Well Details

Well ID: 37-051-24645
Loading map...
Country: United States
State: Pennsylvania
County: Fayette
Municipality: Luzerne Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 152926
Farm/Lease Name: SIEGEL
License Status:
Spud Date:
Permit Date: 2018-02-20
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 39.968914
Longitude: -79.969061

For data sources see[1][2][3]

Well History

Date Event
2018-02-20 New Permit Application
2018-04-02 Performed Spud Operation
2019-06-11 MOD
2019-09-17 MOD

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 CHEVRON APPALACHIA LLC 0.00 0 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 CHEVRON APPALACHIA LLC Other Oil & Gas Wastes 8.89 Bbl INJECTION DISPOSAL WELL 34-157-25511
2018 CHEVRON APPALACHIA LLC Drill Cuttings 460.62 Tons LANDFILL 100172
2018 CHEVRON APPALACHIA LLC Drilling Fluid Waste 735.89 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2018 CHEVRON APPALACHIA LLC Other Oil & Gas Wastes 35.33 Bbl REUSE AT A WELL PAD OUTSIDE PENNSYLVANIA
2018 CHEVRON APPALACHIA LLC Drill Cuttings 2.72 Tons LANDFILL 100663
2018 CHEVRON APPALACHIA LLC Drilling Fluid Waste 1,393.61 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2018 CHEVRON APPALACHIA LLC Drilling Fluid Waste 37.78 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW001
2018 CHEVRON APPALACHIA LLC Drilling Fluid Waste 8.42 Tons RESIDUAL WASTE TRANSFER FACILITY 101532
2019 CHEVRON APPALACHIA LLC Other Oil & Gas Wastes 74.44 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 CHEVRON APPALACHIA LLC Synthetic Liner Materials 3.91 Tons LANDFILL 100663
2019 CHEVRON APPALACHIA LLC Waste Water Treatment Sludge 1.20 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 CHEVRON APPALACHIA LLC Other Oil & Gas Wastes 24.44 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2711827 Primary Facility 2018-03-28 Drilling/Alteration No Violations Noted Cellar on site.
2717197 Primary Facility 2018-04-11 Drilling/Alteration No Violations Noted 30" Conductor set @ 40'.Cellarset @ 8'.
2768491 Primary Facility 2018-08-23 Routine/Partial Inspection No Violations Noted On 08/23/18 at approximately 1015 hours I met with Curtis Small of Chevron to discuss possible redline changes. The operator of an adjacent conventional well accesses their well from the Siegel well pad entrance. The conventional well operator had a preexisting access road that was modified and graveled in accordance with the approved E&S plan during construction of the Siegel well site. The conventional operator indicated to Chevron the access road as modified is steeper than it was originally. Chevron proposed reducing the grade of the road. Redline approval was granted to reduce the grade of the access road within Chevron's LOD.
2846017 Primary Facility 2019-02-15 Compliance Evaluation No Violations Noted On 10/13/18 a synthetic based mud spill occurred at the site, resulting in the issuance of an NOV.

On 02/15/18 I conducted a compliance evaluation inspection at the site. The impacted pad slope, channel, and stormwater basin had been remediated. The remediated areas were properly stabilized and there were no signs of erosion observed. The violations have been corrected and there were no violations observed at the time of inspection.

2853083 Primary Facility 2019-03-13 Drilling/Alteration No Violations Noted This well has had the top hole drilled and cased and is tagged and inside a protective cattle gate waiting on the fluid Rig to arrive and finish drilling. There was no Drill Site Supervisor present on site at the time of this inspection. All equipment staged on site looked ok.

NOTE: I contacted Chevron and had a Compliance Specialist come to the site to darken the well sign information in a bit more clearly as the recent heavy rain made it a bit difficult to read.