37-081-20119

Well Details

Well ID: 37-081-20119
Loading map...
Country: United States
State: Pennsylvania
County: Lycoming
Municipality: Penn Township
Operator Name: EXCO RESOURCES PA LLC
Well Pad ID: 147783
Farm/Lease Name: BARTO UNIT 2H
License Status: ACTIVE
Spud Date:
Permit Date: 2008-09-09
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.270804
Longitude: -76.659747

For data sources see[1][2][3]

Well History

Date Event
2008-09-09 New Permit Application
2008-11-04 Performed Spud Operation
2009-02-24 Drilling Completion
2009-04-04 Perforation
2009-04-10 DEVIATED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2008 CHIEF OIL & GAS LLC 0.00 0 0.00 0 0.00 0
2009 CHIEF OIL & GAS LLC 760984.00 266 0.00 0 0.00 0
2010 CHIEF OIL & GAS LLC 673,446.00 366 0.00 0 0.00 0
2011 EXCO RESOURCES PA LLC 325,399.00 305 0.00 0 0.00 0
2012 EXCO RESOURCES PA LLC 333,795.00 366 0.00 0 0.00 0
2013 EXCO RESOURCES PA LLC 296,615.00 365 0.00 0 0.00 0
2014 EXCO RESOURCES PA LLC 240,988.00 365 0.00 0 0.00 0
2015 EXCO RESOURCES PA LLC 229,294.00 311 0.00 0 0.00 0
2016 EXCO RESOURCES PA LLC 188,690.00 278 0.00 0 0.00 0
2017 EXCO RESOURCES PA LLC 237,515.00 338 0.00 0 0.00 0
2018 EXCO RESOURCES PA LLC 207,756.00 364 0.00 0 0.00 0
2019 EXCO RESOURCES PA LLC 222,194.00 364 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2009 CHIEF OIL & GAS LLC Fracking Fluid 2,366.00 Bbl Brine or Industrial Waste Treatment Plt PA0101508
2009 CHIEF OIL & GAS LLC Drilling 37,176.00 Bbl Brine or Industrial Waste Treatment Plt PA0101508
2009 CHIEF OIL & GAS LLC Brine 261.00 Bbl Brine or Industrial Waste Treatment Plt PA0101508
2009 CHIEF OIL & GAS LLC Fracking Fluid 8,464.00 Bbl Brine or Industrial Waste Treatment Plt PA0028665
2010 CHIEF OIL & GAS LLC Produced Fluid 131.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2010 CHIEF OIL & GAS LLC Fracing Fluid Waste 534.50 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2010 CHIEF OIL & GAS LLC Produced Fluid 134.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2010 CHIEF OIL & GAS LLC Drilling Fluid Waste 1,272.50 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2010 CHIEF OIL & GAS LLC Produced Fluid 608.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW018
2010 CHIEF OIL & GAS LLC Produced Fluid 290.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2010 CHIEF OIL & GAS LLC Produced Fluid 210.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2011 CHIEF OIL & GAS LLC Produced Fluid 1,745.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2011 EXCO RESOURCES PA LLC Produced Fluid 119.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 EXCO RESOURCES PA LLC Produced Fluid 119.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAS2D205BCLE
2011 EXCO RESOURCES PA LLC Produced Fluid 714.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2011 EXCO RESOURCES PA LLC Produced Fluid 762.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0008451
2012 EXCO RESOURCES PA LLC Produced Fluid 1,984.76 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2012 EXCO RESOURCES PA LLC Produced Fluid 219.04 Bbl REUSE OTHER THAN ROAD SPREADING
2012 EXCO RESOURCES PA LLC Drill Cuttings 12.99 Tons LANDFILL 301358
2013 EXCO RESOURCES PA LLC Produced Fluid 109.52 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR119
2013 EXCO RESOURCES PA LLC Produced Fluid 180.95 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC009
2013 EXCO RESOURCES PA LLC Produced Fluid 119.02 Bbl STORAGE PENDING DISPOSAL OR REUSE
2013 EXCO RESOURCES PA LLC Produced Fluid 766.64 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2014 EXCO RESOURCES PA LLC Produced Fluid 177.40 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2014 EXCO RESOURCES PA LLC Produced Fluid 51.30 Bbl REUSE OTHER THAN ROAD SPREADING
2014 EXCO RESOURCES PA LLC Produced Fluid 193.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2014 EXCO RESOURCES PA LLC Produced Fluid 277.60 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR119
2014 EXCO RESOURCES PA LLC Produced Fluid 51.20 Bbl STORAGE PENDING DISPOSAL OR REUSE
2014 EXCO RESOURCES PA LLC Produced Fluid 27.40 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2015 EXCO RESOURCES PA LLC Produced Fluid 415.60 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2015 EXCO RESOURCES PA LLC Produced Fluid 78.60 Bbl REUSE OTHER THAN ROAD SPREADING
2016 EXCO RESOURCES PA LLC Produced Fluid 439.00 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2017 EXCO RESOURCES PA LLC Produced Fluid 607.40 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2018 EXCO RESOURCES PA LLC Produced Fluid 25.60 Bbl REUSE (AT WELL PAD)
2018 EXCO RESOURCES PA LLC Produced Fluid 504.00 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2018 EXCO RESOURCES PA LLC Produced Fluid 169.60 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2019 EXCO RESOURCES PA LLC Produced Fluid 376.20 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2019 EXCO RESOURCES PA LLC Produced Fluid 107.50 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1755973 Primary Facility 2008-12-11 Routine/Complete Inspection No Violations Noted
1760457 Primary Facility 2009-01-06 Routine/Complete Inspection No Violations Noted
1770691 Primary Facility 2009-02-19 Drilling/Alteration Violation(s) Noted
1899629 Primary Facility 2010-07-21 Routine/Partial Inspection No Violations Noted
1929507 Primary Facility 2010-11-15 Follow-up Inspection No Violations Noted
1931770 Primary Facility 2010-12-03 Follow-up Inspection No Violations Noted
1942087 Primary Facility 2011-01-06 Routine/Complete Inspection No Violations Noted
1942181 Primary Facility 2011-01-10 Routine/Complete Inspection Violation(s) Noted
1965807 Primary Facility 2011-04-14 Routine/Complete Inspection No Violations Noted
2069505 Primary Facility 2012-05-18 Routine/Complete Inspection No Violations Noted
2077096 Primary Facility 2012-06-20 Routine/Complete Inspection No Violations Noted
2083396 Primary Facility 2012-07-12 Routine/Complete Inspection No Violations Noted
2120905 Primary Facility 2012-12-04 Complaint Inspection No Violations Noted
2469496 Primary Facility 2016-03-22 Routine/Complete Inspection No Violations Noted At the time of the inspection two wells (081-20109 and 081-20119) were onsite in production. The well pad remains at the originally permitted size and PCSM was implemented for the entire well pad area as permitted by the Lycoming CCD. The well pad is being used as a storage yard for various materials. Please remove the materials/equipment or provide the landowners consent for storage of materials onsite under § 3216 (c) OGA. At some time since the original pad was constructed, the access road was re-routed to accommodate the Barto Compressor Station. The Barto Compressor Station and the re-route of a portion of the access road to your site were covered under ESCGP-1 #4108803 issued to Chief Gathering and currently owned by Regency Energy (Energy Transfer Partners). The plans for the Barto 1-6H well pad do not reflect the current conditions onsite and the permit has now expired. The Department requests you re-permit this well pad from the LOD of the adjacent ESCGP-1# 4108803 to accommodate the well site
2658495 Primary Facility 2017-10-25 Routine/Complete Inspection No Violations Noted The PCSM/Well Site Restoration plans were recently implemented and stabilized with hydro-seed. The footprint of the well pad surface has also been reduced. The 2-part outlet structure on the infiltration basin at the entrance to the site is currently not sealed. This condition currently allows water to discharge several inches below the design capacity. In addition, implementation of the two infiltration basins is not functioning as designed. Currently, water is discharging between the two infiltration features. This concentrated-flow is causing erosion and renders the structures ineffective. Erosion and sedimentation was not noted outside the perimeter E & S controls. I recommend addressing the stabilization, erosion, and PCSM noted above. No violations noted.
2694336 Primary Facility 2018-02-14 Routine/Complete Inspection No Violations Noted Weather was 30° and cloudy at time of inspection. Well has a digital gauge attached to the swab valve and also to the 5 1/2 casing valve. The digital gauge attached to the swab valve read 240 psi and the 5 1/2 casing gauge read 418 psi at time of inspection. There were 2 annulus vents observed during the inspection, but it was unable to be determined where each vent originated from. 0% combustible gas was detected in any location at time of inspection. There was an illegible well tag laying on the ground by the well however no legible well tag with the API number was attached to the well at time of inspection. No violations were noted at time of inspection.
2793330 Primary Facility 2018-10-23 Routine/Complete Inspection No Violations Noted Two wells in a production phase. Two GPUs within containment. No leaks from production equipment. No violations noted.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
1770691 556776 02/19/2009 2009-02-19 201G - Failure to post permit number, operator name, address, telephone number in a conspicuous manner at the site during drilling Administrative
1770691 556777 02/19/2009 2009-02-19 601.101 - O&G Act 223-General. Used only when a specific O&G Act code cannot be used Administrative
1942181 602819 01/10/2011 2011-01-10 78.85 - Inadequate, insufficient, and/or improperly installed cement Environmental Health & Safety 250psi on the 5 1/2 x 9 5/8 and may be connected to other annuli such as the 9 5/8 x 13 3/8 annulus. stone in cellar. Steven Travis from American Peak Production who was present told me that he is not certain that the pressure is limited to only annulus
1942181 602820 01/10/2011 2011-01-10 78.86* - Failure to report defective, insufficient, or improperly cemented casing w/in 24 hrs or submit plan to correct w/in 30 days Administrative 250psi on the 5 1/2 x 9 5/8 and may be connected to other annuli such as the 9 5/8 x 13 3/8 annulus. stone in cellar. Steven Travis from American Peak Production who was present told me that he is not certain that the pressure is limited to only annulus