If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 37-063-24321 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.656703,"lon":-78.882708,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Indiana | |
Municipality: Green Township | |
Operator Name: XTO ENERGY INC | |
Well Pad ID: | |
Farm/Lease Name: MINTA FORSHA 1 | |
License Status: PLUGGED & ABANDONED | |
Spud Date: 1978-09-14 | |
Permit Date: 1978-07-21 | |
Well Type: GAS | |
Unconventional Well: N | |
Configuration: Vertical Well | |
Conservation: Yes | |
Latitude: 40.656703 | |
Longitude: -78.882708 |
Date | Event |
---|---|
1978-07-21 | New Permit Application |
1978-09-14 | Performed Spud Operation |
1978-10-03 | Perforation |
1978-10-04 | Drilling Completion |
1978-12-26 | NEWLY DRILLED |
2015-10-09 | Drilling Completion |
2016-06-16 | FULLY PLUGGED |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
1980 | CABOT OIL & GAS CORP | 187,308.00 | 0 | 0.00 | 0 | 0.00 | 0 |
1981 | CABOT OIL & GAS CORP | 232,383.00 | 0 | 0.00 | 0 | 0.00 | 0 |
1982 | CABOT OIL & GAS CORP | 198,773.00 | 0 | 0.00 | 0 | 0.00 | 0 |
1983 | CABOT OIL & GAS CORP | 158,946.00 | 0 | 0.00 | 0 | 0.00 | 0 |
1984 | CABOT OIL & GAS CORP | 121,241.00 | 0 | 0.00 | 0 | 0.00 | 0 |
1985 | CABOT OIL & GAS CORP | 89,636.00 | 0 | 0.00 | 0 | 0.00 | 0 |
1989 | CABOT OIL & GAS CORP | 65,952.00 | 320 | 0.00 | 0 | 0.00 | 0 |
1991 | CABOT OIL & GAS CORP | 87118.00 | 363 | 0.00 | 0 | 0.00 | 0 |
1992 | CABOT OIL & GAS CORP | 67807.00 | 298 | 0.00 | 0 | 0.00 | 0 |
1993 | CABOT OIL & GAS CORP | 67920.00 | 305 | 0.00 | 0 | 0.00 | 0 |
1994 | CABOT OIL & GAS CORP | 43710.00 | 365 | 0.00 | 0 | 0.00 | 0 |
1995 | CABOT OIL & GAS CORP | 40472.00 | 365 | 0.00 | 0 | 0.00 | 0 |
1996 | CABOT OIL & GAS CORP | 42206 | 365 | 0.00 | 0 | 0.00 | 0 |
1997 | CABOT OIL & GAS CORP | 38858 | 365 | 0.00 | 0 | 0.00 | 0 |
1998 | CABOT OIL & GAS CORP | 40622 | 365 | 209 | 365 | 0.00 | 0 |
1999 | CABOT OIL & GAS CORP | 36397 | 365 | 0.00 | 0 | 0.00 | 0 |
2000 | CABOT OIL & GAS CORP | 38290.21 | 365 | 0.00 | 0 | 0.00 | 0 |
2001 | CABOT OIL & GAS CORP | 33934.9 | 365 | 0.00 | 0 | 0.00 | 0 |
2002 | CABOT OIL & GAS CORP | 34570.57 | 365 | 0.00 | 0 | 0.00 | 0 |
2003 | LINN OPR LLC | 2716 | 30 | 0.00 | 0 | 0.00 | 0 |
2004 | LINN OPR LLC | 33248 | 365 | 0.00 | 0 | 0.00 | 0 |
2005 | LINN OPR LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2006 | LINN OPR INC | 27,215.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2007 | LINN OPR INC | 26407.00 | 222 | 0.00 | 0 | 0.00 | 0 |
2008 | XTO ENERGY INC | 28203.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2009 | XTO ENERGY INC | 26594.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2010 | XTO ENERGY INC | 24,369.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2011 | XTO ENERGY INC | 23,190.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2012 | XTO ENERGY INC | 21,632.00 | 366 | 0.00 | 0 | 0.00 | 0 |
2013 | XTO ENERGY INC | 21,339.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2014 | XTO ENERGY INC | 13,513.00 | 270 | 0.00 | 0 | 0.00 | 0 |
2015 | XTO ENERGY INC | 6,251.00 | 277 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
1991 | CABOT OIL & GAS CORP | Brine | 3,042.00 Bbl | ||
1996 | CABOT OIL & GAS CORP | Brine | 3,580.00 Bbl | Brine or Industrial Waste Treatment Plt | PA 0101508 |
1997 | CABOT OIL & GAS CORP | Brine | 2,579.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0101508 |
1998 | CABOT OIL & GAS CORP | Brine | 2,870.00 Bbl | Brine or Industrial Waste Treatment Plt | 0095273 |
1999 | CABOT OIL & GAS CORP | Brine | 3,171.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0095273 |
2001 | CABOT OIL & GAS CORP | Brine | 3,202.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0095273 |
2002 | CABOT OIL & GAS CORP | Brine | 3,086.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0101508 |
2004 | LINN OPR LLC | Brine | 2,820.00 Bbl | Brine or Industrial Waste Treatment Plt | 0095273 |
2005 | LINN OPR LLC | Brine | 2,755.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0095273 |
2006 | LINN OPR INC | Brine | 2,580.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0095273 |
2008 | XTO ENERGY INC | Brine | 2,189.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0095273 |
2009 | XTO ENERGY INC | Brine | 2,010.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0095273 |
2009 | XTO ENERGY INC | Brine | 181.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0020346 |
2010 | XTO ENERGY INC | Produced Fluid | 2,474.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2011 | XTO ENERGY INC | Produced Fluid | 2,359.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2011 | XTO ENERGY INC | Produced Fluid | 70.00 Bbl | INJECTION DISPOSAL WELL | 34-133-21076 |
2011 | XTO ENERGY INC | Produced Fluid | 251.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0254185 |
2012 | XTO ENERGY INC | Produced Fluid | 190.00 Bbl | INJECTION DISPOSAL WELL | 34-133-24096 |
2012 | XTO ENERGY INC | Produced Fluid | 185.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | 101674 |
2012 | XTO ENERGY INC | Produced Fluid | 313.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2012 | XTO ENERGY INC | Produced Fluid | 190.00 Bbl | INJECTION DISPOSAL WELL | 34-133-21076 |
2012 | XTO ENERGY INC | Produced Fluid | 1,696.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0254185 |
2013 | XTO ENERGY INC | Produced Fluid | 801.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2013 | XTO ENERGY INC | Produced Fluid | 220.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0254185 |
2013 | XTO ENERGY INC | Produced Fluid | 220 Bbl | CENT WASTE TRT FAC NPDES | PA0254185 |
2013 | XTO ENERGY INC | Produced Fluid | 940.00 Bbl | RESIDUAL WASTE TRANSFER FACILITY | 101674 |
2014 | XTO ENERGY INC | Produced Fluid | 460.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | XTO ENERGY INC | Produced Fluid | 595.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NW009 |
2014 | XTO ENERGY INC | Produced Fluid | 105.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
2015 | XTO ENERGY INC | Produced Fluid | 71.91 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NW009 |
2015 | XTO ENERGY INC | Servicing Fluid | 1,580.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
2015 | XTO ENERGY INC | Produced Fluid | 108.56 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2270433 | Primary Facility | 2014-05-06 | Administrative/File Review | In Compliance with Policy | SPILL. |
2270478 | Primary Facility | 2014-05-07 | Incident- Response to Accident or Event | Violation(s) Noted | SPILL. Inspt in response to admin inspt 2270433.Upon notification of spill from answering services, Dept contacted XTO rep E.Greenert via phone.Mr. Greenert stated a release of approx 1 bbl brine into an earthen dike occurred as a result of a faulty phalange on a prod tank.Roll-offs currently en route to site, E&S BMPs to be installed.Water truck already removed remaining contents from tank.Impacted areas delineated.It is not believed that any waterways have been impacted although a stream is located approx 200 ft away from the well.Oriskany. According to records, drilling occurred 9/14/1978-10/4/1978. Well tag present, legible. |
2271245 | Primary Facility | 2014-05-08 | Follow-up Inspection | Outstanding Violations - No Viols Req'd | FUI to inspt record 2270478 (enf 310972) for the reportable release of 1 bbl brine water.Oriskany.At time of inspection, Opr rep Jason Canose & contractors on-site.Excavation of contaminated soils w/in dike previously commenced, not yet completed.Two prod tanks w/in dike not yet removed.Opr's current plan of action is to remove tanks & cont' excavating contaminated soils from base of dike utilizing a conductivity meter as guidance.Due to forecasted heavy rains, Opr intends to place tarp over dike during interim of remediation efforts in order to prevent saturation of contaminated soils & possible further spread of contaminants.Accum precip w/in tarp will be removed & properly disposed of per current regs.BMPs properly installed on down-gradient perimeter of site.AR stable, gated.Dept rec'ds Opr cont' to monitor & maintain AR & well site as increased traffic due to clean-up efforts could potentially result in an accel E&S pollution event. |
2271259 | Primary Facility | 2014-05-12 | Follow-up Inspection | Outstanding Violations - No Viols Req'd | FUI to inspt record 2270478 (enf 310972) for the reportable release of 1 bbl brine water.Oriskany.At time of inspection, Opr rep Jason Canose on-site.Two production tanks previously removed from site. Add'l excavation of contaminated soils w/in dike have occurred since previous inspt on 5/8/14 (record 2271245).Liner in place over excavated areas of dike to protect from precipitation events (record 2271245).Five covered roll-off boxes currently on-site.Upon arrival of add'l roll-off boxes, Opr plans to cont' excavation of impacted soils.Silt sock properly installed on down-gradient perimeter of site.AR stable, gated.Dept rec'ds Opr cont' to monitor & maintain E&S BMPs & AR & well site as increased traffic due to clean-up efforts could potentially result in an accelerated E&S pollution event.A follow-up inspection will be conducted in the future to ensure site is properly cleaned-up and restored. |
2297988 | Primary Facility | 2014-08-25 | Follow-up Inspection | Outstanding Violations - No Viols Req'd | FUI to inspt record 2270478 (enf 310972) for the 5/6 reportable release of 1 bbl brine water. Oriskany. |
2362904 | Primary Facility | 2015-04-20 | Follow-up Inspection | Outstanding Violations - No Viols Req'd | On-site FUI to in response to inspection record 2270478 (enf 310972) for the 5/6/14 reportable release of 1 bbl brine water. Oriskany. |
2405243 | Primary Facility | 2015-08-25 | Compliance Evaluation | No Violations Noted | On-site CEI in response to inspection record 2270478 (enf 310972) for the 5/6/14 reportable release of 1 bbl brine water.Area of excavation partially backfilled. Backfilled areas seeded/mulched with moderate growth observed.Silt sock installed down-gradient of excavated areas.Per the spill policy, 15 day initial report received by Department on 5/23/14 notifying Department that Operator is utilizing Act 2 for site remediation. NIR received by Department on 11/7/14.As the Operator has entered the Act 2 program and remediation is ongoing, violations issued under inspection record 2270478 (enf ID 310972) have been corrected.While on-site, Department contacted Operator representative Jason Canose via phone to inquire about status of remediation (i.e. backfilling). Per Mr. Canose, the backfilling of the site is to be completed as soon as possible. Mr. Canose agreed to provide the Department with updates as appropriate. UPDATE: At 1338, Mr. Canose notified the Department via phone that backfilling is to be completed next week. |
2430047 | Primary Facility | 2015-12-03 | Administrative/File Review | In Compliance with Policy | Admin inspection conducted in response to violations issued under inspection record 2270478 (enf 310972) for the reportable release of 1 bbl brine water. |
2446229 | Primary Facility | 2016-01-27 | Routine/Partial Inspection | No Violations Noted | Oriskany. At time of inspection, well appears plugged with erected monument. Name plate with permit number attached to erected monument. According to records, drilling occurred 9/14/1978-10/4/1978. Notice of Intent to Plug received by Department on 9/30/2015.
E&S plan on-site. Orange fence located around wetland identified on E&S plan. Temporary BMPs appear to be installed per the E&S plan, however Department unable to adequately inspect these BMPs due to snow-cover. Although site is snow-covered, well site does not appear to yet be re-graded and/or restored in accordance with the restoration plan. Department unable to adequately inspect site and access road for any accelerated erosion and sedimentation issues during this inspection due to snow-cover. |
2536016 | Primary Facility | 2016-11-07 | Routine/Complete Inspection | No Violations Noted | At time of inspection access road gate remains at beginning of access road. Beginning section of access road rocked, the remainder of the access road appears to have been removed and permanently restored. Department contacted XTO Rep Dan Rice to determine if gate and a portion of access road are to remain. Mr. Rice stated gate and beginning of access road are to remain to allow access to pipeline.
Well appears to be plugged. Permit number affixed to erected monument in a permanent manner. Site appears permanently stabilized with >70% uniform vegetative growth. Meter box remains on site. Operator Rep Dan Rice stated meter box will be removed this week. UPDATE 11-10-16: Operator Rep Dan Rice contacted Department by phone and left message stating meter box has been removed from site. |
2785547 | Primary Facility | 2018-10-09 | Site Restoration | No Violations Noted | Inspection conducted in response to a Well Site Restoration Report received by Department. As per inspection record #2536016, gate at entrance of access road remains and meter box has been removed. At time of inspection well is plugged. Site vegetated and appears returned to near original contours.
This restoration report is approved. |
Inspection ID | Violation ID | Violation Date | Date Resolved | Violation Code | Violation Type | Violation Comments |
---|---|---|---|---|---|---|
2270478 | 695669 | 05/07/2014 | 2014-05-07 | 78.57 - Failure to post pit approval number | Administrative | A violation is being issued for Operator's failure to properly collect and not discharge brine and other fluids on or into the ground or into the waters of the Commonwealth. |
Violation ID | Penalty ID | Penalty Code | Penalty Status | Penalty Date | Enforcement Date | Penalty Amount | Amount Collected |
---|---|---|---|---|---|---|---|
695669 | 310972 | NOV - Notice of Violation | Comply/Closed | 2017-08-25 |
For data sources see[7]