Well Details

Well ID: 37-105-21915
Loading map...
Country: United States
State: Pennsylvania
County: Potter
Municipality: Summit Township
Operator Name: JKLM ENERGY LLC
Well Pad ID: 154899
Farm/Lease Name: SWEDEN VALLEY 104-1HU
License Status:
Spud Date:
Permit Date: 2018-05-02
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 41.725960
Longitude: -77.927880

For data sources see[1][2][3]

Well History

Date Event
2018-05-02 New Permit Application
2018-06-18 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 JKLM ENERGY LLC 773,621.00 69 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 88.00 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Drill Cuttings 709.53 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Synthetic Liner Materials 8.48 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Produced Fluid 182.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 JKLM ENERGY LLC Produced Fluid 436.55 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2019 JKLM ENERGY LLC Other Oil & Gas Wastes 129.76 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 JKLM ENERGY LLC Produced Fluid 20.55 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 JKLM ENERGY LLC Synthetic Liner Materials 8.36 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Drill Cuttings 656.13 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Waste Water Treatment Sludge 44.38 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Produced Fluid 422.46 Bbl STORAGE PENDING DISPOSAL OR REUSE WMGR123NC038
2019 JKLM ENERGY LLC Produced Fluid 533.00 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2740282 Primary Facility 2018-06-12 Preoperation Inspection No Violations Noted The DEP conducted a PREOP inspection of the JKLM Sweden valley 104 wells site located in Summit Township Potter County on June 12, 2018 at 1100 hrs. JKLM representative Jeff Long was present for the inspection. The weather was 68° sunny, 53% humidity, winds South at 13 mph.

No issues were observed. This inspection meets the requirements of 58 Pa. C.S. 3258 (a.1) regarding a "pre-operational inspection".

I departed the site at 1245 hours.

-ELN

2745524 Primary Facility 2018-06-20 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was conductor only. The well bore was drilled at a depth of 120', the 20" x 120' pipe was set and cemented on 6-18-18"
2750611 Primary Facility 2018-07-10 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was a conductor only. Well is a 20" diameter by 120' in depth set conductor. This conductor was drilled,set and cemented on 6-20-18.
2761820 Primary Facility 2018-08-08 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was a conductor only. The conductor is 20" in diameter at 120' depth. The rigging up(prepping for drilling) was on going at the time of this inspection. Chris Wiley( drilling consultant) was present at this inspection. I was informed that the wells will be Batch Drilled. Batch drilling is the drilling and setting of the surface casing for each well, then the 1st intermediate for each well then the 2nd intermediate for each well and then the production casing for each well. I was informed that the anticipated spud in of the first well (5HU) was Sunday or Monday. No violations were noted at this inspection.
2763384 Primary Facility 2018-08-14 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was conductor only. At the time of this inspection the Falcon 38 Super Single Rig and crew were finishing rigging up to start drilling. The plan is to set surface casing on all five(5) of the wells then go back to each one to set the 1st and 2nd intermediate after the surface casing on all the wells is set. No violations were noted a the time f this inspection.
2767526 Primary Facility 2018-08-27 Routine/Complete Inspection No Violations Noted At the time of this inspection the conductor and the surface casing have been set in the hole and the B.O.P. test was on going at this time with no test results because of equipment issues at the time of this inspection. No violations noted at this inspection.
2772548 Primary Facility 2018-09-10 Routine/Complete Inspection No Violations Noted At the time of this inspection the 1st intermediate had been set and the Falcon 38 rig and crew were drilling to the set point (depth) of the 2nd intermediate string. The other 4 wells on this location have been Batch drilled ( batch drilling is when the conductors and surface casings are set one after another in each well. No violations were noted at this inspection.
2797863 Primary Facility 2018-11-02 Routine/Complete Inspection No Violations Noted At the time of this inspection this well has the conductor (20"),the surface casing (13 3/8"), the first intermediate (10 3/4") and the second intermediate (7 5/8") advanced into the well bore. This setting of these different strings of pipe was started on 8-23-18 and completed on 9-13-18. Ron Burdick drilling supervisor for JKLM was at this inspection. No violations were noted at this inspection.
2811926 Primary Facility 2018-12-07 Routine/Complete Inspection No Violations Noted The Department of Environmental Protection (DEP) conducted a routine inspection of the JKLM Sweden Valley 104 well pad on 12/7/2018 @1115 hours. The weather was 23 degrees, overcast, 3-4" of snow was observed on the ground. Humidity 615 with winds WNW @12mph. Activity onsite consists of personnel removing the containment from the top hole rig activity, and placing it in onsite waste containers, in preparation for transition to the H&P flex rig.

No staining or melted spots were observed on the pad surface. No violations are noted at this time. I departed the site at 1225 hours.

2837972 Primary Facility 2019-02-05 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was top holed only. No determined date was set for drilling this well at the time of this inspection. No violations noted at this inspection.

For data sources see[7]