26.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0095273 |
2019 | MDS ENERGY DEV LLC | Produced Fluid | 89.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0095273 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
1774281 | Primary Facility | 2009-03-06 | Compliance Evaluation | No Violations Noted | No accelerated erosion & sedimentation was noted during the site inspection. Observed that the operator had implemented additional erosion control measures as outlined in the operator response sent on 02/12/09. These additional measures should effectively minimize accelerated erosion & sedimentation provided they are properly maintained. |
1973885 | Primary Facility | 2011-05-17 | Routine/Complete Inspection | No Violations Noted | Well is equipped for production. Tag located. There is no evidence of erosion or sedimentation on the well site or access road. |
1984167 | Primary Facility | 2011-06-16 | Routine/Complete Inspection | No Violations Noted | Operator submitted Application for Drilling or Altering a Well (Deepen a well- Proposed 5000' TD) dated 05-16-11. |
2208319 | Primary Facility | 2013-09-17 | Complaint Inspection | No Violations Noted | Well shut in on 7” x 2” swage. 15 psig on wellhead at time of inspection. At surface, zero percent (0%) of gas measured (MSA 62S combustible gas indicator) outside 9 5/8” conductor casing and within 9 5/8” x 7” annulus. Pit lined and freeboard maintained. Inspection conducted w/WQS G. Higgins. |
2226686 | Primary Facility | 2013-12-05 | Routine/Complete Inspection | No Violations Noted | Drilling appeared to have been completed. Site and access road controls had been implemented properly and there was no observed evidence of accelerated erosion or sedimentation in relation to the site or access road. Drill pit located onsite and it contained fluids and drill cuttings. The drill pit had more than the required two feet of lined freeboard. |
2266943 | Primary Facility | 2014-04-30 | Routine/Complete Inspection | No Violations Noted | Drilling appeared to have been completed, well was not equipped for production. Drill pit located onsite and it contained drill cuttings and fluids. Drill pit had more than two feet of lined freeboard. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that the acess road leaving the site required routine maintenance to prevent any erosion issues from developing. |
2279139 | Primary Facility | 2014-06-17 | Routine/Complete Inspection | No Violations Noted | Drilling appeared to have been completed, well was not equipped for production. Drill pit located onsite and it contained drill cuttings and fluids. Drill pit had more than two feet of lined freeboard. There was no observed accelerated erosion or sedimentation in relation to the site or access road. Met onsite with operator representative Tyler Krukar to review the proposed site restoration extension and existing erosion controls. |
2307054 | Primary Facility | 2014-09-25 | Routine/Complete Inspection | No Violations Noted | Well appeared to be equipped for production. Brine tank located onsite and it appeared to be in sound condition. Site had been regraded, seeded, mulched and the vegetation met 70% uniform coverage. There was no observed accelerated erosion or sedimenation in relation to the site or access road. |
2776725 | Primary Facility | 2018-09-19 | Routine/Complete Inspection | No Violations Noted | This well is tagged and in production. The annulus is open. The well head casing, piping, equipment, pump jack and grounded 100 bbl fiberglass fluid collection tank look ok.
Note: I checked the open annulus and the immediate area around this well for gas leaks utilizing a calibrated Altair 5X Meter and all readings came back at non-detect for the presence of any gas. |
For data sources see[7]