Well Details

Well ID: 37-063-33084
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: Washington Township
Operator Name: ALLIANCE PETRO CO LLC
Well Pad ID:
Farm/Lease Name: H M & F W MCGARA 5
License Status: ACTIVE
Spud Date: 2002-05-19
Permit Date: 2002-04-23
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.706294
Longitude: -79.166570

For data sources see[1][2][3]

Well History

Date Event
2002-04-23 New Permit Application
2002-05-19 Performed Spud Operation
2002-05-22 Drilling Completion
2002-06-03 Perforation
2002-07-24 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2002 PHILLIPS EXPLORATION INC 8968 110 0.00 0 0.00 0
2003 CONSOL GAS CO 0.00 0 0.00 0 0.00 0
2004 PHILLIPS EXPLORATION INC 7526 281 0.00 0 0.00 0
2005 PHILLIPS EXPLORATION INC 6378 347 0.00 0 0.00 0
2006 PHILLIPS EXPLORATION INC 6,582.00 339 0.00 0 0.00 0
2007 PHILLIPS EXPLORATION INC 4829.00 365 0.00 0 0.00 0
2008 PHILLIPS EXPLORATION INC 5074.00 324 0.00 0 0.00 0
2009 PHILLIPS EXPLORATION INC 4017.00 365 0.00 0 0.00 0
2010 PHILLIPS EXPLORATION INC 4,293.00 356 0.00 0 0.00 0
2011 PHILLIPS EXPLORATION INC 3,652.00 332 0.00 0 0.00 0
2012 XTO ENERGY INC 3,263.00 362 0.00 0 0.00 0
2013 XTO ENERGY INC 3,119.00 365 0.00 0 0.00 0
2014 XTO ENERGY INC 2,595.00 365 0.00 0 0.00 0
2015 XTO ENERGY INC 1,655.00 289 0.00 0 0.00 0
2016 XTO ENERGY INC 1,714.00 366 0.00 0 0.00 0
2017 ALLIANCE PETRO CO LLC 1,035.00 334 0.00 0 0.00 0
2018 ALLIANCE PETRO CO LLC 1,305.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2002 PHILLIPS EXPLORATION INC Brine 215.00 Bbl Brine or Industrial Waste Treatment Plt
2003 PHILLIPS EXPLORATION INC Brine 195.00 Bbl Brine or Industrial Waste Treatment Plt
2003 CONSOL GAS CO Brine 65.00 Bbl Brine or Industrial Waste Treatment Plt PA0095273
2003 CONSOL GAS CO Drilling 200.00 Bbl Brine or Industrial Waste Treatment Plt PA0091472
2003 CONSOL GAS CO Fracking Fluid 100.00 Bbl Brine or Industrial Waste Treatment Plt PA0095273
2003 CONSOL GAS CO Brine 692.00 Bbl Brine or Industrial Waste Treatment Plt PA0091472
2003 CONSOL GAS CO Drilling 180.00 Bbl Brine or Industrial Waste Treatment Plt PA0095273
2003 CONSOL GAS CO Drilling 75.00 Bbl Brine or Industrial Waste Treatment Plt PA0095443
2003 CONSOL GAS CO Brine 113.00 Bbl Brine or Industrial Waste Treatment Plt PA0026034
2003 CONSOL GAS CO Fracking Fluid 135.00 Bbl Brine or Industrial Waste Treatment Plt PA0095443
2003 CONSOL GAS CO Fracking Fluid 140.00 Bbl Brine or Industrial Waste Treatment Plt PA0091472
2003 CONSOL GAS CO Brine 99.00 Bbl Injection Disposal Well 5690201
2004 PHILLIPS EXPLORATION INC Brine 35.00 Bbl Brine or Industrial Waste Treatment Plt
2005 PHILLIPS EXPLORATION INC Brine 165.00 Bbl Brine or Industrial Waste Treatment Plt PA0095273
2006 PHILLIPS EXPLORATION INC Brine 165.00 Bbl Brine or Industrial Waste Treatment Plt PA0095273
2008 PHILLIPS EXPLORATION INC Brine 170.00 Bbl Brine or Industrial Waste Treatment Plt PA0101508
2010 PHILLIPS EXPLORATION INC Produced Fluid 6.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026310
2010 PHILLIPS EXPLORATION INC Produced Fluid 5.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2010 PHILLIPS EXPLORATION INC Produced Fluid 1.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0020346
2010 PHILLIPS EXPLORATION INC Produced Fluid 7.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2010 PHILLIPS EXPLORATION INC Produced Fluid 1.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026034
2010 PHILLIPS EXPLORATION INC Produced Fluid 45.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2010 PHILLIPS EXPLORATION INC Produced Fluid 2.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 PHILLIPS EXPLORATION INC Produced Fluid 3.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2011 PHILLIPS EXPLORATION INC Produced Fluid 2.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026310
2011 PHILLIPS EXPLORATION INC Produced Fluid 62.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2011 PHILLIPS EXPLORATION INC Produced Fluid 3.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2013 XTO ENERGY INC Produced Fluid 62 Bbl CENT WASTE TRT FAC NPDES PA0095443
2013 XTO ENERGY INC Produced Fluid 62.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2015 XTO ENERGY INC Produced Fluid 18.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273
2015 XTO ENERGY INC Produced Fluid 18 Bbl CENT WASTE TRT FAC NPDES PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1122742 Primary Facility 2002-05-13 Complaint Inspection Violation(s) Noted Inspection in response to SR 02-063-010.
1188329 Primary Facility 2002-11-20 Follow-up Inspection Recurring Violations id tag attached, e/s occuring above & below site, pit reclaimed, access rd to borrow pit still eroding
1285340 Primary Facility 2003-11-07 Follow-up Inspection No Violations Noted site and access rd. are stable, stone borrow pit is reclaimed, well is op & ID is attached
2089275 Primary Facility 2012-08-01 Routine/Complete Inspection No Violations Noted
2396649 Primary Facility 2015-07-31 Administrative/File Review In Compliance with Policy SPILL.
2396676 Primary Facility 2015-08-03 Administrative/File Review In Compliance with Policy Admin inspt in response to release reported under inspection 2396649.Upon receipt of spill report, Dept contacted and spoke to Opr rep Drew Underwood via phone at 0847.Per Mr. Underwood, a release of 4.16 bbl brine water to ground from a BT occurred as a result of the valve leaking on BT.Mr. Underwood stated that WT noticed leak while reading meter on 7/31 at 1145.Release was subsequently reported to the SWRO at 1338.Well was shut in and BT emptied.After BT was emptied, it was moved from its location so excavation of contaminated soils could commence.Mr. Underwood does not know the last time a WT was at site at time of this call, but agreed to locate info and provide it to Dept.Mr. Underwood reports that no waterways have been impacted as a result of this release.A FUI will be conducted to assess any environmental damage and/or issue any associated viols as necessary.
2396850 Primary Facility 2015-08-03 Incident- Response to Accident or Event Violation(s) Noted On-site inspt conducted in response to inspt 2396676 for 7/31 reportable release of 4.16 bbl brine water.At time of inspt, Opr rep Jason Canose and contractors on-site.BT previously emptied, disconnected, and removed from its former location.Dept observed a vertical spilt under valve of BT, which Opr believes is cause of release.Contractors actively excavating contaminated materials, utilizing a conductivity meter and visual observation as guidance.Area of excavation currently confined to former location of BT.Two roll-off boxes on-site.Dept recommended that tempBMPs are installed as necessary in order to prevent any add’l pollution events from occurring.During excavation, it was discovered that crude oil had also been released.Dept requested an updated quantity of substances released be provided to the Dept. Violations are being issued under 78.54 for this reportable release of production fluids.
2396898 Primary Facility 2015-08-04 Administrative/File Review Outstanding Violations - No Viols Req'd Admin inspection conducted in response to violations issued under inspection record 2396850 (enf ID 328459) for the reportable release of production fluids.
2417881 Primary Facility 2015-10-08 Administrative/File Review Outstanding Violations - No Viols Req'd Admin inspection in response to violations issued under inspection record 2396850 (enf ID 328459) for the reportable release of 4.16 bbl brine water/crude oil to the ground.
2420578 Primary Facility 2015-10-29 Administrative/File Review Outstanding Violations - No Viols Req'd Admin inspection in response to violations issued under inspection record 2396850 (enf ID 328459) for the reportable release of 4.16 bbl brine water/crude oil to the ground.
2425595 Primary Facility 2015-11-18 Administrative/File Review Outstanding Violations - No Viols Req'd Admin inspection in response to violations issued under inspection record 2396850 (enf ID 328459) for the reportable release of 4.16 bbl brine water/crude oil to the ground.
2429509 Primary Facility 2015-12-02 Follow-up Inspection Outstanding Violations - No Viols Req'd On-site FUI conducted in response to viols issued under record 2396850 (enf ID 328459) for reportable release of 4.16 bbl brine water/crude oil.At time of inspt, area of excavation not yet backfilled.It appears a pipeline was encountered and exposed during excavation of contaminated materials.Dept recommends Opr ensure pipeline is not, will not, and was not compromised during earth disturbance activities.Roll-off boxes no longer on-site.Orange security fence surrounding area of excavation is compromised.Temp E&S BMPs installed down-gradient of excavated area.Dept recommends Opr continue to monitor/maintain BMPs and install add’l BMPs as necessary in order to prevent any potential pollution events from occurring.WT present, legible.Damaged BT no longer located on-site.Shared AR currently stabilized.Located adjacent to ag field.Per 11/18 record 2425595, the NIR for this site has not yet been received by the ECB program.Viols issued under record 2396850 (enf ID 328459) remain outstanding.
2430243 Primary Facility 2015-12-03 Compliance Evaluation No Violations Noted Admin CEI in response to viols issued under record 2396850 (enf ID 328459) for reportable release of 4.16 bbl brine water/crude oi.In accordance w/Spill Policy,15 day initial written report received on 8/7/15 notifying Dept that Opr will be utilizing Act 2 for remediation of release.Per a 1507 phone call w/ECB Compliance Specialist E.Elliot, NIR received by Dept today 12/3/15.As Opr has initiated remediation (inspection ID 2396850) and has identified intent to remediate under Act 2 program, viols issued under record 2396850 (enf ID 328459) for reportable release of 4.16 bbl brine water/crude oil have been addressed.Dept recommends Opr cont’ to monitor/maintain site to ensure >70% uniform and adequate veg is attained for final perm stab of site upon backfilling.Upon perm stab and final restoration of site, any temp BMPs shall be properly removed.A FUI is anticipated to be conducted to ensure site is properly restored per current regs.Viols may be forthcoming pending future inspts monitoring site remediation and permanent stabilization.
2454821 Primary Facility 2016-02-22 Administrative/File Review In Compliance with Policy Admin inspection in response to violations issued under inspection record 2396850 (enf ID 328459) for the reportable release of 4.16 bbl brine water/crude oil to the ground.

In accordance with the Spill Policy, the 15 day initial written report was received on 8/7/2015 notifying the Department that the Operator will be utilizing Act 2 for the remediation of this release. The Notice of Intent to Remediate was received by the Department on 12/3/15. The Remedial Investigation/Final Report was received by the Department on 2/1/2016. Operator appears to be in compliance with policy at this time.

2470401 Primary Facility 2016-04-04 Administrative/File Review In Compliance with Policy Admin inspection in response to violations issued under inspection record 2396850 (enf ID 328459) for the reportable release of 4.16 bbl brine water/crude oil to the ground.

In accordance with the Spill Policy, the 15 day initial written report was received on 8/7/2015 notifying the Department that the Operator will be utilizing Act 2 for the remediation of this release. The Notice of Intent to Remediate was received by the Department on 12/3/15. The Remedial Investigation/Final Report was received by the Department on 2/1/2016 and subsequently approved on 3/22/2016 for all COCs identified. Operator appears to be in compliance with policy at this time.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
1122742 304754 05/13/2002 2002-05-13 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) Environmental Health & Safety
1122742 304755 05/13/2002 2002-05-13 102.4NOPLAN - No E&S plan developed, plan not on site Administrative
1188329 327464 11/20/2002 2002-11-20 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) Environmental Health & Safety
2396850 732053 07/31/2015 2015-07-31 78.54 - GENERAL REQUIREMENTS - Operator failed to control and dispose of fluids, residual waste and drill cuttings, including tophole water, brines, drilling fluids, drilling muds, stimulation fluids, well servicing fluids, oil, and production fluids Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
304754 95857 NOV - Notice of Violation Comply/Closed 2003-11-07
304755 95857 NOV - Notice of Violation Comply/Closed 2003-11-07
327464 105974 NOV - Notice of Violation Comply/Closed 2003-11-07
732053 328459 NOV - Notice of Violation Comply/Closed 2015-12-03