{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.743483,"lon":-79.357658,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Somerset | |
Municipality: Addison Township | |
Operator Name: LPR ENERGY LLC | |
Well Pad ID: 149069 | |
Farm/Lease Name: PMG ALLEN UNIT 3H | |
License Status: | |
Spud Date: 2012-11-05 | |
Permit Date: 2012-07-23 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 39.743483 | |
Longitude: -79.357658 |
Date | Event |
---|---|
2012-07-23 | New Permit Application |
2012-10-31 | Performed Spud Operation |
2013-10-11 | Drilling Completion |
2014-08-06 | Perforation |
2015-06-29 | DEVIATED |
For data sources see[4]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 2014-08-06 | 2014-08-11 | 8,890 | 6,980,660 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | 15% Acid | Schlumberger | Perf Cleanup | Hydrocloric Acid | 7647-01-0 | 15 | 0.00655249 | 0 |
L058 | Schlumberger | Iron Stabilizer | Sodium erythorbate | 6381-77-7 | 100 | 0.00032384 | 0 | |
EC6673W | Nalco | Iron Control | Ethylene Glycol | 107-21-1 | 30 | 0.00349811 | 0 | |
J134 | Schlumberger | Gel Breaker | Hemicellulase Enzyme | 9012-54-8 | 100 | 0.0015029 | 0 | |
EC6486A | Nalco | Scale Inhibitor | Ethylene Glycol | 107-21-1 | 30 | 0.00078117 | 0 | |
Proppant | Schlumberger | Proppant | Crystalline Silica | 14808-60-7 | 100 | 12.0573 | 0 | |
J580 | Schlumberger | Gelling Agent | Carboydrate polymer | Proprietary | 100 | 0.0324211 | 0 | |
A264 | Schlumberger | Iron Control | Prop-2-yn-1-ol | 107-19-7 | 10 | 0.00000849 | 0 | |
Aliphatic acids | Proprietary | 30 | 0.00002547 | 0 | ||||
Methanol | 67-56-1 | 40 | 0.00003395 | 0 | ||||
Aliphatic alcohols, ethoxylayed #1 | Proprietary | 30 | 0.00002547 | 0 | ||||
B466 | Schlumberger | Friction Reducer | Distillates (petroleum), hydrotreated light | 64742-47-8 | 30 | 0.000758 | 0 | |
Ammonium Acetate | 631-61-8 | 6 | 0.0001516 | 0 | ||||
Alcohol Ethoxylates | Proprietary | 5 | 0.00012633 | 0 | ||||
EC6116A | Nalco | Biocide | Dibromoacetonitrile | 3252-43-5 | 5 | 0.00012566 | 0 | |
2,2-Dibromo-3-nitrilopropionamide | 10222-01-2 | 30 | 0.00075395 | 0 | ||||
Polyethylene Glycol | 25322-68-3 | 60 | 0.0015079 | 0 | ||||
Base Fluid | Chevron | Carrier/Base Fluid | Water (Including Mix Water Supplied by Client) | 7732-18-5 | 100 | 87.8029 | 0 |
For data sources see[5]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2012 | CHEVRON APPALACHIA LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2013 | CHEVRON APPALACHIA LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2014 | CHEVRON APPALACHIA LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2015 | CHEVRON APPALACHIA LLC | 874,143.00 | 331 | 0.00 | 0 | 0.00 | 0 |
2016 | LPR ENERGY LLC | 425,232.14 | 365 | 0.00 | 0 | 0.00 | 0 |
2017 | LPR ENERGY LLC | 487,107.00 | 359 | 0.00 | 0 | 0.00 | 0 |
2018 | LPR ENERGY LLC | 460,891.00 | 361 | 0.00 | 0 | 0.00 | 0 |
2019 | LPR ENERGY LLC | 371,407.00 | 365 | 0.00 | 0 | 0.00 | 0 |
For data sources see[6]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2013 | CHEVRON APPALACHIA LLC | Drilling Fluid Waste | 88.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2013 | CHEVRON APPALACHIA LLC | Drill Cuttings | 472.78 Tons | LANDFILL | 100172 |
2013 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 95.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2013 | CHEVRON APPALACHIA LLC | Drill Cuttings | 492.74 Tons | LANDFILL | 100419 |
2013 | CHEVRON APPALACHIA LLC | Drilling Fluid Waste | 448.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123SW001 |
2014 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 2,727.67 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW001 |
2014 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 28.33 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | CHEVRON APPALACHIA LLC | Produced Fluid | 82.50 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | CHEVRON APPALACHIA LLC | Fracturing Fluid Waste | 58.23 Tons | LANDFILL | 76-00-08 |
2015 | CHEVRON APPALACHIA LLC | Produced Fluid | 30.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW001 |
2015 | CHEVRON APPALACHIA LLC | Fracturing Fluid Waste | 23.48 Tons | LANDFILL | 100592 |
2015 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 4,304.17 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW001 |
2015 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 13.33 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2015 | CHEVRON APPALACHIA LLC | Produced Fluid | 10,916.84 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2015 | CHEVRON APPALACHIA LLC | Fracturing Fluid Waste | 0.11 Tons | STORAGE PENDING DISPOSAL OR REUSE | MID0209062814 |
2016 | LPR ENERGY LLC | Produced Fluid | 1,418.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
2016 | LPR ENERGY LLC | Produced Fluid | 560.00 Bbl | STORAGE PENDING DISPOSAL OR REUSE | |
2016 | LPR ENERGY LLC | Produced Fluid | 90.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2016 | CHEVRON APPALACHIA LLC | Produced Fluid | 1,521.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2017 | LPR ENERGY LLC | Produced Fluid | 446.00 Bbl | INJECTION DISPOSAL WELL | PAS2D561BSOM |
2017 | LPR ENERGY LLC | Produced Fluid | 65.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW010 |
2017 | LPR ENERGY LLC | Produced Fluid | 441.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2018 | LPR ENERGY LLC | Produced Fluid | 227.00 Bbl | REUSE (AT WELL PAD) | |
2018 | LPR ENERGY LLC | Produced Fluid | 499.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW010 |
2018 | LPR ENERGY LLC | Produced Fluid | 924.00 Bbl | INJECTION DISPOSAL WELL | PAS2D561BSOM |
2018 | LPR ENERGY LLC | Produced Fluid | 170.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2019 | LPR ENERGY LLC | Produced Fluid | 1,753.00 Bbl | INJECTION DISPOSAL WELL | PAS2D561BSOM |
2019 | LPR ENERGY LLC | Produced Fluid | 157.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW010 |
For data sources see[7]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2120861 | Primary Facility | 2012-11-30 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Surface casing was set at 60feet from grade with 36 sacks of Type I (24” pipe). |
2121601 | Primary Facility | 2012-11-28 | Routine/Complete Inspection | No Violations Noted | Inspection result of spud notification. Multi-well pad. |
2123112 | Primary Facility | 2012-12-12 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Conductor was set in well and Chevron was drilling 2H well. |
2128462 | Primary Facility | 2012-12-17 | Routine/Complete Inspection | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Conductor was set in well and Chevron was drilling 2H well. |
2130317 | Primary Facility | 2013-01-14 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling 5H well. |
2143497 | Primary Facility | 2013-02-11 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling 4H well. |
2143511 | Primary Facility | 2013-02-22 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling 6H well. |
2144635 | Primary Facility | 2013-02-25 | Routine/Complete Inspection | No Violations Noted | Multi-well pad. Site ID sign, valid permit, E&S plan, ESCGPI, PPC plan all present.. Security on-site.At time of inspection, in process of skidding rig to resume drilling. 3H spudded, TD not yet reached. 1H had been drilled. 2H, 4H, 5H, 6H also all spudded, TDs not yet reached.Observed small staining on gravel on front edge of rig containment when standing at DSM trailer and noted large snow/gravel pile against brine tanks in back corner of pad which could lead to a potential pollution event by falling into ditches after thawing. Spoke to DSM Ken Silvis who agreed to place the affected gravel on containment and agreed to remove the snow pile.Noted erosion issue from previous inspection on 11/28/12 (ID 2121601) was addressed by utilizing an erosion blanket for stabilization and removing sediment from ditch.Rig and on-site tanks on containment. Tanks and containment appear structurally sound. Access road adequately rocked and no accelerated E&S issues were noted.Department recommends that Operator remove debris from rock-lined ditches. |
2151602 | Primary Facility | 2013-03-13 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Conductor (24 inch pipe) was set at 60 feet and cemented with 9 yds. Water Protection Casing (16”) was set at 413 feet and was cemented with 450 sacks of Class A with 20 bbl. return. Mine Protection Casing (11 ¾”) was set at 650 feet with a basket at 555 feet. The mine casing was cemented with 325 sacks of Class A with 10 bbl. Return. Intermediate protection casing (8 5/8”) was set at 1906 feet and was cemented with 502 sacks of Class A with 15 bbl. Return. Chevron, David Freed and DEP performed a site walk through to inspect the site. |
2169708 | Primary Facility | 2013-05-22 | Routine/Complete Inspection | No Violations Noted | |
2173637 | Primary Facility | 2013-06-10 | Routine/Complete Inspection | No Violations Noted | Routine inspection no issues noted. |
2228140 | Primary Facility | 2013-11-26 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was completing well 4H |
2228230 | Primary Facility | 2013-10-31 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Well 3H was completed to 14,724 ft TD and casing 14,705 ft . Casing was cemented to surface with 1220 sks Solucam as lead and 720 sks Va Cam cement as tail. |
2228631 | Primary Facility | 2013-10-09 | Drilling/Alteration | No Violations Noted | Drilling 3H MD at 14859 ft, KOP at 7645 ft, 1255 sks of lead and 545 sks of tail. |
2228685 | Primary Facility | 2013-10-09 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Well 3H was completed to 14,724 ft TD and casing 14,705 ft . |
2229849 | Primary Facility | 2013-09-26 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Gas well was not in production. Chevron was setting up to drill 4HA. |
2235861 | Primary Facility | 2014-01-13 | Routine/Complete Inspection | No Violations Noted | On 1/13/14 inspected this 6 well, well pad. The weather the day of the inspection was unusually warm and wet. |
2244506 | Primary Facility | 2014-02-10 | Routine/Complete Inspection | No Violations Noted | Met with Curtis Small and inspected the well pad. Chevron was setting up on the well pad to frack a number of wells. The frack tanks will block access to the the pipeline companies access to their pipeline controls. Chevron propsed adding an additional ramp tp allow the pipeline company access to their well controls. The access road will only be temporary. |
2250977 | Primary Facility | 2014-03-05 | Routine/Complete Inspection | No Violations Noted | |
2252443 | Primary Facility | 2014-03-10 | Routine/Complete Inspection | No Violations Noted | On 3/10/14 met with Alex Grant with Chevron and inspected the site. |
2298106 | Primary Facility | 2014-08-20 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was in process of fracking well 5H. Well 1H was temporary shut in. Wells 4HA, 3H and 6H have been completed. Well 2H will be completed the following week. |
2311280 | Primary Facility | 2014-10-08 | Routine/Complete Inspection | No Violations Noted | Work was underway to equip a well for production. A coil tubing rig was located onsite. Secondary containment was located on the well pad and there were 10 green and 4 red trailer tanks located onsite on top of the containment. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that above and on either side of the site there was a cultivated crop field with soybeans. |
2408933 | Primary Facility | 2015-09-18 | Routine/Complete Inspection | No Violations Noted | Unconventional multi-well pad. |
2486260 | Primary Facility | 2016-05-19 | Routine/Complete Inspection | No Violations Noted | no issues. system running |
2532218 | Primary Facility | 2016-10-05 | Routine/Complete Inspection | No Violations Noted | system running |
2549709 | Primary Facility | 2016-12-29 | Routine/Complete Inspection | No Violations Noted | Multi-well Marcellus pad.
Site ID sign, E&S plan, PPC plan and ERP on site. At time of inspection no E&S issues observed on access road. Well pad gated. Pad rocked. Well tag present and legible. Brine tank located in secondary containment appears structurally sound. Department observed discharge from tank secondary containment onto well pad. See Inspection Record #2549692. |
2594469 | Primary Facility | 2017-04-25 | Routine/Complete Inspection | No Violations Noted | system running. no issues |
2594583 | Primary Facility | 2017-05-16 | Routine/Complete Inspection | No Violations Noted | no issues. system running |
2626055 | Primary Facility | 2017-08-16 | Routine/Complete Inspection | No Violations Noted | system running. no issues. |
2656134 | Primary Facility | 2017-11-02 | Routine/Complete Inspection | No Violations Noted | System running no,issues |
2672032 | Primary Facility | 2017-12-18 | Routine/Complete Inspection | No Violations Noted | System running. No,issues |
2672069 | Primary Facility | 2017-12-18 | Routine/Complete Inspection | No Violations Noted | Well appears to be in production. Well tender Matt Gary on site during inspection. DEP OGI P Wyrwas on site during inspection. |
2685384 | Primary Facility | 2018-01-23 | Routine/Complete Inspection | No Violations Noted | System producing. Emergency contact present. Well tag present. |
2700766 | Primary Facility | 2018-03-05 | Routine/Complete Inspection | No Violations Noted | Well tag present and emergency contact information present. No issues at the site |
2700820 | Primary Facility | 2018-03-05 | Routine/Complete Inspection | No Violations Noted | Multi-well site. Well pad gated. Well appears to be in production. Three brine tanks on site. Water truck on site during inspection. |
2719554 | Primary Facility | 2018-04-18 | Routine/Complete Inspection | No Violations Noted | Well appears equipped for production. Three brine tanks on site. Barrell located near brine tank labeled spill kit. Container labeled methanol located in secondary containment. |
2766914 | Primary Facility | 2018-08-23 | Routine/Complete Inspection | No Violations Noted | Well appears equipped for production. Three brine tanks on site. Department contacted operator rep Matt Gary by phone regarding potential E and S issues on access road and well pad. Mr. Gary states the access road and well pad areas will be inspected and any E and S issues will be addressed. |