Well Details

Well ID: 37-019-21476
Loading map...
Country: United States
State: Pennsylvania
County: Butler
Municipality: Allegheny Township
Operator Name: EM ENERGY PA LLC
Well Pad ID: 146023
Farm/Lease Name: R BLAUSER TRUST
License Status: Plugged and Abandoned
Spud Date: 2007-12-19
Permit Date: 2007-06-28
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: No
Latitude: 41.122805
Longitude: -79.753513

For data sources see[1][2][3]

Well History

Date Event
2007-06-28 New Permit Application
2007-12-18 Performed Spud Operation
2007-12-28 Drilling Completion
2008-05-15 Perforation
2008-05-19 Performed Stimulation
2008-09-26 Newly Drilled
2017-11-17 Begin Plugging
2017-11-28 Finished Plugging
2018-06-29 Partially Plugged

For data sources see[4]

Stimulation Data

Stimulation Date Phase Number Chemical Agent Volume (gal) Treating Pressure (psi) Breakdown Pressure (psi)
2008-05-19 Sand 0 0 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2009 BLX INC 13597.00 116 98.00 106 0.00 0
2010 BLX INC 13,880.82 174 0.00 0 337.21 174
2011 BLX INC 21,962.45 122 0.00 0 0.00 0
2012 BLX INC 7,359.98 106 7,323.93 91 0.00 0
2013 EM ENERGY PA LLC 13,786.63 164 0.00 0 89.23 15
2014 EM ENERGY PA LLC 1,166.00 188 0.00 0 0.00 0
2015 EM ENERGY PA LLC 0.00 0 0.00 0 0.00 0
2016 EM ENERGY PA LLC 0.00 0 0.00 0 0.00 0
2017 EM ENERGY PA LLC 0.00 0 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 BLX INC Produced Fluid 120.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2012 BLX INC Produced Fluid 370.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2013 BLX INC Produced Fluid 205.00 Bbl INJECTION DISPOSAL WELL 34-151-23420

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1673077 Primary Facility 2007-12-21 Drilling/Alteration No Violations Noted
1707194 Primary Facility 2008-05-19 Drilling/Alteration No Violations Noted
1708472 Primary Facility 2008-05-23 Drilling/Alteration No Violations Noted
1708723 Primary Facility 2008-05-15 Drilling/Alteration No Violations Noted
1708985 Primary Facility 2008-05-22 Routine/Complete Inspection No Violations Noted
1713519 Primary Facility 2008-06-05 Routine/Complete Inspection No Violations Noted
1728893 Primary Facility 2008-08-14 Routine/Complete Inspection No Violations Noted
1901920 Primary Facility 2010-07-27 Routine/Complete Inspection No Violations Noted
2375861 Primary Facility 2015-06-03 Routine/Partial Inspection No Violations Noted
2377859 Primary Facility 2015-06-09 Routine/Partial Inspection No Violations Noted
2412573 Primary Facility 2015-10-01 Routine/Partial Inspection No Violations Noted
2664010 Primary Facility 2017-11-21 Plugging(Includes Plugged/Mined Through) No Violations Noted At the time of inspection, NWP onsite waiting for wireline truck. 4 1/2" casing was cut, but won't pull. Well still had circulation so it was believed the cut did not go 360* so wireline truck called out to try again. Prior to this, attempting to pump to TD failed because the cement retainer at 5200' would not open. Several attempts were made with no success. It has a 10,000 psi rating so it was agreed to use this as attainable bottom and the retainer could act as a bridge plug. Cement was placed on top of the retainer up to 3844'. The 4 1/2" was then "cut" at 3812'. This is when the attempts to pull it up occurred.
2668925 Primary Facility 2017-11-30 Plugging(Includes Plugged/Mined Through) No Violations Noted At the time of inspection, no activity was taking place at the site. Well has been plugged and a vent with marker has been installed over the well. Area surrounding the well was seeded and mulched and brought back to contour. Activity from last inspection would start with 4 1/2" being recut and pulled up. Cement plugs were set at 3803'-3480', 2430'-1850', 1610'-1450'. Gel in between cement. 7" casing was set at 1503'. At 1450', a Cast Iron Bridge Plug was set. There is gel on top of that to 470'. Last cement plug was set from 470'-361'. Water was emptied and the vent installed.
2671003 Primary Facility 2017-12-14 Administrative/File Review No Violations Noted

For data sources see[8]