37-063-36737

Well Details

Well ID: 37-063-36737
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: West Wheatfield Township
Operator Name: DIVERSIFIED OIL & GAS LLC
Well Pad ID: 149152
Farm/Lease Name: RAU UNIT 1
License Status:
Spud Date: 2010-01-25
Permit Date: 2009-12-30
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: Yes
Latitude: 40.445457
Longitude: -79.077263

For data sources see[1][2][3]

Well History

Date Event
2009-12-30 New Permit Application
2010-01-22 Performed Spud Operation
2010-03-08 Drilling Completion
2010-07-26 Perforation
2011-09-14 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 ATLAS RESOURCES LLC 25,738.00 147 0.00 0 0.00 0
2011 ATLAS RESOURCES LLC 54,414.00 365 0.00 0 0.00 0
2012 ATLAS RESOURCES LLC 36,803.00 366 0.00 0 0.00 0
2013 ATLAS RESOURCES LLC 21,581.00 274 0.00 0 0.00 0
2014 ATLAS RESOURCES LLC 24,156.00 365 0.00 0 0.00 0
2015 ATLAS RESOURCES LLC 14,496.00 365 0.00 0 0.00 0
2016 ATLAS RESOURCES LLC 6,505.00 304 0.00 0 0.00 0
2017 ATLAS RESOURCES LLC 4,305.00 207 0.00 0 0.00 0
2018 DIVERSIFIED OIL & GAS LLC 4,437.00 209 0.00 0 0.00 0
2019 DIVERSIFIED OIL & GAS LLC 2,207.01 303 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 ATLAS RESOURCES LLC Produced Fluid 96.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2010 ATLAS RESOURCES LLC Fracing Fluid Waste 680.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2010 ATLAS RESOURCES LLC Produced Fluid 8,182.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2010 ATLAS RESOURCES LLC Fracing Fluid Waste 220.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2010 ATLAS RESOURCES LLC Fracing Fluid Waste 2,485.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2010 ATLAS RESOURCES LLC Produced Fluid 495.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2010 ATLAS RESOURCES LLC Fracing Fluid Waste 12,815.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2011 ATLAS RESOURCES LLC Produced Fluid 1,050.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 ATLAS RESOURCES LLC Produced Fluid 2,454.00 Bbl INJECTION DISPOSAL WELL 34-155-23584
2011 ATLAS RESOURCES LLC Produced Fluid 2,736.00 Bbl INJECTION DISPOSAL WELL 34-013-20611
2011 ATLAS RESOURCES LLC Produced Fluid 792.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 ATLAS RESOURCES LLC Produced Fluid 3,962.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2012 ATLAS RESOURCES LLC Produced Fluid 798.00 Bbl INJECTION DISPOSAL WELL 34-013-20611
2012 ATLAS RESOURCES LLC Produced Fluid 4,606.00 Bbl INJECTION DISPOSAL WELL 34-059-24067
2013 ATLAS RESOURCES LLC Produced Fluid 2,626.00 Bbl INJECTION DISPOSAL WELL 34-059-24067
2014 ATLAS RESOURCES LLC Produced Fluid 2,287.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 ATLAS RESOURCES LLC Produced Fluid 100.00 Bbl INJECTION DISPOSAL WELL 34-121-23995
2014 ATLAS RESOURCES LLC Produced Fluid 2,024.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW005
2015 ATLAS RESOURCES LLC Produced Fluid 417.20 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW005
2015 ATLAS RESOURCES LLC Produced Fluid 117.00 Bbl INJECTION DISPOSAL WELL 34-007-20919
2015 ATLAS RESOURCES LLC Produced Fluid 1,188.80 Bbl INJECTION DISPOSAL WELL 34-155-24063
2015 ATLAS RESOURCES LLC Produced Fluid 440.00 Bbl REUSE OTHER THAN ROAD SPREADING
2015 ATLAS RESOURCES LLC Produced Fluid 168.00 Bbl INJECTION DISPOSAL WELL 34-007-21847
2016 ATLAS RESOURCES LLC Produced Fluid 209.00 Bbl INJECTION DISPOSAL WELL 34-155-24063
2017 ATLAS RESOURCES LLC Produced Fluid 192.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW001
2018 ATLAS RESOURCES LLC Produced Fluid 205.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW010

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1858481 Primary Facility 2010-01-26 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Conductor pipe set at 10¿ ¿ 30 ¿pipe and 30¿ ¿ 24¿ pipe and used 75 sks class A cement. Current depth at 60.¿ Permit and sedimentary log present. Water not recorded. Sedimentary consisted of ss/sh alternation and coal seam. Filter fence set around the site. Permit set for 9000 ft well to Marcellus.
1859413 Primary Facility 2010-01-28 Routine/Complete Inspection No Violations Noted Drill rig located onsite and drilling was ongoing at the time of the inspection. Observed three below grade pits located onsite and one was in use as a drill pit. This pit had more than the required two feet of lined freeboard. Erosion control measures had been implemented as outlined in the E&S plan located onsite. Observed no accelerated erosion & sedimentation in relation to the well-site. There was very little if any access road to speak of due to the proximity to Bethel Cemetary Road. Operator should continue to monitor the below grade pits and to insure the erosion control measures continue to function properly until well development and final restoration activities are completed.
1861583 Primary Facility 2010-02-03 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Conductor pipe set at 10¿ ¿ 30 ¿pipe and 30¿ ¿ 24¿ pipe and used 75 sks class A cement. 16¿ set at 380¿ using 350 sks and 11 ¾ ¿ to depth of 485¿ using 230 sks with 5bbl return. Current depth at 1770.¿ Permit and sedimentary log present. Sedimentary consisted of ss/sh alternation and coal seam. Filter fence set around the site. Permit set for 9000 ft well to Marcellus.
1865719 Primary Facility 2010-02-23 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Second phase of drilling continued started at 1900¿. Current depth was at 3708¿ for 77/8¿ hole. Current anticipated depth is 9200¿. Permit and sedimentary log present. Sedimentary consisted of ss/sh alternation and coal seam. Filter fence set around the site. Permit set for 9000 ft well to Marcellus.
1867384 Primary Facility 2010-03-02 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Atlas using Union 45 rig. Currently, crew repairing security fence around pit. Current depth was at 5683¿ for 77/8¿ hole. Current anticipated depth is 9200¿. Permit and sedimentary log present. Sedimentary consisted of ss/sh alternation and coal seam. Filter fence set around the site. Permit set for 9000 ft well to Marcellus.
1876968 Primary Facility 2010-04-14 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Well has been completed and Patterson Rig 263 was drilling Rau 2H well. Filter fence set around the site. Well completed as a vertical well into the Marcellus. Spud was called on 1/22/10
1883088 Primary Facility 2010-05-07 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Pit aligned with 20 mil plastic. No freeboard issues. Well has been completed and Patterson Rig 263 was removed from site and completed Rau 2H well. Filter fence set around the site. Well completed as a vertical well into the Marcellus. Spud was called on 1/22/10.
1885591 Primary Facility 2010-05-18 Routine/Complete Inspection No Violations Noted At the time of inspection, the well was drilled not yet set for production. Well site was properly signed with E&S plan at site entrance. Noted three below grade pits were installed onsite and maintained more than a 2ft of lined freeboard, although it is recommended that operator continue to monitor freeboard levels at all times. Soil pile was temporarily seeded and mulched. Observed the properly installation/functioning of temporary bmp¿s as noted in erosion and sedimentation plan. No accelerated erosion or sedimentation concerns were noted in relation to well site or access road. Operator should continue to monitor all temporary E&S controls until final restoration activities have been completed and site is permanently stabilized. (Accompanied with, Water Quality Specialist, Greg Higgins during inspection).
1900994 Primary Facility 2010-07-27 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well sign and E&S plan located at the entrance of site. Met Jim Braun at the site. Universal started Hydro frac of Rau Unit 2H well and completed Stage 1 of 8 stages. At the time, no signs of H2S odors according to Atlas.
1923363 Primary Facility 2010-10-27 Routine/Complete Inspection No Violations Noted At the time of inspection, well drilled in March 2010. Proper signage and ES plan available. Appears site has been recently seeded and mulched as<70% uniform vegetative growth is observed. Four tanks on site are surrounded by dike. No accelerated erosion or sedimentation issues observed. No H2S odors detected by operator during drilling or fracing operations. Tempoary bmp¿s installed as outlined in plan and functioning. Upon final restoration (permanent stabilization, >70% uniform vegetative growth) operator may remove all temporary bmps, until they all should be closely monitored. Access road entrance stable.
1939395 Primary Facility 2010-12-21 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S or IW issues at the site. Well tag present. Site has been restored. Well head consisted of 8¿x 4¿ x 2¿ and manifold to both wells. Wells are in production. Production equipment consisted of separator (200 psi) , heater and 4 ¿ 200 bbl brine tank (located in dike area). No signs of gas leak around equipment. Well head located in security fence.
1944048 Primary Facility 2011-01-10 Site Restoration No Violations Noted At the time of inspection, site signed with ES plan. Well drilled and in production. Well head surrounded by fencing. Four brine tanks surrounded by dike. Now IW or leaks detected. No gas or H2S odors detected. Well is within mile radius of a well that encountered a high levels H2S. Pad and access road sufficiently rocked. Site appears to be restored as adequate vegetation observed and no accelerated erosion or sedimentation issues seen. Note: some snow accumulation located onsite. Operator should continue to maintain and monitor site through winter and spring thaw to ensure site is adequately restored to permanently resist erosion. Accompanied by WQS Marc Maestra during inspection.
1981825 Primary Facility 2011-06-20 Routine/Complete Inspection No Violations Noted 2 tanks of 4 tank battery identified with well. Tag and e&s ok.
2028937 Primary Facility 2011-12-21 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S concerns were present at the site. Well tag was present. Well was in production.
2102301 Primary Facility 2012-09-19 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S concerns were present at the site. Well tag was present. Well was in production.
2207590 Primary Facility 2013-09-19 Routine/Complete Inspection No Violations Noted Mutiple well location. Site has been restored. At time of inspection, Unit #1 is equipped for production. Well is surrounded by protective barrier. Access road is in good condition. (4) Brine tanks appear to be structurally sound and are within a vegetated dike. They are located slightly west of the pad along cornfield. The Dept. did not observe accelerated erosion issues. Site ID sign and well tag are present.
2232843 Primary Facility 2013-12-31 Routine/Complete Inspection No Violations Noted 2 tanks of 4 onsite for well. Tag and e&s ok.
2233816 Primary Facility 2014-01-02 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S concerns were present at the site. Well tag was present. Well was in production.
2234810 Primary Facility 2014-01-08 Routine/Complete Inspection No Violations Noted Mutiple well location. Site has been restored. At time of inspection, Unit #1 is equipped for production. Well is surrounded by protective barrier. Access road is in good condition. (4) Brine tanks appear to be structurally sound and are within a vegetated dike. They are located slightly west of the pad along cornfield. Site is covered in snow making assessment of vegetation growth and E&S controls difficult. Well tag present.
2318135 Primary Facility 2014-09-19 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S concerns were present at the site. Well tag was present. Well was in production.
2337072 Primary Facility 2015-01-20 Routine/Complete Inspection No Violations Noted At the time of inspection, no E&S concerns were present at the site. Well tag was present. Well was in production.
2368627 Primary Facility 2015-05-11 Routine/Complete Inspection No Violations Noted system running. no issues
2382925 Primary Facility 2015-06-15 Routine/Complete Inspection No Violations Noted No issues. system running
2418236 Primary Facility 2015-08-31 Routine/Complete Inspection No Violations Noted At the time of inspection, no concerns were present at the site. Well tag was present. Well was in production
2438005 Primary Facility 2015-11-14 Routine/Complete Inspection No Violations Noted well in production
2439008 Primary Facility 2015-12-26 Routine/Complete Inspection No Violations Noted At the time of inspection, well tag present. Well was in production.
2473131 Primary Facility 2016-04-06 Routine/Complete Inspection No Violations Noted no issues. system running
2478016 Primary Facility 2016-04-07 Routine/Complete Inspection No Violations Noted
2488859 Primary Facility 2016-05-26 Routine/Complete Inspection No Violations Noted no issues. system running
2511804 Primary Facility 2016-08-16 Routine/Complete Inspection No Violations Noted system running. no issues
2538948 Primary Facility 2016-11-14 Routine/Complete Inspection No Violations Noted system running no issues
2579326 Primary Facility 2017-03-02 Routine/Complete Inspection No Violations Noted system running no issues
2583050 Primary Facility 2017-04-13 Routine/Complete Inspection No Violations Noted Multi-well pad. Marcellus. At time of inspection, well drilled and appears equipped for production. Wells surrounded by gate. Well tag present, legible.
2688714 Primary Facility 2018-01-31 Routine/Complete Inspection No Violations Noted System producing. Emergency contact present. Well tag present.
2706438 Primary Facility 2018-03-16 Routine/Complete Inspection No Violations Noted Wellhead has well tag showing api number well name and emergency contact. Annulus open at well head. Production reporting up to date.
2834069 Primary Facility 2019-01-29 Routine/Complete Inspection No Violations Noted On 1/29/19 at 1149 hrs., I conducted a routine inspection of Diversified Oil & Gas, LLC's RAU Unit 1 well (API 063-36737) in West Wheatfield Twp., Indiana Co. Snow cover prevented proper evaluation of site stabilization. The pad appears to be restored and permanently stabilized. The well is equipped for production and a site ID sign is posted. A well tag is present at the well head. There are 4 production fluid tanks located within adequate secondary containment. There are no violations noted for this inspection.

For data sources see[7]