If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 37-105-21855 | |
Country: United States | |
State: Pennsylvania | |
County: Potter | |
Municipality: Summit Township | |
Operator Name: JKLM ENERGY LLC | |
Well Pad ID: 153187 | |
Farm/Lease Name: SWEDEN VALLEY | |
License Status: Active | |
Spud Date: 2016-02-20 | |
Permit Date: 2015-12-21 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: Yes | |
Latitude: 41.713331 | |
Longitude: -77.912706 |
Date | Event |
---|---|
2015-12-21 | New Permit Application |
2016-02-19 | Performed Spud Operation |
2016-07-09 | Drilling Completion |
2016-07-21 | Perforation |
2016-08-12 | Perforation |
2016-08-13 | Perforation |
2016-08-14 | Perforation |
2016-08-15 | Perforation |
2016-08-16 | Perforation |
2016-08-17 | Perforation |
2016-08-18 | Perforation |
2016-08-19 | Perforation |
2016-08-20 | Perforation |
2019-07-22 | Deviated |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2016 | JKLM ENERGY LLC | 65,162.39 | 15 | 0.00 | 0 | 0.00 | 0 |
2017 | JKLM ENERGY LLC | 2,534,827.48 | 359 | 0.00 | 0 | 0.00 | 0 |
2018 | JKLM ENERGY LLC | 1,202,093.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2019 | JKLM ENERGY LLC | 817,435.00 | 333 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2016 | JKLM ENERGY LLC | Synthetic Liner Materials | 16.33 Tons | LANDFILL | 301358 |
2016 | JKLM ENERGY LLC | Produced Fluid | 11,300.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
2016 | JKLM ENERGY LLC | Drilling Fluid Waste | 1,930.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0254185 |
2016 | JKLM ENERGY LLC | Drilling Fluid Waste | 1,930.00 Bbl | CENT WASTE TRT FAC NPDES | PA0254185 |
2016 | JKLM ENERGY LLC | Waste Water Treatment Sludge | 38.67 Tons | LANDFILL | 301358 |
2016 | JKLM ENERGY LLC | Drill Cuttings | 1,399.73 Tons | LANDFILL | 301358 |
2016 | JKLM ENERGY LLC | Drilling Fluid Waste | 488.33 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2016 | JKLM ENERGY LLC | Produced Fluid | 843.67 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2016 | JKLM ENERGY LLC | Drilling Fluid Waste | 2,206.67 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NW009 |
2016 | JKLM ENERGY LLC | Other Oil & Gas Wastes | 206.67 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2017 | JKLM ENERGY LLC | Produced Fluid | 761.67 Bbl | INJECTION DISPOSAL WELL | 34-133-24189 |
2017 | JKLM ENERGY LLC | Other Oil & Gas Wastes | 2,104.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2017 | JKLM ENERGY LLC | Produced Fluid | 3,075.33 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC010 |
2017 | JKLM ENERGY LLC | Produced Fluid | 36.67 Bbl | INJECTION DISPOSAL WELL | 34-133-24096 |
2017 | JKLM ENERGY LLC | Produced Fluid | 22,604.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
2017 | JKLM ENERGY LLC | Other Oil & Gas Wastes | 1,133.00 Bbl | REUSE (AT WELL PAD) | |
2017 | JKLM ENERGY LLC | Basic Sediment | 36.67 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2017 | JKLM ENERGY LLC | Drilling Fluid Waste | 748.66 Bbl | REUSE (AT WELL PAD) | |
2017 | JKLM ENERGY LLC | Other Oil & Gas Wastes | 120.67 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
2017 | JKLM ENERGY LLC | Synthetic Liner Materials | 6.00 Tons | LANDFILL | 301358 |
2017 | JKLM ENERGY LLC | Produced Fluid | 6,783.34 Bbl | REUSE (AT WELL PAD) | |
2017 | JKLM ENERGY LLC | Produced Fluid | 192.67 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123 |
2017 | JKLM ENERGY LLC | Produced Fluid | 41.67 Bbl | INJECTION DISPOSAL WELL | 34-133-20114 |
2017 | JKLM ENERGY LLC | Produced Fluid | 10,243.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2017 | JKLM ENERGY LLC | Waste Water Treatment Sludge | 7.00 Tons | LANDFILL | 301358 |
2018 | JKLM ENERGY LLC | Produced Fluid | 547.92 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123 |
2018 | JKLM ENERGY LLC | Other Oil & Gas Wastes | 427.56 Bbl | REUSE (AT WELL PAD) | |
2018 | JKLM ENERGY LLC | Produced Fluid | 411.67 Bbl | INJECTION DISPOSAL WELL | 34-133-24096 |
2018 | JKLM ENERGY LLC | Produced Fluid | 2,192.99 Bbl | REUSE (AT WELL PAD) | |
2018 | JKLM ENERGY LLC | Produced Fluid | 2,805.33 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR119 |
2018 | JKLM ENERGY LLC | Produced Fluid | 409.00 Bbl | INJECTION DISPOSAL WELL | 34-133-20114 |
2018 | JKLM ENERGY LLC | Produced Fluid | 3,285.67 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
2018 | JKLM ENERGY LLC | Produced Fluid | 2,836.76 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC010 |
2018 | JKLM ENERGY LLC | Produced Fluid | 337.00 Bbl | INJECTION DISPOSAL WELL | 34-133-24189 |
2018 | JKLM ENERGY LLC | Other Oil & Gas Wastes | 66.75 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC010 |
2018 | JKLM ENERGY LLC | Produced Fluid | 764.99 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2018 | JKLM ENERGY LLC | Synthetic Liner Materials | 0.93 Tons | LANDFILL | 301358 |
2019 | JKLM ENERGY LLC | Produced Fluid | 863.34 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
2019 | JKLM ENERGY LLC | Produced Fluid | 1,403.34 Bbl | INJECTION DISPOSAL WELL | 34-133-24096 |
2019 | JKLM ENERGY LLC | Produced Fluid | 586.67 Bbl | INJECTION DISPOSAL WELL | 34-133-24189 |
2019 | JKLM ENERGY LLC | Produced Fluid | 210.00 Bbl | INJECTION DISPOSAL WELL | 34-155-24099 |
2019 | JKLM ENERGY LLC | Produced Fluid | 214.85 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123 |
2019 | JKLM ENERGY LLC | Produced Fluid | 548.78 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC010 |
2019 | JKLM ENERGY LLC | Produced Fluid | 1,039.99 Bbl | STORAGE PENDING DISPOSAL OR REUSE | WMGR123NC038 |
2019 | JKLM ENERGY LLC | Produced Fluid | 36.67 Bbl | INJECTION DISPOSAL WELL | 34-155-22403 |
2019 | JKLM ENERGY LLC | Produced Fluid | 611.67 Bbl | REUSE (AT WELL PAD) |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2438035 | Primary Facility | 2016-01-05 | Routine/Partial Inspection | No Violations Noted | Preconstruction meeting for the Sweden Valley 101 well pad. Logging operations to begin on 1/6/15. Site construction anticipated to begin after logging operations completed and will take approximately 3 weeks. TLT |
2452374 | Primary Facility | 2016-02-18 | Preoperation Inspection | No Violations Noted | Preoperational inspection. Spud notices for the 2HU - 5HU wells were received on 2/17/16 with an anticipated spud date of 2/19/16. Site has been constructed and stabilized. Perimeter E&S controls have been installed. TLT |
2467659 | Primary Facility | 2016-03-24 | Routine/Complete Inspection | No Violations Noted | |
2470279 | Primary Facility | 2016-03-29 | Routine/Complete Inspection | No Violations Noted | |
2472921 | Primary Facility | 2016-04-08 | Routine/Complete Inspection | No Violations Noted | |
2509744 | Primary Facility | 2016-08-11 | Routine/Complete Inspection | No Violations Noted | |
2511295 | Primary Facility | 2016-07-19 | Routine/Complete Inspection | No Violations Noted | |
2546838 | Primary Facility | 2016-12-16 | Routine/Complete Inspection | No Violations Noted | Routine inspection. The 2HU - 4HU wells have been drilled and stimulated. Production equipment has been installed at the site. The site was snow covered and frozen, therefore vegetative cover and E&S controls were not observed. TLT |
2551292 | Primary Facility | 2017-01-09 | Routine/Complete Inspection | No Violations Noted | |
2564749 | Primary Facility | 2017-02-24 | Routine/Complete Inspection | No Violations Noted | |
2606492 | Primary Facility | 2017-05-18 | Routine/Complete Inspection | No Violations Noted | |
2609675 | Primary Facility | 2017-06-22 | Routine/Partial Inspection | No Violations Noted | On 6/22/17 at 1345 hrs I conducted a routine inspection at the Sweden Valley 101 well site. It was overcast and 82 degrees F. Sean Bacha, Oil and Gas Consultant, was present at the site during the inspection.
The 2HU - 4HU wells were drilled in 2016 and are equipped for production. The 5HU well was spud, however, then plugged in December 2016. A new well permit application for the 6V well (105-21900) was received on 6/5/17. I observed the E&S controls, production equipment and other materials staged on site. Grass is becoming well established on the topsoil stockpile and around the sediment traps; however, vegetative cover on the well pad fill slopes remains sparse. The sediment traps were observed (Photo #1). ST-1 (southern trap) held a minimal amount of water and had a field measured specific conductance of 209 micro Siemens/cm. The filter fabric had come off the rock filter and should be restaked (Photo #2). ST-2 (northern trap) was approximately half full and had a specific conductance of 73 micro Sie |
2690882 | Primary Facility | 2018-01-25 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was in production. The wellhead assembly all fittings all flow lines and all vented annulus were tested for gas. Results of this testing was that no gas was detected on the wellhead assembly or fittings , flow lines , vented annulus or well area. |
2691190 | Primary Facility | 2018-02-05 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was in production. The wellhead assembly all fittings, flow lines and vented annulus were tested for gas. Results of this testing was that no gas was detected on any of these areas of this well. |
2706610 | Primary Facility | 2018-03-12 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was in production. The well annulus 13 3/8"x 9 5/8" and 9 5/8" x 5 1/2" were being vented. The wellhead assembly,fittings,flow lines and annulus vents were tested for combustable gas. Results of this testing was that the 13 3/8" x 9 5/8" had 0% LEL (lower explosion limit) and 0% Methane measured on it with the gas meter. The 9 5/8" x 5 1/2" annulus vent tested 100% LEL (lower explosion limit) and 25% Methane combustable gas. No other gas was detected on the wellhead assembly or the well area. |
2715624 | Primary Facility | 2018-04-06 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection the annulus vents, and cellar and well area were tested for combustable gas. Results of this testing was that no combustable gas was detected on the annulus vents, the cellar or the well area. Rob Bowens (production supervisor) was at this inspection. |
2767318 | Primary Facility | 2018-08-24 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was in production. No combustible gas was detected on the annulus vents,cellar or the well area at this inspection. No violations noted at this inspection. |
2768964 | Primary Facility | 2018-08-23 | Routine/Complete Inspection | No Violations Noted | The DEP conducted a routine inspection of the JKLM Sweden Valley 101 Well Pad ESG29-105-15-0003 on 8/23/2018 @1130 hours. The weather was 70 degrees sunny, 58% humidity and winds WNW 13 mph.
The 2HU-4HU wells were drilled in 2016 and are currently in production. The 5HU well was spud, then plugged in December 2016. The access road, well pad and associated controls were inspected. A compressor unit appears to have been installed on the SE corner of the well pad. Large puddles were observed on the pad surface from recent heavy rains. All puddles on teh pad surface measured <300mS/cm(Photo#3). The fluid in teh duck pond containment had a field measured conductivity of 300uS/cm. JKLM representatives were contact and a vac truck was dispatched to the site. The elevated conductivity fluid was removed. A violation of 25 Pa Code 78a.56(a) is cited as IMMEDIATELY CORRECTED against the 2HU well API#105-21855 due to the remediation of the elevated conductivity fluid by a vac truck during the inspection. I departe |
2804702 | Primary Facility | 2018-11-19 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was in production. There are two (2) annulus vents openly venting on this well. Annulus vent intermediate 2 x production (9 5/8" x 5 1/2") was venting 100% LEL (lower explosion limit) and 100% METHANE combustible gas. No other annulus vents were noted venting at this inspection. No violations noted at the time of this inspection. |
2822372 | Primary Facility | 2019-01-02 | Routine/Complete Inspection | No Violations Noted | The Department of Environmental Protection conducted a routine inspection of the JKLM Sweden Valley 101 Well Pad located in Summit Twp, Potter Co. on 1/2/2019 @1115 hours. The weather 32 degrees, cloudy, 78% humidity winds, S @5mph. The site appears to be set up for production.
Empty production tanks appear to be stored around the perimeter of the site. Puddles observed on the pad surface were field screened for conductivity and found to be within normal range. No violations are noted at this time. We departed the site at 1200 hours. |
2845844 | Primary Facility | 2019-02-27 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well as in production. A digital gauge was indicating a psi (pounds per square inch) of 1089. There are two annulus vents that are vented to surface and were tested for combustible gas with an Altair 5 x Multi Gas Meter. This gas meter was calibrated on 2-20-19. Results of this testing were 0% LEL ( lower explosion limit) and 0% Methane on the 13 3/8" x 9 5/8" vent and 100% LEL and 9% Methane on the 9 5/8" x 5 1/2" vent. No violations noted at this inspection. |
For data sources see[7]