Well Details

Well ID: 37-059-27545
Loading map...
Country: United States
State: Pennsylvania
County: Greene
Municipality: Whiteley Township
Operator Name: RICE DRILLING B LLC
Well Pad ID: 154376
Farm/Lease Name: STATTLER ROAD
License Status: Inactive
Spud Date: 2018-03-16
Permit Date: 2017-11-16
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 39.814419
Longitude: -80.173956

For data sources see[1][2][3]

Well History

Date Event
Newly Drilled
2017-11-16 New Permit Application
2018-03-16 Performed Spud Operation
2018-03-21 MOD
2018-06-23 Drilling Completion
2019-03-25 MOD
2019-04-26 Inactive Well Request Granted

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 RICE DRILLING B LLC 0.00 0 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 RICE DRILLING B LLC Other Oil & Gas Wastes 94.91 Bbl REUSE (AT WELL PAD)
2018 RICE DRILLING B LLC Drilling Fluid Waste 640.00 Bbl REUSE (AT WELL PAD)
2018 RICE DRILLING B LLC Other Oil & Gas Wastes 10.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2018 RICE DRILLING B LLC Drill Cuttings 505.05 Tons LANDFILL 100419
2018 RICE DRILLING B LLC Other Oil & Gas Wastes 11.11 Bbl REUSE AT A WELL PAD OUTSIDE PENNSYLVANIA
2018 RICE DRILLING B LLC Other Oil & Gas Wastes 153.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 RICE DRILLING B LLC Other Oil & Gas Wastes 13.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 RICE DRILLING B LLC Other Oil & Gas Wastes 1,789.38 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2653613 Primary Facility 2017-10-03 Administrative/File Review No Violations Noted The purpose of the inspection was to discuss redline changes to the Stattler Road site. Rice requested Department approval to shift BMPs toward the LOD to allow PCSM to be built during the initial construction phase in order to limit future earth disturbance. The redline changes were approved.
2708947 Primary Facility 2018-03-19 Drilling/Alteration No Violations Noted 26" Conductor set @ 40'. No cellar installed.
2743897 Primary Facility 2018-06-21 Drilling/Alteration No Violations Noted Operator began drilling operations on 6/17/18. Surface and coal protective casings have been set and cemented. Operator reports Pittsburgh coal seam 969'-978'. Operator drilling ahead at 1,180'.

Operator dewatering and repairing containment.

KB - 13'