Well Details

Well ID: 37-005-30945
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: Washington Township
Operator Name: MDS ENERGY DEV LLC
Well Pad ID: 146030
Farm/Lease Name: WILLIAM & PHILIP MCAULEY 1M-D
License Status:
Spud Date:
Permit Date: 2011-12-09
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: Yes
Latitude: 40.926208
Longitude: -79.528344

For data sources see[1][2][3]

Well History

Date Event
2011-12-09 New Permit Application
2012-03-21 Performed Spud Operation
2012-07-29 Drilling Completion
2013-02-27 New Permit Application
2013-07-01 Drilling Completion
2013-07-22 Perforation
2014-04-10 DRILLED DEEPER
2014-04-10 NEWLY DRILLED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2013-07-22 2013-07-22 6,268 97,027 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 HCL Acid (0%-7.5%) Nabors Completion and Production Services Bulk Acid Hydrogen Chloride 7647-01-0 7 0.019114 0
Other Ingredients Nabors Completion and Production Services Other Ingredients Polymer Proprietary 10 0.0142433 0
Alkyl Phosphate Ether Proprietary 1 0.00142422 0
Ammonium salts Proprietary 100 0.0284866 0
Water 7732-18-5 48 0.000246604 0
Dioxane 123-91-1 1 0.00000543 0
Demineralized Water 7732-18-5 50 0.000562736 0
Polymer Proprietary 1 0.00142422 0
Monoethanolamine Proprietary 100 0.00142422 0
Phosphoric Acid 7664-38-2 100 0.00142422 0
Proprietary Proprietary 50 0.00290602 0
Solvent Proprietary 1 0.00142422 0
Anionic Polyacrylamide 910644-97-2 40 0.0393415 0
ammonium, (2-Hydroxyethyl)trimethyl-, chloride 67-48-1 80 0.000900594 0
Water 7732-18-5 60 0.00348614 0
Proprietary Proprietary 2 0.0019674 0
Proprietary Proprietary 1 0.00142422 0
Proprietary Proprietary 100 0.142433 0
Water 7732-18-5 40 0.0393415 0
Propylene glycol 57-55-6 15 0.0147528 0
Water 7732-18-5 80 0.00505593 0
2-Butoxyethanol 111-76-2 13 0.00006735 0
Proprietary Proprietary 15 0.000871262 0
Water 7732-18-5 50 0.0712165 0
WFR-3B Nabors Completion and Production Services Friction Reducer Mineral Spirits 8052-41-3 10 0.009904 0
Ethoxylated Alcohols 68551-12-2 4 0.003962 0
Hydrotreated light distillates, non-aromatic, BTEX free 64742-47-8 30 0.029713 0
Propylene Glycol 57-55-6 25 0.024761 0
KR-153SL Nabors Completion and Production Services Biocides Polyethlyene-Glycol 25322-68-3 50 0.003349 0
2,2-dibromo-3-nitrilopropionamide 10222-01-2 20 0.00134 0
Sand Nabors Completion and Production Services Sand - Bulk - Pennsylvania Crystalline Silica, quartz 14808-60-7 99.9 22.5133 0
Nitrogen per MSCF Nabors Completion and Production Services Nitrogen Materials Nitrogen 7727-37-9 100 26.6302 0
ICP-1000 Nabors Completion and Production Services Iron Control Additives Anionic Copolymer Proprietary 50 0.006002 0
Propylene glycol 57-55-6 50 0.006002 0
Super 100 NE Nabors Completion and Production Services Surfactants & Foamers N-Cocoamidopropyl-N,N-dimethyl-N-2-hydroxypropylsulfobetaine
68139-30-0 15 0.020634 0
Isopropyl Alcohol 67-63-0 40 0.055025 0
2-Butoxyethanol 111-76-2 5 0.006878 0
methyl alcohol 67-56-1 15 0.020634 0
Acid Inhibitor 2 (AI-2) Nabors Completion and Production Services Acid Corrosion Inhibitors Propargyl Alcohol 107-19-7 40 0.000408 0
Tar bases, quinoline derivs, benzyl chloride-quaternized 72480-70-7 10 0.000102 0
Isopropyl Alcohol 67-63-0 40 0.000408 0
Ethoxylated Nonylphenol 68412-54-4 13 0.000133 0
Glycol Ethers 111-46-6 40 0.000408 0
Water MDS Energy LTD Water Water 7732-18-5 100 49.9894 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2011 MDS ENERGY LTD 0.00 0 0.00 0 0.00 0
2012 MDS ENERGY LTD 0.00 0 0.00 0 0.00 0
2013 MDS ENERGY DEV LLC 6,762.00 98 0.00 0 0.00 0
2014 MDS ENERGY DEV LLC 8,385.00 364 0.00 0 0.00 0
2015 MDS ENERGY DEV LLC 3,170.30 356 0.00 0 0.00 0
2016 MDS ENERGY DEV LLC 2,291.20 311 0.00 0 0.00 0
2017 MDS ENERGY DEV LLC 2,048.90 316 0.00 0 0.00 0
2018 MDS ENERGY DEV LLC 1,701.00 354 0.00 0 0.00 0
2019 MDS ENERGY DEV LLC 1,318.00 339 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2012 MDS ENERGY LTD Drilling Fluid Waste 270.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE EPA ID: 748-163
2012 MDS ENERGY LTD Fracing Fluid Waste 240.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE EPA ID: 748-163
2013 MDS ENERGY DEV LLC Produced Fluid 80.00 Bbl INJECTION DISPOSAL WELL 34-155-23759
2013 MDS ENERGY DEV LLC Fracing Fluid Waste 2,275.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW006
2013 MDS ENERGY DEV LLC Produced Fluid 680.00 Bbl INJECTION DISPOSAL WELL 34-155-23223
2013 MDS ENERGY DEV LLC Produced Fluid 80.00 Bbl INJECTION DISPOSAL WELL 34-155-21438
2013 MDS ENERGY DEV LLC Fracing Fluid Waste 160.00 Bbl INJECTION DISPOSAL WELL 34-155-23223
2013 MDS ENERGY DEV LLC Fracing Fluid Waste 160.00 Bbl INJECTION DISPOSAL WELL 34-155-23759
2014 MDS ENERGY DEV LLC Produced Fluid 88.00 Bbl INJECTION DISPOSAL WELL 34-155-21438
2014 MDS ENERGY DEV LLC Produced Fluid 210.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW009

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2052424 Primary Facility 2012-03-21 Routine/Complete Inspection No Violations Noted Site construction had commenced at the time of inspection. No accelerated erosion noted on the well pad or access road. The E&S plan was on site and being implemented at the time of inspection.
2086943 Primary Facility 2012-07-27 Routine/Complete Inspection No Violations Noted The Department notes that the day before the inspection the site received a very significant precipitation event. At the time of inspection the site appeared to be in sound condition. No observation of accelerated erosion or sedimentation in relation to the well pad or access road leaving the site at the time of inspection. The site was temporary stabilized and all erosion and sedimentation BMP's were properly installed and maintained. The pit located onsite appeared to be sound condition and had the required 2 feet of freeboard. The Department suggest the Operator continue to monitor the site weekly and after significant precipitation event to ensure the E&S controls are maintained.
2127669 Primary Facility 2013-01-02 Routine/Complete Inspection No Violations Noted Site was covered with approximately 6 inches of snow. Drilling had been completed but site was not equipped for production. E&S controls were implemented in accordance with the on-site E&S plan and appeared adequate. Site had not yet been restored; soil pile and flow back pit were still present. Liner of the pit appeared to be in good condition.
2128483 Primary Facility 2013-01-07 Drilling/Alteration No Violations Noted Well open on 7” x 2” swage and venting gas out installed vent pipe (moderate expression). Pit on location lined and freeboard maintained.
2160620 Primary Facility 2013-04-23 Routine/Complete Inspection No Violations Noted Site and access road controls had been implemented properly and there was no observed evidence of accelerated erosion or sedimentation in relation to the site or access road. Drill pit located onsite and it had more than the required two feet of lined freeboard.
2176332 Primary Facility 2013-06-18 Routine/Complete Inspection No Violations Noted Site and access road controls had been implemented properly and there was no observed evidence of accelerated erosion or sedimentation in relation to the site or access road. Drill pit located onsite and it had more than the required two feet of lined freeboard. Well did not appear to have been stimulated. Well appeared to be equipped for natural production.
2182331 Primary Facility 2013-07-01 Drilling/Alteration No Violations Noted Tripping out of hole at time of inspection. Waiting to log hole before running 4 1/2” production casing.
2235439 Primary Facility 2014-01-10 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. Site had been regraded and the vegetative cover appeared to meet the 70% uniform coverage criteria. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2340600 Primary Facility 2015-02-03 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. There was no observed accelerated erosion or sedimentation in relation to the site or access road. Brine tanks located onsite and they appeared to be in sound condition.
2394451 Primary Facility 2015-07-31 Site Restoration No Violations Noted ell appeared to be equipped for production. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that the area surrounding the well-head had been returned to agricultural crop activities. Brine tanks located onsite and they appeared to be in sound condition.
2680297 Primary Facility 2018-01-09 Routine/Complete Inspection No Violations Noted This well is tagged and in production. The well head casing, production set equipment and two grounded 100 bbl fiberglass tanks look ok.