If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 37-063-36827 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.534092,"lon":-79.198464,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Indiana | |
Municipality: Center Township | |
Operator Name: XTO ENERGY INC | |
Well Pad ID: 148549 | |
Farm/Lease Name: HOMER CITY POWER PLANT 8421H | |
License Status: | |
Spud Date: 2010-05-19 | |
Permit Date: 2010-04-21 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 40.534092 | |
Longitude: -79.198464 |
Date | Event |
---|---|
2010-04-21 | New Permit Application |
2010-05-19 | Performed Spud Operation |
2010-07-02 | Drilling Completion |
2010-08-10 | Perforation |
2011-01-24 | DEVIATED |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2010 | XTO ENERGY INC | 371,204.00 | 122 | 0.00 | 0 | 0.00 | 0 |
2011 | XTO ENERGY INC | 660,593.00 | 363 | 0.00 | 0 | 0.00 | 0 |
2012 | XTO ENERGY INC | 423,230.00 | 366 | 0.00 | 0 | 0.00 | 0 |
2013 | XTO ENERGY INC | 372,920.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2014 | XTO ENERGY INC | 263,187.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2015 | XTO ENERGY INC | 227,861.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2016 | XTO ENERGY INC | 206,916.00 | 316 | 0.00 | 0 | 0.00 | 0 |
2017 | XTO ENERGY INC | 103,680.00 | 351 | 0.00 | 0 | 0.00 | 0 |
2018 | XTO ENERGY INC | 172,563.28 | 356 | 0.00 | 0 | 0.00 | 0 |
2019 | XTO ENERGY INC | 185,645.60 | 356 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2010 | XTO ENERGY INC | Produced Fluid | 6,038.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2010 | XTO ENERGY INC | Drilling Fluid Waste | 549.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0091472 |
2010 | XTO ENERGY INC | Produced Fluid | 160.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095443 |
2010 | XTO ENERGY INC | Fracing Fluid Waste | 1,272.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2010 | XTO ENERGY INC | Fracing Fluid Waste | 4,534.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | 101674 |
2011 | XTO ENERGY INC | Produced Fluid | 738.00 Bbl | INJECTION DISPOSAL WELL | 34-133-24096 |
2011 | XTO ENERGY INC | Produced Fluid | 104.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | EPA ID: 748-163 |
2011 | XTO ENERGY INC | Produced Fluid | 204.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0254185 |
2011 | XTO ENERGY INC | Produced Fluid | 160.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0091472 |
2011 | XTO ENERGY INC | Produced Fluid | 1,609.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2011 | XTO ENERGY INC | Produced Fluid | 689.00 Bbl | INJECTION DISPOSAL WELL | 34-133-21076 |
2012 | XTO ENERGY INC | Produced Fluid | 314.00 Bbl | INJECTION DISPOSAL WELL | 34-133-24096 |
2012 | XTO ENERGY INC | Produced Fluid | 92.00 Bbl | INJECTION DISPOSAL WELL | 34-133-24189 |
2012 | XTO ENERGY INC | Produced Fluid | 2,409.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0254185 |
2012 | XTO ENERGY INC | Produced Fluid | 92.00 Bbl | INJECTION DISPOSAL WELL | 34-133-21076 |
2013 | XTO ENERGY INC | Produced Fluid | 319.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0254185 |
2013 | XTO ENERGY INC | Produced Fluid | 304.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0254185 |
2013 | XTO ENERGY INC | Produced Fluid | 304.00 Bbl | CENT WASTE TRT FAC NPDES | PA0254185 |
2013 | XTO ENERGY INC | Produced Fluid | 496.00 Bbl | RESIDUAL WASTE TRANSFER FACILITY | 101674 |
2014 | XTO ENERGY INC | Produced Fluid | 221.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
2014 | XTO ENERGY INC | Produced Fluid | 499.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NW009 |
2015 | XTO ENERGY INC | Produced Fluid | 465.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NW009 |
2015 | XTO ENERGY INC | Produced Fluid | 67.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
2016 | XTO ENERGY INC | Produced Fluid | 1.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | ORDER 2014-04 |
2016 | XTO ENERGY INC | Produced Fluid | 432.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NW009 |
2016 | XTO ENERGY INC | Produced Fluid | 336.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW009 |
2017 | XTO ENERGY INC | Produced Fluid | 90.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2017 | XTO ENERGY INC | Produced Fluid | 40.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW009 |
2018 | XTO ENERGY INC | Other Oil & Gas Wastes | 33.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW009 |
2018 | XTO ENERGY INC | Produced Fluid | 288.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW009 |
2019 | XTO ENERGY INC | Produced Fluid | 270.00 Bbl | INJECTION DISPOSAL WELL | 34-133-21076 |
2019 | XTO ENERGY INC | Produced Fluid | 652.00 Bbl | INJECTION DISPOSAL WELL | 34-133-24189 |
2019 | XTO ENERGY INC | Produced Fluid | 375.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW009 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
1886284 | Primary Facility | 2010-05-19 | Drilling/Alteration | No Violations Noted | Remarks: Inspection shows contractor, Nabors Drilling rigged up preparing to commence drilling operations. |
1887966 | Primary Facility | 2010-05-19 | Drilling/Alteration | No Violations Noted | MARCELLUS - drilling/E&S ok/pit&ID ok |
1889899 | Primary Facility | 2010-05-28 | Drilling/Alteration | Violation(s) Noted | |
1890997 | Primary Facility | 2010-06-03 | Routine/Complete Inspection | No Violations Noted | Marcellus well. Well being drilled at time of inspection. |
1891024 | Primary Facility | 2010-06-03 | Routine/Complete Inspection | No Violations Noted | Marcellus well. Well being drilled at time of inspection. E&S plan on site. ESCGP-1 inspection/review revealed the following: |
1891076 | Primary Facility | 2010-06-09 | Routine/Complete Inspection | No Violations Noted | Marcellus well. Inspection conducted with oil & gas inspector Rick Hoover in response to possible gas migration at well. |
1892993 | Primary Facility | 2010-06-09 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | 0800hrs notified of gas to surface on annulus of 9 5/8 casing. |
1893002 | Primary Facility | 2010-06-10 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | LOGGING WITH HALLIBURTON WELL SERVICES |
1893005 | Primary Facility | 2010-06-16 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | LOGGING WITH HALLIBURTON WELL SERVICES |
1893008 | Primary Facility | 2010-06-14 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | DRILLING ON CEMENT RETAINER |
1894911 | Primary Facility | 2010-06-25 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | DRILLING AT 9,139 FT. |
1894921 | Primary Facility | 2010-06-22 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | DRILLING AT 7,773 FT. |
1896080 | Primary Facility | 2010-07-01 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | 5.5" production casing set @ 11,330 - cemented to surface |
1897022 | Primary Facility | 2010-06-11 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | MARCELLUS - drilling suspended due to annular gas migration/monitored 3 staged squeeze jobs |
1897246 | Primary Facility | 2010-07-09 | Drilling/Alteration | Outstanding Violations - No Viols Req'd | |
1909432 | Primary Facility | 2010-08-17 | Routine/Complete Inspection | Outstanding Violations - No Viols Req'd | well being equipped for production/E&S ok/ID ok |
1915202 | Primary Facility | 2010-09-22 | Routine/Complete Inspection | No Violations Noted | Marcellus well. Site ID sign in place. E&S plan on site. ESCGP-1 plan approval on site. Well just recently equipped for production. |
1915685 | Primary Facility | 2010-09-22 | Routine/Complete Inspection | Outstanding Violations - No Viols Req'd | |
1917378 | Primary Facility | 2010-09-28 | Routine/Complete Inspection | Outstanding Violations - No Viols Req'd | |
1917419 | Primary Facility | 2010-10-01 | Routine/Complete Inspection | Outstanding Violations - No Viols Req'd | |
1921895 | Primary Facility | 2010-10-05 | Routine/Complete Inspection | No Violations Noted | |
1928242 | Primary Facility | 2010-11-18 | Administrative/File Review | No Violations Noted | review files for completion of Consent Order. |
1960632 | Primary Facility | 2011-03-24 | Routine/Complete Inspection | No Violations Noted | |
2042785 | Primary Facility | 2012-02-02 | Routine/Complete Inspection | No Violations Noted | Routine inspection. Drilling completed on 7/02/10. Well tag present. Well drilled and equipped for prodcution. Access road ok, minor rutting exhibited. Pad adequately rocked. It appears that site has been seeded/mulch with observed growth,although department reccomends operator reseed in spring to ensure uniform 70% vegeative cover is maintained. Temporary bmp's located/functioning down gradient from site. No accelerated erosion or sedimenation isues noted on site or access road. Prodcution equipment located in metal containment dike. Recommend operator properly dipose of water stormwater accumulated in dike. No violations noted during this inspection. |
2053591 | Primary Facility | 2012-03-20 | Routine/Complete Inspection | No Violations Noted | |
2089073 | Primary Facility | 2012-08-01 | Routine/Complete Inspection | No Violations Noted | During this inspection, well tag present. Access road exhibits minor rutting due to recent heavy rains recommend operator ocntinue to closely monitor and maitain access raod in order to prevent a possible pollution event. Well drilled and in prodcution. Temporary bmp's downgradient from well pad present, recommend operator remove as site appears permently stabilized with adequte rock and vegetation capable of resisting erosion. Brine tank locked within lined metal containment. No IW issues noted at time of inspection. No violations noted during inspection. |
2136266 | Primary Facility | 2013-01-31 | Routine/Complete Inspection | No Violations Noted | During this inspection, well tag present. Access road exhibits minor rutting recommend operator ocntinue to closely monitor and maitain access road in order to prevent a possible pollution event. Well drilled (TD 7/02/10) and in prodcution. Site appears permanently stabilized with adequate rock and vegetative cover capable of resisting erosion. Brine tank locked within lined metal containment. Vent placed on well, due to heavy winds unable to determine if well currently venting gas. No IW issues noted at time of inspection. No violations noted during inspection. |
2181065 | Primary Facility | 2013-06-13 | Administrative/File Review | In Compliance with Policy | On-site meeting with XTO rep Dan Rice regarding site restoration. Mr. Rice requested meeting to show Department small unvegetated mound on far left corner of pad when standing at access road entrance. Mound will not remain vegetated. Department recommended Operator rock mound to ensure stabilization is maintained. |
2436447 | Primary Facility | 2015-12-18 | Routine/Complete Inspection | No Violations Noted | Horizonal Marcellus |
2502626 | Primary Facility | 2016-07-18 | Routine/Complete Inspection | No Violations Noted | Single well Marcellus site. Well appears equipped for production.
At time of inspection site ID sign, well permit, E&S plan, ESCGP, and PPC plan all on site. No E&S issues observed in relation to the access road or the well pad. Well tag present and legible. Brine tank located in secondary containment appears structurally sound. |
2519647 | Primary Facility | 2016-09-13 | Routine/Complete Inspection | No Violations Noted | Marcellus site.
At time of inspection Site ID sign, PPC plan, E&S plan, Well permit, and ESCGP on site. Access road and pad rocked. No E&S issues observed on access road or on site. It appears well is equipped for production. Well head surrounded by fence. Well tag present and legible. Brine tank located in secondary containment appears structurally sound. The NOT for the ESCGP-1 associated with this well site (ESX09-063-0005) has been approved at the time of this inspection. |
2621326 | Primary Facility | 2017-08-02 | Routine/Complete Inspection | No Violations Noted | Marcellus. At time of inspection, well drilled and appears equipped for production. Surrounded by chain-link fence, cement barriers. |
2623184 | Primary Facility | 2017-08-08 | Routine/Complete Inspection | No Violations Noted | |
2758955 | Primary Facility | 2018-08-01 | Routine/Complete Inspection | No Violations Noted | Well appears to be in good working condition. |
2786816 | Primary Facility | 2018-10-10 | Routine/Complete Inspection | No Violations Noted | Well appears equipped for production. Well head surrounded by cement barriers and security fence. |
Inspection ID | Violation ID | Violation Date | Date Resolved | Violation Code | Violation Type | Violation Comments |
---|---|---|---|---|---|---|
1889899 | 588966 | 05/28/2010 | 2010-05-28 | 78.83GRNDWTR - Improper casing to protect fresh groundwater | Administrative |
Violation ID | Penalty ID | Penalty Code | Penalty Status | Penalty Date | Enforcement Date | Penalty Amount | Amount Collected |
---|---|---|---|---|---|---|---|
588966 | 258913 | NOV - Notice of Violation | Unresolvable | 2010-07-09 | |||
588966 | 265673 | CACP - Consent Assessment of Civil Penalty | Comply/Closed | 2010-12-10 | 2010-12-10 | $150,000.00 | $150,000.00 |
For data sources see[7]