37-007-20437

Well Details

Well ID: 37-007-20437
Loading map...
Country: United States
State: Pennsylvania
County: Beaver
Municipality: New Sewickley Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 151096
Farm/Lease Name: BEAVER PAD 5
License Status:
Spud Date:
Permit Date: 2014-07-24
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 40.758740
Longitude: -80.217937

For data sources see[1][2][3]

Well History

Date Event
2014-07-24 New Permit Application
2015-01-06 Performed Spud Operation
2015-12-03 New Permit Application

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2016-06-06 2016-06-11 4,800 10,669,900 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 87.1961 91,203,900.0
TRS 11800, TRS 3001, EC6111A TightRock Solutions Frac Fluid Additives Sodium Phosphate, Tribasic 7601-54-9 5 0.000975921 1020.78
Methanol 67-56-1 1 0.000187576 196.198
Amine Triphosphate Proprietary 30 0.00585553 6124.66
Inorganic Salt Proprietary 10 0.0075909 7939.8
Alkyl Alcohol Proprietary 10 0.0075909 7939.8
Oxyalkylated Alcohol Proprietary 5 0.00379545 3969.9
Ethylene Glycol 107-21-1 5 0.000975921 1020.78
Hydrotreated Light Distillate 64742-47-8 30 0.0227727 23819.4
Glutaraldehyde 111-30-8 30 0.00562728 5885.93
Hydrochloric Acid (7.5%) Axiall Acidizing Hydrogen Chloride 7647-01-0 40 0.793009 829458
LEB 10X Weatherford Gel Breaker Ethylene Glycol 107-21-1 40 0.00000730 7.636
Unihibitor G GeoSafe Acid Corrosion Inhibitor Acetophenone 98-86-2 1 0.00000653 6.83
Ethoxylated Alcohol 68002-97-1 35 0.00022853 239.034
Methanol 67-56-1 5 0.00003265 34.148
Glycol Ether 112-34-5 60 0.000391766 409.773
Formaldehyde 50-00-0 1 0.00000653 6.83
Thiourea 62-56-6 1 0.00000653 6.83
WGA-3 PfP Technology Water Viscosifier Guar Gum 9000-30-0 100 0.00066924 700
Sand (Proppant) Sargent Proppant Silica 14808-60-7 99.9 10.6951 11,186,700.0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2015 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2016 PENNENERGY RESOURCES LLC 371,756.00 151 0.00 0 8,731.00 151
2017 PENNENERGY RESOURCES LLC 702,932.00 339 0.00 0 10,302.00 339
2018 PENNENERGY RESOURCES LLC 544,734.00 354 0.00 0 6,140.00 354
2019 PENNENERGY RESOURCES LLC 448,138.00 351 0.00 0 3,488.00 351

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2015 PENNENERGY RESOURCES LLC Drill Cuttings 728.78 Tons LANDFILL CID # 28726
2016 PENNENERGY RESOURCES LLC Fracturing Fluid Waste 26.41 Tons LANDFILL CID # 28726
2016 PENNENERGY RESOURCES LLC Produced Fluid 767.69 Bbl INJECTION DISPOSAL WELL 34-155-22403
2016 PENNENERGY RESOURCES LLC Produced Fluid 25.00 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Synthetic Liner Materials 0.33 Tons LANDFILL CID # 28726
2016 PENNENERGY RESOURCES LLC Produced Fluid 2,299.60 Bbl INJECTION DISPOSAL WELL 34-155-23795
2016 PENNENERGY RESOURCES LLC Produced Fluid 576.98 Bbl INJECTION DISPOSAL WELL 34-155-23223
2016 PENNENERGY RESOURCES LLC Fracturing Fluid Waste 39.63 Tons LANDFILL UT2300249
2016 PENNENERGY RESOURCES LLC Produced Fluid 5,986.88 Bbl INJECTION DISPOSAL WELL 34-155-23196
2016 PENNENERGY RESOURCES LLC Produced Fluid 18,761.60 Bbl REUSE OTHER THAN ROAD SPREADING
2016 PENNENERGY RESOURCES LLC Produced Fluid 25.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Produced Fluid 284.81 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC 31.14 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC Produced Fluid 25.00 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2017 PENNENERGY RESOURCES LLC 21.95 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 31.14 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC Servicing Fluid 8.67 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 224.18 Bbl INJECTION DISPOSAL WELL 34-155-23223
2017 PENNENERGY RESOURCES LLC 224.18 Bbl INJECTION DISPOSAL WELL 34-155-23223
2017 PENNENERGY RESOURCES LLC 176.61 Bbl INJECTION DISPOSAL WELL 34-155-23196
2017 PENNENERGY RESOURCES LLC 80,983.79 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Produced Fluid 25.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2017 PENNENERGY RESOURCES LLC Synthetic Liner Materials 13.28 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 176.61 Bbl INJECTION DISPOSAL WELL 34-155-23196
2017 PENNENERGY RESOURCES LLC Produced Fluid 78,109.27 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Produced Fluid 2,012.73 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Produced Fluid 27.50 Bbl INJECTION DISPOSAL WELL 34-155-22403
2019 PENNENERGY RESOURCES LLC Produced Fluid 60.69 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 PENNENERGY RESOURCES LLC Produced Fluid 34.69 Bbl INJECTION DISPOSAL WELL 34-155-22403
2019 PENNENERGY RESOURCES LLC Produced Fluid 279.62 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 1,427.21 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Produced Fluid 147.90 Bbl INJECTION DISPOSAL WELL 34-155-23196

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2305071 Primary Facility 2014-09-05 Preoperation Inspection No Violations Noted This preoperational inspection satisfies operator's obligation as outlined under Title 58 , Ch 32 § 3258 a. 1.
2342016 Primary Facility 2015-01-06 Drilling/Alteration No Violations Noted A TRACK RIG IS DRILLING AND INSTALLING 40' OF 16" CONDUCTOR.
2378791 Primary Facility 2015-06-02 Routine/Complete Inspection No Violations Noted
2380746 Primary Facility 2015-06-02 Drilling/Alteration No Violations Noted HIGHLANDS RIG 9 IS READY TO PULL DRILL RODS, THEN RUN AND CEMENT 624' OF 113/4" CASING. THE SITE IS IN GOOD CONDITION.
2381741 Primary Facility 2015-06-19 Routine/Complete Inspection No Violations Noted
2381961 Primary Facility 2015-06-02 Drilling/Alteration No Violations Noted HIGHLANDS 9 IS READY TO PULL DRILL RODS, THEN RUN AND CEMENT THE 113/4" CASING.
2381969 Primary Facility 2015-06-11 Drilling/Alteration No Violations Noted TOP HOLE DRILLING IS COMPLETE AT 2,293'.
2390979 Primary Facility 2015-07-08 Drilling/Alteration No Violations Noted TOP HOLE IS DONE. THE RIG IS GONE. THE PAD IS COVERED.
2418403 Primary Facility 2015-10-01 Drilling/Alteration No Violations Noted TOP HOLE DRILLING IS COMPLETE. THE AREA AROUND THE WELL IS COVERED. THE PAD IS FENCED AND LOCKED.
2428029 Primary Facility 2015-11-20 Routine/Complete Inspection No Violations Noted
2436882 Primary Facility 2015-12-29 Routine/Complete Inspection No Violations Noted
2449907 Primary Facility 2016-01-11 Drilling/Alteration No Violations Noted THE HORIZONTAL PORTION OF THIS WELL IS COMPLETE, AND THE RIG IS GONE. THE WELL IS COVERED WITH A STEEL PLATE. THE SITE IS IN GOOD CONDITION.
2467242 Primary Facility 2016-03-22 Routine/Complete Inspection No Violations Noted
2468824 Primary Facility 2016-03-15 Drilling/Alteration No Violations Noted THIS WELL IS DRILLED BUT NOT FRACED. THE WELL IS SHUT IN WAITING FOR FRAC JOB.
2468841 Primary Facility 2016-03-23 Drilling/Alteration No Violations Noted A BOND LOG WAS RUN. CASING PRESSURE TESTING ON THE SITE IS ALMOST COMPLETE.

THE SITE IS IN GOOD CONDITION.

2469248 Primary Facility 2016-03-29 Drilling/Alteration No Violations Noted A BOND LOG WAS DONE AND CASING PRESSURE TESTING IS COMPLETE.

CUD ENERGY SERVICES ONSITE PREPARING WELLS FOR FRACING.

2477581 Primary Facility 2016-04-20 Drilling/Alteration No Violations Noted THIS WELL HAS BEEN PRESSURE TESTED AND LOGGED. THE WELL IS NOT FRACED.

THE SITE IS IN GOOD CONDITION.

2478908 Primary Facility 2016-04-22 Routine/Complete Inspection No Violations Noted
2480592 Primary Facility 2016-04-06 Drilling/Alteration No Violations Noted 1H HAS BEEN PRESSURE TESTED. THE WELL WILL BE FRACED LATER.

THE SITE IS IN GOOD CONDITION.

2501652 Primary Facility 2016-07-11 Routine/Complete Inspection No Violations Noted
2508632 Primary Facility 2016-06-07 Drilling/Alteration No Violations Noted STAGE 4 OF 30 IS BEING FRACED.

THE SITE IS IN GOOD CONDITION.

2521471 Primary Facility 2016-09-21 Routine/Complete Inspection No Violations Noted
2542659 Primary Facility 2016-11-17 Routine/Complete Inspection No Violations Noted
2559982 Primary Facility 2017-02-09 Routine/Complete Inspection No Violations Noted On 2/9/17, WQS Brian MacQuarrie onsite at unconventional well site. Act 9 sign in place. Erosion and Sedimentation Plan in mailbox. Four wells in production. Two four hundred bbl tanks installed within stainless steel secondary containment. Temporary AST setup onsite used for stimulation of wells. Freshwater impoundment fenced in. Erosion and Sedimentation Best Management Practices installed and maintained including compost filter sock and sediment trap. Site stabilized with vegetative growth. No apparent E/S issues. Light snow covering on ground during inspection.
2564556 Primary Facility 2017-02-24 Routine/Complete Inspection No Violations Noted On 2/24/2017, WQS Brian MacQuarrie onsite at unconventional well site. Act 9 sign in place. Erosion and Sedimentation Plan in mailbox. Four wells properly tagged and in production. Two four hundred bbl tanks installed within stainless steel secondary containment. Temporary AST containing impaired water removed from site. Four clamshell and one frac tank onsite within secondary containment. Two rolloffs containing residual waste ( plastic liners and hdpe pipe) awaiting disposal. Secondary containment installed around well heads removed. Freshwater impoundment fenced in. Erosion and Sedimentation Best Management Practices installed and maintained including compost filter sock and sediment trap. Site stabilized with vegetative growth. No apparent E/S issues.
2633392 Primary Facility 2017-09-07 Routine/Complete Inspection No Violations Noted On 9/07/2017, WQS Brian MacQuarrie onsite at unconventional well site. Four wells in production. Truck onsite transferring fluids from production tanks. Two 400 bbl tanks in containment. Erosion and Sedimentation best management practices installed and maintained including sediment trap. Majority of site well vegetated. Small area along access road needs to be re-seeded. No apparent E/S issues.
2667467 Primary Facility 2017-12-05 Routine/Complete Inspection No Violations Noted Site had been constructed as outlined in the E&S plan contained within the ESCGP. All site and access road erosion controls had been implemented and properly maintained. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All disturbed areas had been stabilized with vegetation attaining 70% uniform vegetative cover. The well appeared to be equipped for production. Two brine tanks located onsite within containment. Both the tanks and the containment appeared to be in sound condition.
2687681 Primary Facility 2018-01-29 Routine/Complete Inspection No Violations Noted Site and access road had been constructed in accordance with the ESCGP. All site and access road erosion controls had been implemented and maintained properly. All disturbed slopes and soil stockpiles had been stabilized with vegetation. There was no observed accelerated erosion or sedimentation in relation to the site or access road. There was an Act 9 sign located onsite in accordance with 25 Pa Code Chapter 78a.55(i). Well appeared to be equipped for production. Two brine tanks were located onsite within secondary containment. Both the tanks and containment appeared to be in sound condition. Well development impoundment located onsite and it appeared to contain withdrawn water and accumulated precipitation.
2768203 Primary Facility 2018-08-28 Routine/Complete Inspection No Violations Noted This well and all other equipment on the pad are in good condition.