37-059-27508

Well Details

Well ID: 37-059-27508
Loading map...
Country: United States
State: Pennsylvania
County: Greene
Municipality: Jackson Township
Operator Name: EQT PROD CO
Well Pad ID: 154155
Farm/Lease Name: STATE GAME LANDS 179 NFR60H15
License Status:
Spud Date:
Permit Date: 2017-10-19
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 39.815328
Longitude: -80.402203

For data sources see[1][2][3]

Well History

Date Event
2017-10-19 New Permit Application
2017-10-31 Performed Spud Operation
2018-03-07 MOD

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 EQT PROD CO 0.00 0 0.00 0 0.00 0
2019 EQT PROD CO 347,295.00 41 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 EQT PROD CO Drill Cuttings 212.16 Tons LANDFILL 100172
2017 EQT PROD CO Other Oil & Gas Wastes 13.00 Bbl REUSE (AT WELL PAD)
2017 EQT PROD CO Drill Cuttings 126.29 Tons LANDFILL 100663
2018 EQT PROD CO Drill Cuttings 666.75 Tons LANDFILL 100172
2018 EQT PROD CO Drill Cuttings 384.08 Tons LANDFILL 100663
2018 EQT PROD CO Drilling Fluid Waste 260.00 Bbl REUSE (AT WELL PAD)
2018 EQT PROD CO Other Oil & Gas Wastes 77.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2018 EQT PROD CO Other Oil & Gas Wastes 3.20 Tons LANDFILL 100663
2018 EQT PROD CO Other Oil & Gas Wastes 212.00 Bbl REUSE (AT WELL PAD)
2018 EQT PROD CO Other Oil & Gas Wastes 23.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2018 EQT PROD CO Other Oil & Gas Wastes 1.19 Tons RESIDUAL WASTE PROCESSING FACILITY ODNR 2015-511
2019 EQT PROD CO Produced Fluid 30.40 Bbl REUSE (AT WELL PAD)
2019 EQT PROD CO Produced Fluid 74.68 Tons RESIDUAL WASTE PROCESSING FACILITY ODNR 2015-511
2019 EQT PROD CO Soil Contaminated by Oil 17.02 Tons LANDFILL CID # 28726
2019 EQT PROD CO Produced Fluid 14.65 Bbl INJECTION DISPOSAL WELL 34-167-28462
2019 EQT PROD CO Other Oil & Gas Wastes 61.25 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 EQT PROD CO Waste Water Treatment Sludge 8.69 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 EQT PROD CO Soil Contaminated by Oil & Gas Related Spills 17.02 Tons LANDFILL CID # 28726
2019 EQT PROD CO Other Oil & Gas Wastes 7.50 Bbl RESIDUAL WASTE PROCESSING FACILITY
2019 EQT PROD CO Produced Fluid 32.46 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 EQT PROD CO Produced Fluid 0.69 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 EQT PROD CO Produced Fluid 415.28 Bbl SURFACE IMPOUNDMENT 95-7-37312-19
2019 EQT PROD CO Other Oil & Gas Wastes 7.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2019 EQT PROD CO Other Oil & Gas Wastes 3.75 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW010
2019 EQT PROD CO Produced Fluid 153.37 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW010
2019 EQT PROD CO Other Oil & Gas Wastes 163.31 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2632606 Primary Facility 2017-08-02 Routine/Complete Inspection No Violations Noted On August 2, 2017, the Department performed an inspection of the EQT State Gamelands 179 well pad site. Present at time of inspection was Bill Balog (EQT), Will Brogan and Mike Stephan (DEP). The site is located in Aleppo and Jackson Twps., Greene Co. The inspection was a follow up inspection of the site after noted violations on July 31, 2017.

The operator was in process of repairing E&S BMPs which were damaged and failed during a recent heavy rainfall event. The operator has agreed to repair the stream crossing for Reinhart Rd. In Jackson Twp. The operator will apply for necessary Emergency 105 permit to perform repairs to the stream crossing and to remediate impacts to an unnamed trib. to Job Creek from sediment discharges associated with E&S BMPs failure on site after the recent rainfall event. The remediation will be performed by hand as much as possible.

13 wells have been permitted for the site. Site under construction. No wells have been drilled at time of inspection.

2636843 Primary Facility 2017-09-07 Routine/Complete Inspection No Violations Noted On September 7, 2017, the Department performed an inspection of the EQT State Gamelands 179 well pad site. Presnt at ime of inspection was Rex Nelson (EQT). The site is located in Aleppo and Jackson Twps., Greene Co. The inspection was a routine inspection after notification by the operator of E&S failures on site after a recent rainfall event.

The operator has repaired E&S BMPs which were damaged and failed during a heavy rainfall event. The operator reported a rainfall of 1 1/2" during a 1 hour timeframe on September 5, 2017. During the September 6, 2017 E&S inspection the operator noted failures along the silt sock down gradient from the excess material stockpiles. The operator has stabilized the site with armor guard hydro seed as areas of construction are complete. The erosion prevention seeding did not perform as expected and sediment laden water over toped the silt sock discharging small amount of sediment approximately 20' outside the LOD. The operator has contacted the seeding company to reappl

2651389 Primary Facility 2017-10-05 Preoperation Inspection No Violations Noted On October 5, 2017, the Department performed an inspection of the EQT State Gamelands 179 well pad site. Presnt at ime of inspection was Rex Nelson (EQT). The site is located in Aleppo and Jackson Twps., Greene Co. The inspection was a inspection after a request by the operator for a pre-operational inspection.

The operator has completed installation of all E&S controls. The well pad final grading and stoning is being completed. The operator has completed construction of the access road and PCSMs along the access road. The construction of the well pad PCSMs (wet pond) is almost complete. The operator has temporarily stabilized the well pad and stockpile slopes with hydro seeding and slope armoring.

13 wells have been permitted to be drilled on site. None of the wells have been drilled at time of inspection.

2656499 Primary Facility 2017-11-02 Drilling/Alteration No Violations Noted Conductor set @ 40'. Setting Cellar Tech after conductor are in.
2673591 Primary Facility 2017-12-12 Drilling/Alteration No Violations Noted Drilling Water / Coal Protection Casing and cementing today (12/11/2017).
2673600 Primary Facility 2017-12-05 Drilling/Alteration No Violations Noted Drilling Water/Coal Protection Casing and cementing tonight(12/3/2017).
2702313 Primary Facility 2018-03-07 Drilling/Alteration No Violations Noted Surface, coal, and intermediate casings have been set and cemented to the surface. Operator drilled pilot hole to 5,753' TMD. Rig off well. Rig currently drilling 059-27505.

Depths from KB KB = 13'