37-105-21850

Well Details

Well ID: 37-105-21850
Loading map...
Country: United States
State: Pennsylvania
County: Potter
Municipality: Summit Township
Operator Name: JKLM ENERGY LLC
Well Pad ID: 149395
Farm/Lease Name: SWEDEN VALLEY 102 3HU
License Status:
Spud Date:
Permit Date: 2015-05-14
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 41.717201
Longitude: -77.899922

For data sources see[1][2][3]

Well History

Date Event
2015-05-14 New Permit Application
2015-06-02 Performed Spud Operation
2015-08-25 Drilling Completion
2015-09-20 Perforation
2016-01-15 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2015-09-19 2015-09-27 11,586 8,054,810 0
2 2015-09-19 2015-09-27 11,586 7,000,000 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Scale Inhibitor, LSI-20 Trican Scale Inhibitor Organic Phosphonic Acid Salts Proprietary 20 0.00344766 2625.12
Methanol 67-56-1 15 0.00258574 1968.84
Sand (Proppant) Trican Proppant Crystalline silica: Quartz (SiO2) 14808-60-7 100 10.6168 8,083,880.0
Iron Control, FEAC-20 Trican Iron Control Acetic acid 64-19-7 45 0.00207179 1577.51
Citric acid 77-92-9 30 0.00138119 1051.67
Friction Reducer, FR-20 Trican Friction Reducer Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00154964 1179.93
Mineral oil/ light hydrotreated pet. distillate 64742-47-8 20 0.0154964 11799.3
9-Octadecenamide,N,N-bis(2-hydroxyethyl)-, (9Z) 93-83-4 2 0.00154964 1179.93
Ammonium Chloride 12125-02-9 1 0.000774821 589.965
Ethanaminium, N,N,N-trimethyl-2-[(1-oxo-2-propenyl)oxy]-,
chloride, polymer with 2-propenamide
69418-26-4 30 0.0232446 17698.9
Water Baker Hughes Carrier Water 7732-18-5 100 99.9993 67,952,200.0
Water 7732-18-5 100 88.2789 67,217,400.0
Chlorine Dioxide Baker Hughes Biocide Chlorine Dioxide 10049-04-4 0.3 0.000674937 458.637
Hydrochloric Acid (28%) Trican Acidizing Water 7732-18-5 72 0.00259078 1972.68
Hydrochloric Acid 7647-01-0 28 0.00100753 767.153
Acid Inhibitor, AI-11 Trican Acid Inhibitor Potassium Iodide 7681-11-0 5 0.00009754 74.271
Propargyl alcohol derivative Proprietary 60 0.0011705 891.246
Prop-2-yn-1-ol 107-19-7 1 0.00001951 14.854
Water JKLM Carrier/Base Fluid
Hydrochloric Acid (7.5%) Trican Acidizing Hydrochloric Acid 7647-01-0 7.5 0.0749575 57074.2
Water 7732-18-5 92.5 0.924476 703915

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2015 JKLM ENERGY LLC 0.00 0 0.00 0 0.00 0
2016 JKLM ENERGY LLC 3,010,803.32 351 0.00 0 0.00 0
2017 JKLM ENERGY LLC 1,258,114.44 359 0.00 0 0.00 0
2018 JKLM ENERGY LLC 801,493.00 353 0.00 0 0.00 0
2019 JKLM ENERGY LLC 45,080.00 24 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2015 JKLM ENERGY LLC Drilling Fluid Waste 2,200.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2015 JKLM ENERGY LLC Fracturing Fluid Waste 5.70 Tons LANDFILL 301358
2015 JKLM ENERGY LLC Drill Cuttings 2,358.60 Tons LANDFILL 301358
2015 JKLM ENERGY LLC Drilling Fluid Waste 5,310.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW005
2015 JKLM ENERGY LLC Drilling Fluid Waste 2,200.00 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2015 JKLM ENERGY LLC Fracing Fluid Waste 5,720.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 3192
2015 JKLM ENERGY LLC Drilling Fluid Waste 49.76 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR097R017
2015 JKLM ENERGY LLC Basic Sediment 1,200.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW009
2015 JKLM ENERGY LLC Drill Cuttings 1,321.83 Tons LANDFILL NY # 02S17
2015 JKLM ENERGY LLC General O&G waste not covered by other waste types 99.52 Tons RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR097R017
2015 JKLM ENERGY LLC Fracing Fluid Waste 1,080.00 Bbl INJECTION DISPOSAL WELL 34-155-24078
2015 JKLM ENERGY LLC Fracing Fluid Waste 26,610.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW009
2016 JKLM ENERGY LLC Produced Fluid 14,095.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2016 JKLM ENERGY LLC Soil Contaminated by Oil & Gas Related Spills 15.72 Tons LANDFILL 301358
2016 JKLM ENERGY LLC Drilling Fluid Waste 1,940.00 Bbl CENT WASTE TRT FAC NPDES PA0254185
2016 JKLM ENERGY LLC Produced Fluid 345.00 Bbl INJECTION DISPOSAL WELL 34-133-20114
2016 JKLM ENERGY LLC Fracturing Fluid Waste 4,520.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW009
2016 JKLM ENERGY LLC Produced Fluid 815.00 Bbl INJECTION DISPOSAL WELL 34-133-24096
2016 JKLM ENERGY LLC Produced Fluid 7,240.00 Bbl CENT WASTE TRT FAC NPDES PA0254185
2016 JKLM ENERGY LLC Produced Fluid 955.74 Bbl CENT WASTE TRT FAC NPDES PA0102784
2016 JKLM ENERGY LLC Produced Fluid 7,240.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0254185
2016 JKLM ENERGY LLC Drilling Fluid Waste 1,940.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0254185
2016 JKLM ENERGY LLC Soil Contaminated by Oil 15.72 Tons LANDFILL 301358
2016 JKLM ENERGY LLC Drilling Fluid Waste 7,085.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW009
2016 JKLM ENERGY LLC Produced Fluid 955.74 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0102784
2016 JKLM ENERGY LLC Produced Fluid 46,348.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2017 JKLM ENERGY LLC Other Oil & Gas Wastes 755.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2017 JKLM ENERGY LLC Produced Fluid 8,225.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2017 JKLM ENERGY LLC Other Oil & Gas Wastes 1,145.00 Bbl REUSE (AT WELL PAD)
2017 JKLM ENERGY LLC Produced Fluid 5,560.00 Bbl REUSE (AT WELL PAD)
2017 JKLM ENERGY LLC Produced Fluid 3,885.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2017 JKLM ENERGY LLC Produced Fluid 130.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2017 JKLM ENERGY LLC Drilling Fluid Waste 77.00 Bbl REUSE (AT WELL PAD)
2017 JKLM ENERGY LLC Synthetic Liner Materials 8.00 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Synthetic Liner Materials 3.94 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Produced Fluid 103.24 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 JKLM ENERGY LLC Produced Fluid 2,814.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 460.00 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Produced Fluid 1,179.52 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 JKLM ENERGY LLC Produced Fluid 1,937.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2018 JKLM ENERGY LLC Produced Fluid 234.00 Bbl INJECTION DISPOSAL WELL 34-133-24189
2018 JKLM ENERGY LLC Produced Fluid 4,141.00 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Produced Fluid 245.00 Bbl INJECTION DISPOSAL WELL 34-133-24096
2018 JKLM ENERGY LLC Produced Fluid 1,225.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2019 JKLM ENERGY LLC Synthetic Liner Materials 15.13 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Produced Fluid 220.00 Bbl STORAGE PENDING DISPOSAL OR REUSE WMGR123NC038
2019 JKLM ENERGY LLC Produced Fluid 2,960.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 JKLM ENERGY LLC Produced Fluid 990.00 Bbl REUSE (AT WELL PAD)
2019 JKLM ENERGY LLC Produced Fluid 1,938.95 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2375252 Primary Facility 2015-06-02 Preoperation Inspection No Violations Noted Preop inspection at Sweden Valley 102 pad. Pad has been expanded. Construction/stabilization work nearly complete. Perimeter controls installed and majority of disturbed areas stabilized. Anticipate spudding of 3HU well on 6/2/15. TLT
2377498 Primary Facility 2015-06-09 Routine/Complete Inspection Violation(s) Noted
2386000 Primary Facility 2015-06-29 Incident- Response to Accident or Event Violation(s) Noted Incident inspection to document release of an estimated 275 gallons of phosphonic acid. Release occurred when a tote of anti-corrosion agent was punctured. Release cleanup and mitigation was initiated shortly after the release was discovered. TLT
2392130 Primary Facility 2015-07-13 Incident- Response to Accident or Event Violation(s) Noted Inspection to document 63 gal calcium chloride release reported 7/7/15, which had been cleaned up. While on site, evidence of a new release was observed along the east side of the pad. Multiple damp areas on pad surface immediately adjacent to the containment. Containment nearly full with high conductivity fluid. Two samples collected. Sample results confirm pollutional substance on pad surface. TLT
2392957 Primary Facility 2015-07-23 Routine/Complete Inspection No Violations Noted
2413444 Primary Facility 2015-10-02 Routine/Complete Inspection No Violations Noted
2418192 Primary Facility 2015-10-14 Routine/Complete Inspection No Violations Noted
2425145 Primary Facility 2015-11-09 Administrative/File Review No Violations Noted 11/9/15 - The DEP has received the Site Characterization Action Completion report regarding the releases at the Sweden Valley Pad 102 (105-21850). The review will be conductance in accordance with the Alternativer Remdiation provision of the department policy document 800-5000-001 - Addressing Spills and Releases at Oil and Gas Well Sites or Access Roads.
2440848 Primary Facility 2015-12-31 Administrative/File Review No Violations Noted The DEP has reviewed the 11/2/15 document titled "Combination Site Characterization Report and Remedial Action Plan" submitted for this site in accordance with the Alternative Remediation provision of the department policy document 800-5000-001 Addressing Spills and Releases at Oil and Gas Well Sites and Access Roads; no technical deficiencies were noted.
2442638 Primary Facility 2016-01-19 Follow-up Inspection Outstanding Violations - No Viols Req'd Inspection to follow up on the 6/27/15 phosphonic acid spill and the 7/13/15 brine release. Areas where soil was excavated in association with the releases were observed. The site was snow covered and ground was frozen. No new violations were cited. The spill violations remain outstanding and will be resolved upon receipt and review of the Remedial Action Completion Reports. TLT
2443706 Primary Facility 2016-01-06 Routine/Complete Inspection No Violations Noted
2449099 Primary Facility 2016-02-03 Routine/Complete Inspection No Violations Noted
2473928 Primary Facility 2016-04-08 Follow-up Inspection Pending Inspection to follow up on the 6/29/15 and 7/13/15 outstanding violations. These violations will be resolved upon receipt and review of the Remedial Action Completion Report. Site snow covered during inspection. A damp area was noted near some production equipment. Soil and standing water screened for conductivity. Conductivity readings were elevated. A sample was collected from the standing water. Additional violations may be cited pending the sample results. TLT
2481726 Primary Facility 2016-05-05 Routine/Complete Inspection No Violations Noted
2483765 Primary Facility 2016-05-10 Administrative/File Review Outstanding Violations - Viols Req'd Admin inspection to review the Site Inspection and Soil Sampling Report provided by JKLM. Report summarizes JKLM's investigation of an area that exhibited elevated soil/water conductivity, as found during DEP's 4/8/16 inspection. Based upon the results of DEP's sample collected on 4/8/16, a violation is cited against the 3HU well. The violation is immediately corrected as JKLM recovered the water as soon as being made aware. The 6/29/15 and 7/13/15 violations against the 3HU remain outstanding and will be resolved upon receipt and review of the Remedial Action Completion Reports. TLT
2488575 Primary Facility 2016-05-25 Administrative/File Review No Violations Noted The DEP has reviewed the 5/16/16 “Remedial Action Completion Report” for the JKLM – Sweden Valley Pad 102 site located in Summit Township, Potter Co. The plan was reviewed in accordance with the Alternative Remediation provision of the DEP policy document 800-5000-011 Addressing Spills and Releases at Oil and Gas Well Sites and Access Roads; no technical deficiencies were noted. Response Actions conducted under the Alternative Remediation provision do not qualify for the relief of environmental liability provided by the Land Recycling and Environmental Remediation Standards Act.
2493891 Primary Facility 2016-06-10 Compliance Evaluation No Violations Noted Compliance evaluation inspection to verify that the 6/29/15 and 7/13/15 outstanding violations could be resolved. Inspection also to follow up on remedial actions completed in response to 4/8/16 inspection. Alternative Remediation Report for phoshonic acid and brine releases was approved by the DEP Environmental Cleanup and Brownfields Program on 5/25/16. Summary report documenting cleanup and confirmation sampling for area adjacent to glycol unit (associated with the 4/8/16 inspection) reviewed on 6/10/16 with no deficiencies noted. Outstanding violations have been resolved. TLT
2509728 Primary Facility 2016-08-09 Routine/Complete Inspection No Violations Noted
2595701 Primary Facility 2017-05-15 Routine/Complete Inspection No Violations Noted
2676441 Primary Facility 2017-12-28 Routine/Complete Inspection No Violations Noted A routine inspection of the JKLM Sweden Valley 102 well pad was conducted on 12/28/2017 @1130 hours. Present were myself and Jason Logsdon, JKLM pipeline Supervisor. The weather was 8 degrees and partly sunny. This inspection was completed during a tour of JKLM's activity in the Sweden Valley area between 1100 hours and 1500 hours.

No violations are noted at this time.

2819850 Primary Facility 2019-04-02 Routine/Complete Inspection No Violations Noted The Department of Environmental Protection conducted a routine inspection of the JKLM Sweden Valley 102 well pad located in Summitt Twp, Potter Co on 4/2/2019 @1115 hours. The weather was 42 degrees, overcast, winds S 14mph, humidity 30%. Onsite activity consists of a work-over rig and contractor, Deep Well Services fishing out the 2 3/8" pipe in the process of cleaning out and redrilling the 3H well. Scott West, JKLM was present onsite for the inspection.

Multiple issues were observed during the inspection and reported to onsite personnel. These issues were being corrected when i departed the site.

No violations are noted at this time. I departed the site @1320 hours.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2377498 725183 06/09/2015 2015-06-09 78.55(a) - CONTROL AND DISPOSAL PLANNING - Operator failed to prepare and implement a plan under 25 Pa. Code Section 91.34 for the control and disposal of fluids, residual waste and drill cuttings, including tophole water, brines, drilling fluids, ad Administrative PPC plan not submitted to the Department prior to generation of waste
2377498 725185 06/09/2015 2015-06-09 78.55(f)5v - EMERGENCY RESPONSE FOR UNCONVENTIONAL WELL SITES - Failure of the unconventional well operator to submit a copy of the emergency response plan and subsequent updates to PEMA, the Department, county emergency agency and the Public Safety Administrative Operator has not submitted either a company-wide or site-specific ER Plan
2386000 727372 06/29/2015 2015-06-29 CSL 402(b) - POTENTIAL POLLUTION - Conducting an activity regulated by a permit issued pursuant to Section 402 of The Clean Streams Law to prevent the potential of pollution to waters of the Commonwealth without a permit or contrary to a permit issue Environmental Health & Safety CSL 402. An estimated 275 gallons of phosphonic acid was released when a tote of anti-corrosion agent was punctured. The acid was released into containment. The containment was breached due to a hole, which was discovered during the spill response. Steady rain on 6/27/15 mobilized the phosphonic ac
2386000 727373 06/29/2015 2015-06-29 OGA3218.2(A) - Failure to design and construct unconventional well site to prevent spills to the ground surface and off well site. Environmental Health & Safety An estimated 275 gallons of phosphonic acid was released when a tote of anti-corrosion agent was punctured. The acid was released into containment. The containment was breached due to a hole, which was discovered during the spill response. Steady rain on 6/27/15 mobilized the phosphonic acid causin
2392130 730453 07/13/2015 2015-07-13 CSL 402(b) - POTENTIAL POLLUTION - Conducting an activity regulated by a permit issued pursuant to Section 402 of The Clean Streams Law to prevent the potential of pollution to waters of the Commonwealth without a permit or contrary to a permit issue Environmental Health & Safety CSL 402 for the potential to pollute Waters of the Commonwealth. Purpose of the inspection was to document a 63 gal calcium chloride release reported 7/7/15, which had been cleaned up. While on site, evidence of a new release was observed along the east side of the pad. Observed multiple damp areas
2392130 730454 07/13/2015 2015-07-13 78.54 - GENERAL REQUIREMENTS - Operator failed to control and dispose of fluids, residual waste and drill cuttings, including tophole water, brines, drilling fluids, drilling muds, stimulation fluids, well servicing fluids, oil, and production fluids Environmental Health & Safety 78.54 for failure to control and dispose of fluids, residual waste and drill cuttings, including tophole water, brines, drilling fluids, drilling muds, stimluation fluids, well servicing fluids, oil, and production fluids in a manner that prevents pollution of the Waters of the Commonwealth. Purpos
2392130 730455 07/13/2015 2015-07-13 SWMA301 - Failure to properly store, transport, process or dispose of a residual waste. Environmental Health & Safety SWMA 301 for failure to properly store, transport, process or dispose of a residual waste. Purpose of the inspection was to document a 63 gal calcium chloride release reported 7/7/15, which had been cleaned up. While on site, evidence of a new release was observed along the east side of the pad. Obs
2392130 730456 07/13/2015 2015-07-13 OGA3218.2(A) - Failure to design and construct unconventional well site to prevent spills to the ground surface and off well site. Environmental Health & Safety OGA 3218.2(a). Failure to design and construct unconventional well site to prevent spills to the ground surface and off well site. The containment was not suffieciently impervious and able to contain the spilled material. Purpose of the inspection was to document a 63 gal calcium chloride release re
2483765 759168 2016-05-10 2016-05-10 CSL 402(b) Environmental Health & Safety 35 P.S. 691.402(b) for causing or allowing an unpermitted discharge with the potential to pollute Waters of the Commonwealth. An area was observed adjacent to a glycol unit that exhibited elevated soil conductivity. Ponded water was also screened for conductivity and a sample collected. Sample resul

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
725183 324924 NOV - Notice of Violation Comply/Closed 2015-07-02
725185 324924 NOV - Notice of Violation Comply/Closed 2015-07-02
727372 325308 NOV - Notice of Violation
727373 325308 NOV - Notice of Violation
730453 327703 NOV - Notice of Violation
730454 327703 NOV - Notice of Violation
730455 327703 NOV - Notice of Violation
730456 327703 NOV - Notice of Violation