{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.743443,"lon":-79.357686,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Somerset | |
Municipality: Addison Township | |
Operator Name: LPR ENERGY LLC | |
Well Pad ID: 149069 | |
Farm/Lease Name: PMG ALLEN UNIT 4H | |
License Status: | |
Spud Date: 2012-11-07 | |
Permit Date: 2012-07-23 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 39.743443 | |
Longitude: -79.357686 |
Date | Event |
---|---|
2012-07-23 | New Permit Application |
2013-03-15 | Performed Spud Operation |
2013-11-09 | Drilling Completion |
2014-07-21 | Perforation |
2015-06-29 | DEVIATED |
For data sources see[4]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 2014-07-21 | 2014-07-24 | 8,840 | 4,799,200 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | EC6116A | Nalco | Biocide | Polyethylene Glycol | 25322-68-3 | 60 | 0.00154473 | 0 |
2,2-Dibromo-3-nitrilopropionamide | 10222-01-2 | 30 | 0.00077236 | 0 | ||||
Dibromoacetonitrile | 3252-43-5 | 5 | 0.00012873 | 0 | ||||
EC6486A | Nalco | Scale Inhibitor | Ethylene Glycol | 107-21-1 | 30 | 0.00078168 | 0 | |
7.5% Acid | Schlumberger | Perf Cleanup | Hydrocloric Acid | 7647-01-0 | 8 | 0.00420768 | 0 | |
Proppant | Schlumberger | Proppant | Crystalline Silica | 14808-60-7 | 100 | 11.7068 | 0 | |
Base Fluid | Chevron | Carrier/Base Fluid | Water (Including Mix Water Supplied by Client) | 7732-18-5 | 100 | 88.179 | 0 | |
L058 | Schlumberger | Iron Stabilizer | Sodium erythorbate | 6381-77-7 | 100 | 0.00032751 | 0 | |
A264 | Schlumberger | Iron Control | Aliphatic alcohols, ethoxylayed #1 | Proprietary | 30 | 0.00002517 | 0 | |
Methanol | 67-56-1 | 40 | 0.00003356 | 0 | ||||
Prop-2-yn-1-ol | 107-19-7 | 10 | 0.00000839 | 0 | ||||
Aliphatic acids | Proprietary | 30 | 0.00002517 | 0 | ||||
J580 | Schlumberger | Gelling Agent | Carboydrate polymer | Proprietary | 100 | 0.0315582 | 0 | |
EC6673W | Nalco | Iron Control | Ethylene Glycol | 107-21-1 | 30 | 0.00360148 | 0 | |
B466 | Schlumberger | Friction Reducer | Distillates (petroleum), hydrotreated light | 64742-47-8 | 30 | 0.0007526 | 0 | |
Alcohol Ethoxylates | Proprietary | 5 | 0.00012543 | 0 | ||||
Ammonium Acetate | 631-61-8 | 6 | 0.00015052 | 0 | ||||
J134 | Schlumberger | Gel Breaker | Hemicellulase Enzyme | 9012-54-8 | 100 | 0.00146299 | 0 |
For data sources see[5]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2012 | CHEVRON APPALACHIA LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2013 | CHEVRON APPALACHIA LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2014 | CHEVRON APPALACHIA LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2015 | CHEVRON APPALACHIA LLC | 237,190.00 | 343 | 0.00 | 0 | 0.00 | 0 |
2016 | LPR ENERGY LLC | 147,659.92 | 365 | 0.00 | 0 | 0.00 | 0 |
2017 | LPR ENERGY LLC | 101,186.00 | 354 | 0.00 | 0 | 0.00 | 0 |
2018 | LPR ENERGY LLC | 123,707.00 | 363 | 0.00 | 0 | 0.00 | 0 |
2019 | LPR ENERGY LLC | 140,874.00 | 352 | 0.00 | 0 | 0.00 | 0 |
For data sources see[6]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2013 | CHEVRON APPALACHIA LLC | Drilling Fluid Waste | 88.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2013 | CHEVRON APPALACHIA LLC | Drill Cuttings | 472.78 Tons | LANDFILL | 100172 |
2013 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 200.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2013 | CHEVRON APPALACHIA LLC | Drill Cuttings | 492.74 Tons | LANDFILL | 100419 |
2013 | CHEVRON APPALACHIA LLC | Drilling Fluid Waste | 1,575.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123SW001 |
2014 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 2,727.67 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW001 |
2014 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 28.33 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | CHEVRON APPALACHIA LLC | Produced Fluid | 82.50 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | CHEVRON APPALACHIA LLC | Fracturing Fluid Waste | 58.23 Tons | LANDFILL | 76-00-08 |
2015 | CHEVRON APPALACHIA LLC | Produced Fluid | 30.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW001 |
2015 | CHEVRON APPALACHIA LLC | Fracturing Fluid Waste | 23.48 Tons | LANDFILL | 100592 |
2015 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 4,304.17 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW001 |
2015 | CHEVRON APPALACHIA LLC | Fracing Fluid Waste | 13.33 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2015 | CHEVRON APPALACHIA LLC | Produced Fluid | 10,916.84 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2015 | CHEVRON APPALACHIA LLC | Fracturing Fluid Waste | 0.11 Tons | STORAGE PENDING DISPOSAL OR REUSE | MID0209062814 |
2016 | LPR ENERGY LLC | Produced Fluid | 1,278.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123SW005 |
2016 | LPR ENERGY LLC | Produced Fluid | 145.00 Bbl | STORAGE PENDING DISPOSAL OR REUSE | |
2016 | LPR ENERGY LLC | Produced Fluid | 135.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2016 | CHEVRON APPALACHIA LLC | Produced Fluid | 1,521.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2017 | LPR ENERGY LLC | Produced Fluid | 667.00 Bbl | INJECTION DISPOSAL WELL | PAS2D561BSOM |
2017 | LPR ENERGY LLC | Produced Fluid | 139.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW010 |
2017 | LPR ENERGY LLC | Produced Fluid | 672.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2018 | LPR ENERGY LLC | Produced Fluid | 166.00 Bbl | REUSE (AT WELL PAD) | |
2018 | LPR ENERGY LLC | Produced Fluid | 422.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW010 |
2018 | LPR ENERGY LLC | Produced Fluid | 795.00 Bbl | INJECTION DISPOSAL WELL | PAS2D561BSOM |
2018 | LPR ENERGY LLC | Produced Fluid | 194.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2019 | LPR ENERGY LLC | Produced Fluid | 979.00 Bbl | INJECTION DISPOSAL WELL | PAS2D561BSOM |
2019 | LPR ENERGY LLC | Produced Fluid | 60.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW010 |
For data sources see[7]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2120867 | Primary Facility | 2012-11-30 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Surface casing was set at 68feet from grade with 30 sacks of Type I (24 “ pipe). |
2121600 | Primary Facility | 2012-11-28 | Routine/Complete Inspection | No Violations Noted | Inspection result of spud notification. Multi-well pad. |
2128467 | Primary Facility | 2012-12-17 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling well 2H. |
2128637 | Primary Facility | 2013-01-08 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling well 5H. |
2143500 | Primary Facility | 2013-02-11 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Well 4H was drilled to 386 feet. Keane 2144 rig shanked a bit and decided to stop drilling hole. Chevron, Natasha Sackivichik (Drilling Engineer) called DEP and informed DEP of skidding rig to well 6H.. Chevron plugged well 4H will 910 sacks of Class A cement. |
2143513 | Primary Facility | 2013-02-22 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling well 6H. |
2144637 | Primary Facility | 2013-02-25 | Routine/Complete Inspection | No Violations Noted | Multi-well pad. Site ID sign, valid permit, E&S plan, ESCGPI, PPC plan all present.. Security on-site.At time of inspection, in process of skidding rig to resume drilling. 4H spudded, TD not yet reached. 1H had been drilled. 2H, 3H, 5H, 6H also all spudded, TDs not yet reached.Observed small staining on gravel on front edge of rig containment when standing at DSM trailer and noted large snow/gravel pile against brine tanks in back corner of pad which could lead to a potential pollution event by falling into ditches after thawing. Spoke to DSM Ken Silvis who agreed to place the affected gravel on containment and agreed to remove the snow pile.Noted erosion issue from previous inspection on 11/28/12 (ID 2121600) was addressed by utilizing an erosion blanket for stabilization and removing sediment from ditch.Rig and on-site tanks on containment. Tanks and containment appear structurally sound. Access road adequately rocked and no accelerated E&S issues were noted.Department recommends that Operator remove debris from rock-lined ditches. |
2151598 | Primary Facility | 2013-03-13 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling well 3H. |
2173642 | Primary Facility | 2013-06-10 | Routine/Complete Inspection | No Violations Noted | Routine inspection no issues noted. |
2181331 | Primary Facility | 2013-05-22 | Routine/Complete Inspection | No Violations Noted | Met on site with Chevron. Signed off on a minor modification to the restoration plan. |
2220943 | Primary Facility | 2013-11-12 | Administrative/File Review | In Compliance with Policy | REPORTED SPILL OF APPROXIMATELY 8 GALS OF OIL BASED DRILLING MUD. CHEVRON REP, BETH SMOCK, REPORTED THE REALSE AT 7:29AM ON 11/9/13. DEPARTMENT FOLLOWED UP WITH OPERATOR AND IT APPEARS THAT OPERATOR IS IMPLEMENTING AND FOLLOWING CURRENT SPILL POLICY AND NOTIFIED THE DEPT AND BEGAN CLEAN UP MEASURES IN A TIMELY MANNER. |
2228134 | Primary Facility | 2013-11-26 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Well 4H was drilled to 12,224 ft TD with 6459 ft KOP and 9227 ft LP. Production pipe was set and was cemented back to surface with 1730 sacks of Varicam (lead) 400 sks SoloCam (tail) with 32 bbl return. Haliburton performed the cementing of the production pipe. |
2228278 | Primary Facility | 2013-10-31 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling well 3H. |
2228715 | Primary Facility | 2013-10-09 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was drilling well 6H. |
2229858 | Primary Facility | 2013-09-26 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Gas well was not in production. Chevron was setting up to drill 4HA. |
2235871 | Primary Facility | 2014-01-13 | Routine/Complete Inspection | No Violations Noted | On 1/13/14 inspected this 6 well, well pad. The weather the day of the inspection was unusually warm and wet. |
2244509 | Primary Facility | 2014-02-10 | Routine/Complete Inspection | No Violations Noted | Met with Curtis Small and inspected the well pad. Chevron was setting up on the well pad to frack a number of wells. The frack tanks will block access to the the pipeline companies access to their pipeline controls. Chevron propsed adding an additional ramp tp allow the pipeline company access to their well controls. The access road will only be temporary. |
2250981 | Primary Facility | 2014-03-05 | Routine/Complete Inspection | No Violations Noted | On 3/5/14 met with Joe Brusco with Chevron and inspected the site. |
2252447 | Primary Facility | 2014-03-10 | Routine/Complete Inspection | No Violations Noted | On 3/10/14 met with Alex Grant with Chevron and inspected the site. |
2298113 | Primary Facility | 2014-08-20 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was in process of fracking well 5H. Well 1H was temporary shut in. Wells 4HA, 3H and 6H have been completed. Well 2H will be completed the following week. |
2298118 | Primary Facility | 2014-08-20 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Chevron was in process of fracking well 5H. Well 1H was temporary shut in. Wells 4HA, 3H and 6H have been completed. Well 2H will be completed the following week. |
2311283 | Primary Facility | 2014-10-08 | Routine/Complete Inspection | No Violations Noted | Work was underway to equip a well for production. A coil tubing rig was located onsite. Secondary containment was located on the well pad and there were 10 green and 4 red trailer tanks located onsite on top of the containment. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that above and on either side of the site there was a cultivated crop field with soybeans. |
2408931 | Primary Facility | 2015-09-18 | Routine/Complete Inspection | No Violations Noted | At time of inspection, well tag present and legible. |
2486267 | Primary Facility | 2016-05-19 | Routine/Complete Inspection | No Violations Noted | no issues. system running |
2532224 | Primary Facility | 2016-10-05 | Routine/Complete Inspection | No Violations Noted | system running |
2549692 | Primary Facility | 2016-12-29 | Routine/Complete Inspection | Violation(s) Noted | Multi-well Marcellus pad.
Site ID sign, E&S plan, ERP and PPC plan on site. At time of inspection no E&S issues observed on access road. Well pad gated. Pad rocked. Well appears to be in production. Well tag present and legible. Brine tank located in secondary containment. At this time approx 10 inches of liquid located in secondary containment. Department observed a hose discharging fluids from tank secondary containment onto well pad. This hose begins in bottom of secondary containment, goes over containment wall, and ends on rocked area of well pad. No oil/sheen was observed on fluid located in containment or on/around fluid released onto pad. No erosion gullies or ponding of water was observed near discharge point. Department recorded a pH of 8.7 and specific conductivity of 1595 microsemens/cm from water sample taken from containment area and a pH of 8.6 and specific conductivity of 1595 microsemens/cm from water sample taken from discharging hose. Department contacted Operator Rep Clayton Hill (Dall |
2562081 | Primary Facility | 2017-02-13 | Administrative/File Review | Outstanding Violations - Viols Req'd | Admin inspection to Inspection Record # 2549692 where violations were issued for failure to properly store, transport, process or dispose of a residual waste, for land applied top-hole water or precipitation water that does not meet requirements for pH, conductivity and sheen, and for failure to spread top-hole water or precipitation water from a pit over an undisturbed, vegetated area capable of absorbing the water.
Operator Rep Clayton Hill contacted Department by phone. Mr. Hill requested clarification on the violation issued for failure to properly store, transport, process or dispose of a residual waste. Department stated that the violation was issued because production fluid was moved from one site (the Allen) to another site (the Saylor). Mr. Hill stated they were bringing the Saylor Unit 2H well online and used the produced fluid to assist in setting pipe down hole. Mr. Hill offered to provide disposal manifests from the Saylor well. Department stated manifests could be sent electronically or by mai |
2568069 | Primary Facility | 2017-02-24 | Administrative/File Review | Outstanding Violations - Viols Req'd | Admin inspection to Inspection Record # 2549692 where violations were issued for failure to properly store, transport, process or dispose of a residual waste, for land applied top-hole water or precipitation water that does not meet requirements for pH, conductivity and sheen, and for failure to spread top-hole water or precipitation water from a pit over an undisturbed, vegetated area capable of absorbing the water.
Department received response to NOV from Operator. In response to the violation issued under 78a.60 DISHCHARGE REQUIREMENTS, Operator states that a new freshwater discharge plan has been implemented and new pH and conductivity meters purchased. In addition, Operator has increased employee training regarding 78a regulations. Department recommends Operator conduct field tests to ensure the soils where the top-hole release occurred are not contaminated. Department requests Operator provide Department with results when results are obtained. In response to the violation issued for failure to prop |
2586747 | Primary Facility | 2017-04-17 | Administrative/File Review | Outstanding Violations - Viols Req'd | Admin inspection to Inspection Record # 2549692 where violations were issued for failure to properly store, transport, process or dispose of a residual waste, for land applied top-hole water or precipitation water that does not meet requirements for pH, conductivity and sheen, and for failure to spread top-hole water or precipitation water from a pit over an undisturbed, vegetated area capable of absorbing the water.
As per previous inspection (inspection record #2568069), Department requested field tests be performed to ensure soil where top-hole release occurred are not contaminated. At the time of this inspection Department has not received those results. Department contacted Operator by phone and left message requesting sample results. Operator Rep. Clayton Hill responded and sent sample results via e-mail. Previously issued violation for land applied top-hole water that does not meet requirements for pH, conductivity, and sheen remains outstanding. Other violations issued under inspection record #2549 |
2588067 | Primary Facility | 2017-04-24 | Compliance Evaluation | No Violations Noted | Compliance Evaluation Inspection to Inspection Record # 2549692 where violations were issued for failure to properly store, transport, process or dispose of a residual waste, for land applied top-hole water or precipitation water that does not meet requirements for pH, conductivity and sheen, and for failure to spread top-hole water or precipitation water from a pit over an undisturbed, vegetated area capable of absorbing the water.
Department contacted Operator Rep Clayton Hill by phone with questions regarding sample results submitted by Operator. Mr. Hill returned call on 4-25-17. In response to the Department's questions, Mr. Hill stated that a background sample was not collected, a sample of the fluid released was not collected, and that coordinates of where the grab sample was collected were not recorded. He also stated that the grab sample was collected 6” deep at the location of the top-hole discharge; the sample was not a composite sample. Sample results provided by Operator do not include a test fo |
2594470 | Primary Facility | 2017-04-25 | Routine/Complete Inspection | No Violations Noted | system running. no issues |
2594584 | Primary Facility | 2017-05-16 | Routine/Complete Inspection | No Violations Noted | system running. no issues |
2619665 | Primary Facility | 2017-07-19 | Administrative/File Review | No Violations Noted | Admin inspection to a phone call received from Operator rep Bob Liddle. Mr. Liddle requested regulation clarification regarding a landowner constructing a field road off of a current access road.
According to Department records, the ESCGP for this site was terminated in 2015. Therefore, the Operator is only responsible for the access road, well pad, and any PCSM BMP’s. The Operator remains responsible for any E&S issues that develop on the access road and well pad, even if landowner activity results in those E&S issues. |
2626056 | Primary Facility | 2017-08-16 | Routine/Complete Inspection | No Violations Noted | system running. no issues |
2656139 | Primary Facility | 2017-11-02 | Routine/Complete Inspection | No Violations Noted | System running nomissues |
2672035 | Primary Facility | 2017-12-18 | Routine/Complete Inspection | No Violations Noted | System producing. No,issues |
2672070 | Primary Facility | 2017-12-18 | Routine/Complete Inspection | No Violations Noted | Well appears to be in production. Well tender Matt Gary on site during inspection. DEP OGI P Wyrwas on site during inspection. |
2685386 | Primary Facility | 2018-01-23 | Routine/Complete Inspection | No Violations Noted | System producing. Emergency contact present. Well tag present. |
2700769 | Primary Facility | 2018-03-05 | Routine/Complete Inspection | No Violations Noted | Well tag present and emergency contact information present. No issues at the site |
2700821 | Primary Facility | 2018-03-05 | Routine/Complete Inspection | No Violations Noted | Multi-well site. Well pad gated. Well appears to be in production. Three brine tanks on site. Water truck on site during inspection. |
2719556 | Primary Facility | 2018-04-18 | Routine/Complete Inspection | No Violations Noted | Well appears equipped for production. Three brine tanks on site. Barrell located near brine tank labeled spill kit. Container labeled methanol located in secondary containment. |
2766917 | Primary Facility | 2018-08-23 | Routine/Complete Inspection | No Violations Noted | Well appears equipped for production. Three brine tanks on site. Department contacted operator rep Matt Gary by phone regarding potential E and S issues on access road and well pad. Mr. Gary states the access road and well pad areas will be inspected and any E and S issues will be addressed. |
Inspection ID | Violation ID | Violation Date | Date Resolved | Violation Code | Violation Type | Violation Comments |
---|---|---|---|---|---|---|
2549692 | 778114 | 2016-12-29 | 2017-02-24 | SWMA 301 | Environmental Health & Safety | |
2549692 | 778115 | 2016-12-29 | 2017-04-24 | 78a60(b)2 | Environmental Health & Safety | |
2549692 | 778116 | 2016-12-29 | 2017-02-24 | 78a60(b)5 | Environmental Health & Safety | |
2562081 | 778537 | 2017-02-13 | 2017-02-24 | SWMA 301 | Environmental Health & Safety | |
2562081 | 778538 | 2017-02-13 | 2017-04-24 | 78a60(b)2 | Environmental Health & Safety | |
2562081 | 778539 | 2017-02-13 | 2017-04-24 | 78a60(b)5 | Environmental Health & Safety | |
2568069 | 780327 | 2017-02-24 | 2017-04-24 | 78a60(b)2 | Environmental Health & Safety | |
2568069 | 780328 | 2017-02-24 | 2017-04-24 | 78a60(b)2 | Environmental Health & Safety | |
2586747 | 784140 | 2017-04-17 | 2017-04-24 | 78a60(b)2 | Environmental Health & Safety |
Violation ID | Penalty ID | Penalty Code | Penalty Status | Penalty Date | Enforcement Date | Penalty Amount | Amount Collected |
---|---|---|---|---|---|---|---|
778114 | 350907 | NOV - Notice of Violation | 2017-05-25 | ||||
778115 | 350907 | NOV - Notice of Violation | 2017-05-25 | ||||
778116 | 350907 | NOV - Notice of Violation | 2017-05-25 | ||||
784140 | 350907 | NOV - Notice of Violation | 2017-05-25 |