37-005-31161

Well Details

Well ID: 37-005-31161
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: Parks Township
Operator Name: BAKER GAS INC
Well Pad ID: 150078
Farm/Lease Name: ALAN L SUMMERHILL ET UX 1
License Status:
Spud Date:
Permit Date: 2013-08-21
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.655794
Longitude: -79.503861

For data sources see[1][2][3]

Well History

Date Event
2013-08-21 New Permit Application
2013-11-07 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2013 0.00 0 0.00 0 0.00 0
2014 2,064.00 298 0.00 0 0.00 0
2015 1,099.00 365 0.00 0 0.00 0
2016 993.00 326 0.00 0 0.00 0
2017 739.00 294 0.00 0 0.00 0
2018 967.00 327 0.00 0 0.00 0
2019 800.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2013 Drilling Fluid Waste 250 Bbl CENT WASTE TRT FAC NPDES PA0095443
2013 Drilling Fluid Waste 250.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2219492 Primary Facility 2013-11-06 Routine/Complete Inspection No Violations Noted Drilling had not commeced. The E&S plan had been implemented as compiled and there was no observed accelerated erosion or sedimentation in relation to the site or the access road.
2222007 Primary Facility 2013-11-06 Drilling/Alteration No Violations Noted no drilling:notif OK
2225962 Primary Facility 2013-12-03 Routine/Complete Inspection No Violations Noted Drilling appeared to have been completed and the well was not equipped for production. Drill pit had been regraded. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All erosion controls appeared to be functioning properly. The Department recommends that the operator temporarily stabilize the cut and fill slopes in accordance with PA Code 25 Chapeter 102.22.
2235749 Primary Facility 2014-01-13 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Site had been effectively regraded and temporarily stabilized. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that the culvert in place to convey water from above the well pad, and off the recently instaled pipeline, to below the well pad required maintenance at both the culvert inlet and outlet after recent precipitation events. If the pipeline is left without temporary stabilization and the culvert inlet and outlet are not addressed there is a potential for an erosion issue to develop with this specific area.
2254159 Primary Facility 2014-03-17 Routine/Complete Inspection Violation(s) Noted Well appeared to be equipped for production. Site had been effectively regraded and temporarily stabilized. The areas around the inlet and outlet of the culvert implemented to convey water under the pad and access road had not been addressed. These areas were outlined as an area of concern in an inspection dated 01/13/14. Specifically the pipeline area had not been temporarily stabilized and the culvert inlet had not been stabilized. In addition the culvert outlet flow had knocked down the silt fencing implemented below the site and sediment had been transported offsite.
2259546 Primary Facility 2014-04-04 Follow-up Inspection Outstanding Violations - No Viols Req'd Well appeared to be equipped for production. Site had been effectively regraded and temporarily stabilized. Inspection performed as follow-up to the documentation recieved from the operator on April 1, 2014 as a response to the previously issued NOV. The E&S controls implemented as outlined in the documenation are ineffective at minimizing accelerated erosion & sedimenation. Specifically the spring flow inlet area had not been stabilized. The flow could either be captured via a culvert, diverted around the disturbed area and into a culvert or conveyed via a rocked and stabilized channel to the culvert inlet. In addition the outlet required additional rock to convey the flow past the disturbed area and the perimeter controls. Hay bales and silt fencing are not recommended erosion controls that are to be utilized in areas of concentrated direct flow as outlined in the Department's E&S manual.
2269810 Primary Facility 2014-05-12 Compliance Evaluation No Violations Noted Well appeared to be equipped for production. Site had been effectively regraded and temporarily stabilized. Inspection performed as follow-up to the documentation recieved from the operator on April 1, 2014 as a response to the previously issued NOV and a subsequent onsite meeting with Tim Baker from Baker Gas. The upgradient portion of the runoff flow above the well-site had been stabilized with rock, as had the outlet portion of the culvert which conveyed runoff underneath the well pad.
2357484 Primary Facility 2015-03-31 Site Restoration No Violations Noted Well was equipped for production. Site had been effectively regraded and the vegetative cover had attained 70% uniform coverage criteria. There was no observed accelerated erosion or sedimentation in relation to the site or access road. WQS Higgins observed that a logging operation had been utilizing the access road as a skidding. This activity has resulted in the access road requiring routine maintenance.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2254159 691049 03/17/2014 2014-03-17 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) Environmental Health & Safety 102.11

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
691049 308730 NOV - Notice of Violation

For data sources see[7]