37-035-21268

Well Details

Well ID: 37-035-21268
Loading map...
Country: United States
State: Pennsylvania
County: Clinton
Municipality: Chapman Township
Operator Name: XTO ENERGY INC
Well Pad ID: 148997
Farm/Lease Name: PA TRACT E 1H
License Status:
Spud Date: 2011-12-01
Permit Date: 2011-11-14
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.409683
Longitude: -77.621067

For data sources see[1][2][3]

Well History

Date Event
2011-11-14 New Permit Application
2011-12-04 Performed Spud Operation
2012-04-30 Drilling Completion
2012-10-19 DEVIATED
2013-05-02 Perforation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2013-07-08 2013-07-11 8,200 4,309,330 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Hydrochloric Acid (15%) PPG Industries Acidizing Other - (non-hazardous) NA 85 0.432372 174778
Hydrochloric Acid 7647-01-0 15 0.0763009 30843.1
Sand (Proppant) Nabors Proppant Silica Substrate NA 100 10.2743 4,153,200.0
Acid Corrosion Inhibitor, A12 Nabors Corrosion Inhibitor Isopropyl Alcohol 67-63-0 30 0.000348433 140.847
Propargyl Alcohol 107-19-7 30 0.000348433 140.847
Other -(non hazardous) NA 3 0.00003484 14.085
Proprietary Component NA 7 0.00008130 32.864
Short Chained glycol ether 112-34-5 30 0.000348433 140.847
Friction Reducer, WFR-3B Nabors Friction Reducer Propylene glycol 57-55-6 15 0.00644283 2604.39
Other -(non hazardous) NA 15 0.00644283 2604.39
Ethoxylated oleylamine 26635-93-8 5 0.00214761 868.128
Hydrotreated light distillates (10-30%) 64742-47-8 50 0.0214761 8681.28
Ethoxylated Alcohol Blend NA 15 0.00644283 2604.39
Hydrochloric Acid (7.5%) PPG Industries Acidizing Other - (non-hazardous) NA 92.5 0.160405 64840.7
Hydrochloric Acid 7647-01-0 7.5 0.0130058 5257.35
Biocide KR-153SL Nabors Biocide 2,2-Dibromo-3-nitrilo-propionamide 10222-01-2 20 0.00486687 1967.33
Other -(non hazardous) NA 30 0.0073003 2951
Polyethylene Glycol 25322-68-3 50 0.0121672 4918.33
Water XTO Carrier/Base Fluid Water 7732-18-5 100 88.9625 35,961,300.0
Scale Inhibitor, TSC Nabors Scale Inhibitor 2-Phosphonobutane-1,2,4-tricarboxylic acid, potassium salt 93858-78-7 15 0.00188959 763.827
Anionic copolymer NA 15 0.00188959 763.827
Propylene glycol 57-55-6 40 0.00503889 2036.87
Other -(non hazardous) NA 15 0.00188959 763.827

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2011 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2012 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2013 XTO ENERGY INC 81,596.00 153 0.00 0 0.00 0
2014 XTO ENERGY INC 131,883.00 355 0.00 0 0.00 0
2015 XTO ENERGY INC 89,742.00 364 0.00 0 0.00 0
2016 XTO ENERGY INC 53,460.00 327 0.00 0 0.00 0
2017 XTO ENERGY INC 49,266.00 326 0.00 0 0.00 0
2018 XTO ENERGY INC 32,057.19 289 0.00 0 0.00 0
2019 XTO ENERGY INC 24,776.89 294 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2012 XTO ENERGY INC Drill Cuttings 763.19 Tons LANDFILL 100955
2012 XTO ENERGY INC Drill Cuttings 45.04 Tons LANDFILL 301626
2013 XTO ENERGY INC Produced Fluid 301.00 Bbl INJECTION DISPOSAL WELL 34-133-20114
2013 XTO ENERGY INC Produced Fluid 109.00 Bbl INJECTION DISPOSAL WELL 34-133-21076
2013 XTO ENERGY INC Produced Fluid 2,273.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR119
2013 XTO ENERGY INC Fracing Fluid Waste 424.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR119
2013 XTO ENERGY INC Fracing Fluid Waste 5,322.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2013 XTO ENERGY INC Fracing Fluid Waste 120.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2013 XTO ENERGY INC Produced Fluid 800.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2013 XTO ENERGY INC Produced Fluid 201.00 Bbl INJECTION DISPOSAL WELL 34-133-24096
2014 XTO ENERGY INC Produced Fluid 261.00 Bbl INJECTION DISPOSAL WELL 34-133-20114
2014 XTO ENERGY INC Produced Fluid 4,909.38 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR119
2014 XTO ENERGY INC Produced Fluid 1,232.51 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2014 XTO ENERGY INC Produced Fluid 1,294.07 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2015 XTO ENERGY INC Produced Fluid 884.50 Bbl INJECTION DISPOSAL WELL 34-133-24096
2015 XTO ENERGY INC Produced Fluid 102.00 Bbl INJECTION DISPOSAL WELL 34-133-21076
2015 XTO ENERGY INC Produced Fluid 211.00 Bbl INJECTION DISPOSAL WELL 34-133-20114
2015 XTO ENERGY INC Produced Fluid 1,971.22 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2015 XTO ENERGY INC Produced Fluid 2,410.95 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2016 XTO ENERGY INC Produced Fluid 310.95 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2016 XTO ENERGY INC Produced Fluid 334.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2016 XTO ENERGY INC Produced Fluid 109.00 Bbl INJECTION DISPOSAL WELL 34-133-20114
2016 XTO ENERGY INC Produced Fluid 202.38 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 XTO ENERGY INC Produced Fluid 171.86 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2016 XTO ENERGY INC Produced Fluid 906.00 Bbl INJECTION DISPOSAL WELL 34-133-24096
2017 XTO ENERGY INC Produced Fluid 1,135.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2017 XTO ENERGY INC Soil Contaminated by Oil 0.32 Tons LANDFILL 100955
2017 XTO ENERGY INC Soil Contaminated by Oil & Gas Related Spills 0.32 Tons LANDFILL 100955
2017 XTO ENERGY INC Produced Fluid 1,000.79 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2017 XTO ENERGY INC Produced Fluid 232.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2018 XTO ENERGY INC Produced Fluid 281.52 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 XTO ENERGY INC Produced Fluid 106.00 Bbl INJECTION DISPOSAL WELL 34-133-24189
2018 XTO ENERGY INC Produced Fluid 46.00 Bbl REUSE (AT WELL PAD)
2018 XTO ENERGY INC Produced Fluid 991.58 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 XTO ENERGY INC Produced Fluid 96.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2019 XTO ENERGY INC Waste Water Treatment Sludge 5.73 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE ORDER 2014-04
2019 XTO ENERGY INC Produced Fluid 125.00 Bbl INJECTION DISPOSAL WELL 34-133-24189
2019 XTO ENERGY INC Produced Fluid 216.00 Bbl INJECTION DISPOSAL WELL 34-133-21076
2019 XTO ENERGY INC Other Oil & Gas Wastes 188.00 Bbl REUSE (AT WELL PAD)
2019 XTO ENERGY INC Produced Fluid 42.00 Bbl INJECTION DISPOSAL WELL 34-133-20114
2019 XTO ENERGY INC Produced Fluid 337.00 Bbl INJECTION DISPOSAL WELL 34-133-24096
2019 XTO ENERGY INC Produced Fluid 235.00 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2044014 Primary Facility 2012-01-26 Routine/Complete Inspection No Violations Noted
2067990 Primary Facility 2012-04-10 Routine/Complete Inspection No Violations Noted
2071575 Primary Facility 2012-05-29 Drilling/Alteration No Violations Noted
2092558 Primary Facility 2012-07-05 Routine/Complete Inspection No Violations Noted
2098625 Primary Facility 2012-08-07 Routine/Complete Inspection No Violations Noted
2106254 Primary Facility 2012-09-25 Routine/Complete Inspection No Violations Noted
2115278 Primary Facility 2012-11-07 Routine/Complete Inspection No Violations Noted
2160205 Primary Facility 2013-04-22 Follow-up Inspection No Violations Noted
2160322 Primary Facility 2013-04-04 Routine/Complete Inspection No Violations Noted
2168364 Primary Facility 2013-05-09 Routine/Complete Inspection No Violations Noted
2169200 Primary Facility 2013-05-22 Routine/Complete Inspection No Violations Noted
2169668 Primary Facility 2013-05-23 Incident- Response to Accident or Event No Violations Noted
2175705 Primary Facility 2013-06-17 Routine/Complete Inspection No Violations Noted
2184073 Primary Facility 2013-07-16 Routine/Complete Inspection No Violations Noted
2196087 Primary Facility 2013-08-14 Routine/Complete Inspection No Violations Noted
2202363 Primary Facility 2013-09-03 Routine/Complete Inspection No Violations Noted
2250596 Primary Facility 2014-03-05 Incident- Response to Accident or Event Viol(s) Noted & Immediately Corrected
2344063 Primary Facility 2015-02-10 Routine/Complete Inspection No Violations Noted
2422233 Primary Facility 2015-10-15 Routine/Complete Inspection Violation(s) Noted Routine inspection of wells in production. Methane detected on 9 5/8" annulus vent. Violations Noted.
2514332 Primary Facility 2016-08-23 Site Restoration No Violations Noted
2556667 Primary Facility 2017-01-23 Routine/Complete Inspection No Violations Noted Routine inspection of unconventional well in production. No violations noted at time of inspection.
2721047 Primary Facility 2018-04-20 Routine/Complete Inspection No Violations Noted The weather is 45 Deg. F and sunny at the time of inspection. Routine inspection of XTO Energy INC., PA Tract Unit E Pad, 1H well on April 20, 2018. There are 6 wells on this pad.

Well # 1H is active and producing. Annular vents surface by intermediate (13-3/8¿ x 9-5/8¿) and intermediate by production (9-5/8¿ x 5-1/2¿) are open and vented. 0% combustible gas was detected at the annulus or in the area immediately surrounding the well. Production xmas tree top (tubing) pressure reading is 114 PSI, casing pressure is 300 PSI. No violations are noted at time of inspection. Wellsite looks neat and well organized. DEP Representative - Ulyana Trynovich, Oil and Gas Inspector.

2829571 Primary Facility 2019-01-17 Routine/Complete Inspection No Violations Noted On January 17, 2019, Department representative Brad Kline conducted a routine site inspection at XTO Energy PA Tract 1H Pad E. Monthly tank maintenance log was available for review. No E&S issues were observed during the time of inspection. The site is stable and well vegetated meeting the 70% uniform, perennial, vegetative cover.

There are a total of 6 producing wells located on this well pad. All wells are tagged with API/well permit numbers. No bubbling within the cellars was observed. There are 6 line heaters with water separators and 6 steel vertical production fluids tanks onsite. Both line heaters and production fluid tanks were stationed in secondary containment.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2250596 690078 03/05/2014 2014-03-05 78.54* - Failure to properly control or dispose of industrial or residual waste to prevent pollution of the waters of the Commonwealth. Environmental Health & Safety Release of brine fluid to the pad during transfer to a tanker for dispoasal at another location
2422233 738473 10/15/2015 2015-10-15 78.86 - CASING AND CEMENTING - DEFECTIVE CASING OR CEMENTING - Operator failed to report defect in a well that has defective, insufficient or improperly cemented casing to the Department within 24 hours of discovery. Operator failed to correct defec Environmental Health & Safety Gas discovered on 9 5/8 annulus vent. 100% Methane