Well ID: 37-059-27418 | ![]() Sorry, we have no imagery here. Sorry, we have no imagery here. ![]() |
Country: United States | |
State: Pennsylvania | |
County: Greene | |
Municipality: Whiteley Township | |
Operator Name: RICE DRILLING B LLC | |
Well Pad ID: 154362 | |
Farm/Lease Name: MAC 1V | |
License Status: | |
Spud Date: | |
Permit Date: 2017-08-22 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Vertical Well | |
Conservation: No | |
Latitude: 39.827683 | |
Longitude: -80.159172 |
Date | Event |
---|---|
2017-08-22 | New Permit Application |
2018-06-12 | Permit Renewal Application |
For data sources see[4]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2653567 | Primary Facility | 2017-10-03 | Routine/Partial Inspection | No Violations Noted | The Act 9 sign was in place and all required documents were present at the site. The purpose of the inspection was to discuss redline changes to the site. Rice requested Department approval to shift BMPs toward the LOD to allow PCSM to be built during the initial construction phase to limit future earth disturbance. The redline changes were approved. |
2666987 | Primary Facility | 2017-11-28 | Compliance Evaluation | No Violations Noted | The Act 9 sign was in place and all required documents were present at the site. A large portion of the site was temporarily stabilized. An NOV was previously issued in response to a BMP failure that caused sediment to leave the LOD and enter waters of the Commonwealth. Repairs had been made to the BMPs and there was no sediment leaving the site. There were no violations observed at the time of inspection. |
2712315 | Primary Facility | 2018-03-23 | Routine/Partial Inspection | No Violations Noted | The Act 9 sign was in place and all required documents were present at the site. The land owner requested EQT add a culvert in an access road diversion channel and gravel in the adjacent area to allow better access to their property with farm equipment. Due to the addition of impervious area, it was recommended to EQT that they contact Department engineering staff. Redline approval was not granted.
During the inspection EQT informed the Department a slip had occurred upslope of the rain garden on the north side of the site. The slip material was contained in the rain garden. No slip material left the LOD. There were no violations observed at the time of inspection. |