Well Details

Well ID: 37-063-36702
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: West Wheatfield Township
Operator Name: PENNECO OIL CO INC
Well Pad ID:
Farm/Lease Name: JAMES MCCONNELL 3
License Status:
Spud Date: 2009-11-22
Permit Date: 2009-10-26
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.456102
Longitude: -79.106683

For data sources see[1][2][3]

Well History

Date Event
2009-10-26 New Permit Application
2009-11-18 Performed Spud Operation
2009-12-02 Drilling Completion
2009-12-08 Perforation
2010-09-28 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2009 PENNECO OIL CO INC 0.00 0 0.00 0 0.00 0
2010 PENNECO OIL CO INC 5,195.00 245 0.00 0 0.00 0
2011 PENNECO OIL CO INC 5,048.00 334 0.00 0 0.00 0
2012 PENNECO OIL CO INC 3,790.00 366 0.00 0 0.00 0
2013 PENNECO OIL CO INC 2,851.00 365 0.00 0 0.00 0
2014 PENNECO OIL CO INC 2,531.00 365 0.00 0 0.00 0
2015 PENNECO OIL CO INC 2,059.91 305 0.00 0 0.00 0
2016 PENNECO OIL CO INC 2,174.71 366 0.00 0 0.00 0
2017 PENNECO OIL CO INC 1,808.00 365 0.00 0 0.00 0
2018 PENNECO OIL CO INC 1,684.68 91 0.00 0 0.00 0
2019 PENNECO OIL CO INC 1,243.87 242 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 PENNECO OIL CO INC Produced Fluid 25.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2011 PENNECO OIL CO INC Produced Fluid 144.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 PENNECO OIL CO INC Produced Fluid 35.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2011 PENNECO OIL CO INC Produced Fluid 40.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2012 PENNECO OIL CO INC Produced Fluid 30.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2013 PENNECO OIL CO INC Produced Fluid 91.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2013 PENNECO OIL CO INC Produced Fluid 91 Bbl CENT WASTE TRT FAC NPDES PA0095443
2014 PENNECO OIL CO INC Produced Fluid 27 Bbl CENT WASTE TRT FAC NPDES PA0095443
2014 PENNECO OIL CO INC Produced Fluid 27.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2015 PENNECO OIL CO INC Produced Fluid 85 Bbl CENT WASTE TRT FAC NPDES PA0095443
2015 PENNECO OIL CO INC Produced Fluid 85.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2016 PENNECO OIL CO INC Produced Fluid 70 Bbl CENT WASTE TRT FAC NPDES PA0095443
2016 PENNECO OIL CO INC Produced Fluid 70.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2017 PENNECO OIL CO INC Produced Fluid 22.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273
2019 PENNECO OIL CO INC Produced Fluid 33.33 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1845230 Primary Facility 2009-11-19 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well location marked at site. Pit dug but no aligned. Filter fence set around the site. Well sign and E&S plan located at the entrance way of site. Down gradient filter fence present along site pad. Rig not present. Called Penneco to change on-site E&S plan.
1847467 Primary Facility 2009-11-23 Routine/Complete Inspection No Violations Noted At the time of inspection, the well was actively being drilled. The site was properly signed with E&S plan onsite available for review. The pit sustained a 2ft of freeboard and was structural ok, but it is recommended that measures to secure the pit liner are enhanced, as the liner did not appear to be suitably secured with either backfill or stakes. Noted that filter fabric fence was installed down gradient from site, but it is recommended the operator monitor all sediment BMP¿s to ensure proper functioning ability in order to prevent potential pollution events such as accelerated erosion or sedimentation issues. Also noted, that inspector Paul Wyrwas made a phone call to operator noting the relocation of drill pit, which was not changed on the E&S plan. Also noted the prior approval was given, with the exception that proper landowner consent was received, that the well may be established closer than 200ft to an existing building/ water supply.
1847593 Primary Facility 2009-12-04 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Conductor pipe set at 37 ft ¿ 13 3/8 ¿pipe. Current depth at 220¿ Second stringer 9 5/8¿ pipe was set at 210 ft using 75 sks and basket at 84¿. Permit and sedimentary log present. Water not recorded. Sedimentary consisted of ss/sh alternation and coal seam. No voids or methane detected. Filter fence set around the site. Permit set for 4975 ft well.
1917839 Primary Facility 2010-09-22 Site Restoration No Violations Noted During this inspection, well properly tagged and in production. Drilling completed on 12/2/2009. Site restored with minimum 705 vegetative cover, although recommend that operator reseed to ensure that uniform coverage is achieved across the site. Access road appears stable. No accelerated erosion or sedimentation issues were noted in relation to well site or access road. Appears that brine tank may have a small seep or minor (< 5gals) release occurred during pumping of tank as discoloration along a section of bottom of tank and rock underlying tank is noted. Spoke with Dean Walters of Penneco on 9/28/10 at 930am regarding the possible concerns with the tank, operator had plans to look at tank and get back to me on findings. A follow up inspection will be conducted to ensure action has been taken and/or cleanup measures are performed as needed. Accompanied with WQS Dana Burk during inspection.
1917845 Primary Facility 2010-10-01 Follow-up Inspection No Violations Noted This inspection is being conducted as a follow-up to a possible concern with the structural integrity of brine tank. Brine tank appears empty. Side of tank and rock were slightly discolored. Spoke to landowner, who stated that operator pumped out brine tank earlier in the week and had plans to repair tank early next week.
1931748 Primary Facility 2010-12-02 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well completed with 8¿ x 4¿ pipe and reduced to 2¿ production line. Line connected to totalize meter, separator (showing 300 psi), heater running and 100 bbl brine tank (<10 bbl fluid). No signs of leakage around well head. Well tag present
2295836 Primary Facility 2014-05-07 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S or IW issues at the site. No signs of leakage around well head. Well tag present. Gas well was in production.

For data sources see[7]