37-115-20470

Well Details

Well ID: 37-115-20470
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Forest Lake Township
Operator Name: BKV OPR LLC
Well Pad ID: 145322
Farm/Lease Name: BAKER 2H
License Status:
Spud Date:
Permit Date: 2010-11-15
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.884119
Longitude: -75.992461

For data sources see[1][2][3]

Well History

Date Event
2010-11-15 New Permit Application
2011-01-28 Performed Spud Operation
2011-04-20 Drilling Completion
2012-04-30 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2012-01-27 2012-01-27 6,225 4,917,822

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Sand, White, 40/70 Baker Hughes Proppant Quartz 14808-60-7 100.00 6.96
Water Operator Carrier Water 7732-18-5 100.00 84.77
Sand, White, 30/50 Baker Hughes Proppant Quartz 14808-60-7 100.00 6.23
Hydrochloric Acid 10.1-15 Baker Hughes Acidizing Hydrochloric acid 7647-01-0 15.00 0.02
Water 7732-18-5 85.00 0.13
Additional Ingredients Baker Hughes Surfactant Ethoxylated Alcohol
Potassium chloride 7447-40-7
Water 7732-18-5
Polyacrylate
Sorbitan Monooleate
Sodium chloride 7647-14-5
Poly (acrylamide-co-acrylic acid)
FRW-18 Baker Hughes Friction Reducer Distillates, petroleum, hydrotreated light 64742-47-8 30.00 0.03
Alpha 1427 Baker Hughes Biocide Quaternary ammonium compounds,
benzyl-C12-16-alkyldimethyl, chlorides
68424-85-1 5.00 0.00111000
Glutaraldehyde 111-30-8 30.00 0.00663000
Ethanol 64-17-5 5.00 0.00111000
Didecyl dimethyl ammonium chloride 7173-51-5 10.00 0.00221000
Sand, White, 100 mesh Baker Hughes Proppant Quartz 14808-60-7 100.00 1.61
InFlo 250W Baker Hughes Surfactant Surfactants 80.00 0.00039000
2-Butoxyethanol 111-76-2 5.00 0.00002000
Methanol 67-56-1 30.00 0.00014000
Additional Ingredients Surfactant Salt
Ferrotrol 300L Baker Hughes Iron Control Citric acid 77-92-9 60.00 0.00109000
Hydrochloric Acid 5.1-7.5 Baker Hughes Acidizing Water 7732-18-5 92.50 0.18
Hydrochloric acid 7647-01-0 7.50 0.01
Scaletrol 720 Baker Hughes Scale Inhibitor Ethylene glycol 107-21-1 30.00 0.00455000
Calcium chloride 10043-52-4 5.00 0.00076000

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 CARRIZO (MARCELLUS) LLC 0.00 0 0.00 0 0.00 0
2011 CARRIZO (MARCELLUS) LLC 0.00 0 0.00 0 0.00 0
2012 CARRIZO (MARCELLUS) LLC 1,180,785.00 247 0.00 0 0.00 0
2013 CARRIZO (MARCELLUS) LLC 742,924.00 275 0.00 0 0.00 0
2014 CARRIZO (MARCELLUS) LLC 22,465.88 21 0.00 0 0.00 0
2015 CARRIZO (MARCELLUS) LLC 11,594.49 11 0.00 0 0.00 0
2016 CARRIZO (MARCELLUS) LLC 170,695.81 68 0.00 0 0.00 0
2017 CARRIZO (MARCELLUS) LLC 493,313.62 328 0.00 0 0.00 0
2018 BKV OPR LLC 278,516.93 364 0.00 0 0.00 0
2019 BKV OPR LLC 197,443.18 363 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 CARRIZO (MARCELLUS) LLC Drill Cuttings 1,692.00 Tons LANDFILL NY STATE #32S11
2011 CARRIZO (MARCELLUS) LLC Drill Cuttings 396.00 Tons LANDFILL THR029
2012 CARRIZO (MARCELLUS) LLC Drill Cuttings 198.00 Tons LANDFILL NY STATE #32S11
2012 CARRIZO (MARCELLUS) LLC Drill Cuttings 90.00 Tons LANDFILL THR029
2012 CARRIZO (MARCELLUS) LLC Produced Fluid 31,851.00 Bbl REUSE OTHER THAN ROAD SPREADING
2013 CARRIZO (MARCELLUS) LLC Produced Fluid 215.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE003
2013 CARRIZO (MARCELLUS) LLC Produced Fluid 990.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 CARRIZO (MARCELLUS) LLC Produced Fluid 147.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR119
2014 CARRIZO (MARCELLUS) LLC Produced Fluid 735.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2014 CARRIZO (MARCELLUS) LLC Produced Fluid 805.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2015 CARRIZO (MARCELLUS) LLC Produced Fluid 15.69 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE003
2015 CARRIZO (MARCELLUS) LLC Produced Fluid 4.03 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2015 CARRIZO (MARCELLUS) LLC Produced Fluid 41.20 Bbl REUSE OTHER THAN ROAD SPREADING
2015 CARRIZO (MARCELLUS) LLC Produced Fluid 13.15 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2016 CARRIZO (MARCELLUS) LLC Other Oil & Gas Wastes 15.18 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 CARRIZO (MARCELLUS) LLC Produced Fluid 39.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE003
2016 CARRIZO (MARCELLUS) LLC Produced Fluid 4.81 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE003
2016 CARRIZO (MARCELLUS) LLC Produced Fluid 155.84 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NC010
2016 CARRIZO (MARCELLUS) LLC Produced Fluid 120.45 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2016 CARRIZO (MARCELLUS) LLC Produced Fluid 1.28 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2017 CARRIZO (MARCELLUS) LLC Produced Fluid 553.25 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2017 CARRIZO (MARCELLUS) LLC Produced Fluid 128.19 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2017 CARRIZO (MARCELLUS) LLC Produced Fluid 77.93 Bbl REUSE (AT WELL PAD)
2017 CARRIZO (MARCELLUS) LLC Produced Fluid 247.22 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE003
2017 CARRIZO (MARCELLUS) LLC Produced Fluid 25.02 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 BKV OPR LLC Produced Fluid 15.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE003
2018 CARRIZO (MARCELLUS) LLC Produced Fluid 82.15 Bbl REUSE (AT WELL PAD)
2018 CARRIZO (MARCELLUS) LLC Produced Fluid 248.17 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2019 BKV OPR LLC Produced Fluid 15.00 Bbl REUSE (AT WELL PAD)
2019 BKV OPR LLC Produced Fluid 75.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE003
2019 BKV OPR LLC Produced Fluid 15.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2019 BKV OPR LLC Produced Fluid 271.43 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1965935 Primary Facility 2011-04-15 Drilling/Alteration No Violations Noted John Savage - Company Man. Nabors rig MO5. At TD=12,200'. Will be running 5 1/2 production string and cementing in approx. 24 hrs. Discussed with company man to improve conditions on work area - observed residual mud on plastic and should be kept cleaner. Observed some bubbling in cellars of two other wells on pad. Operator will check out status of these wells and report back to DEP.
1985317 Primary Facility 2011-06-27 Routine/Complete Inspection Pending Bubbling observed in cellar of well along outside of 9 5/8". Operator to clean out cellar so further investigation can be completed to be determine source of bubbling.
2007321 Primary Facility 2011-09-29 Routine/Complete Inspection No Violations Noted
2014413 Primary Facility 2011-10-25 Routine/Complete Inspection Pending DEP arrived on site at 11:00 am. The purpose of the inspection was to check the status of the wells and note any activity on site. At the time of inspection, crews were on site installing new plastic secondary containment for upcoming frac. Six wells have been drilled (1H - 6H). All six wells are currently shut in and not vented. Inspection of Baker 2H cellar revealed steady bubbling alongside the 9 5/8" casing. Bubbling was also present @ 6" away from the 9 5/8" casing. Due to the level of fluid in the cellar, the source could not be determined. It is requested by the DEP that the source be indentified. The Operator is to notify the DEP when this work is to be completed. The Operator shall provide a summary of the findings, and a description of what repairs need to be completed. According to Chapter 78 Section 78.86. Defective casing or cementing....the Operator has the option to corect the defect or submit a plan to correct the defect for approval by the DEP within 30 days.
2037796 Primary Facility 2012-01-26 Drilling/Alteration No Violations Noted Pre-frac insepction. Met with Co. Man Bill Weeks and Steve Osborne. BJ is frac contractor. Plastic and mating is down. inspected pump trucks. Catch pans under pistons should be cleaned out. A couple of pump trucks have excess grea/oil on them should be cleaned and disposed of. some spots of purple fluid on containment should be cleaned up. Any spilled petroleum products need to be cleaned up off of containment. Fraccing 2,4, and 6.
2053178 Primary Facility 2012-03-13 Routine/Complete Inspection No Violations Noted Please refer to Baker 1H 3-13-12 inspection report regarding details of the investigation. Permit number is 115-20471.
2077194 Primary Facility 2012-06-18 Routine/Complete Inspection Violation(s) Noted See inspection report for full details.
2357018 Primary Facility 2015-04-01 Routine/Complete Inspection Pending Cellar has little water with slight bubbles, unable to determine if gas, about 1700 lbs on production casing, vent pipe open and venting to tank, will request a vac truck be present while we are there to determine if gas is present.
2414134 Primary Facility 2015-10-08 Follow-up Inspection No Violations Noted At time of inspection, arrived on site at 11:30 a.m., the wells were shut in with a crew working on the production lines, the cellar had water at the bottom with no bubbling detected, the (9x5) vent pipe was open and venting to a tank, there was 1535psi on the production casing and 16psi on the production line. I took a walk around the site and everything looked OK.
2451823 Primary Facility 2016-01-21 Routine/Complete Inspection No Violations Noted The Department was on site to inspect the Baker well pad (ESX10-115-0029). The wells associated with the pad are as follows:

115-20471 115-20470 115-20469 115-20468 115-20467 115-20466 115-20465

The site was stable and well vegetated with no apparent erosional issues. There were no violations.

If there are any issues please feel free to contact me

2509562 Primary Facility 2016-07-28 Routine/Complete Inspection No Violations Noted The Department was on site to inspect the Baker well pad (ESX10-115-0029). The wells associated with the pad are as follows:

115-20471 115-20470 115-20469 115-20468 115-20467 115-20466 115-20465

The site was stable and well vegetated with no apparent erosional issues. There were no violations.

If there are any issues please feel free to contact me.

2511740 Primary Facility 2016-08-17 Site Restoration No Violations Noted The Department was on site to conduct a Notice of Termination on the Baker well pad (ESX10-115-0029 (1)). The wells associated with the pad are as follows:

115-20471 115-20470 115-20469 115-20468 115-20467 115-20466 115-20465

The site was rocky, but where there was enough soil for growth, vegetation was meeting or exceeding the 70% vegetative standard.  There were a few remaining BMPs (silt sock) and these were promptly removed by Carrizo employees.  Off the access road to the Impoundment and Well Site the landowner constructed an earthwork gun range, well vegetated and stable.  This is causing no impact to the site or access road.  
The area was stable and had no erosional issues at this time and it is recommended that this Notice of Termination be APPROVED. 

There were no violations.

If there are any issues please feel free to contact me.

2512477 Primary Facility 2016-08-22 Routine/Complete Inspection No Violations Noted At time of inspection, arrived on site at 13:00p.m., the cellar had water at the bottom with no bubbling noticed; the (9x5) vent pipe was open and venting into a tank. There was 496psi on the production casing and 936psi on the production line. I took a walk around the location and everything looked OK.

I left the site at 13:40p.m.

2606521 Primary Facility 2017-06-21 Routine/Complete Inspection No Violations Noted At time of inspection, arrived on site at 10:35a.m.

The cellar was about a quarter full of water with no bubbling noticed. The (9x5) annulus vent pipe was open and venting into the production tank. There was 502psi on the production casing and 458psi on the production line. I took a walk around the location and there were no obvious concerns noticed. I left the site at 11:20a.m.

2713022 Primary Facility 2018-03-28 Routine/Complete Inspection No Violations Noted At time of inspection.

The well was in production. There was water 3.5' below grade in the cellar with no bubbling noticed and no gas detected in the remainder of the cellar. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2817025 Primary Facility 2018-12-18 Routine/Complete Inspection No Violations Noted At time of inspection.

The well was in production. There was water 4' below grade in the cellar with no bubbling noticed and there was no gas detected in the remainder of the cellar with a MSA Altair 5X multi gas detector that was calibrated on 12/3/18. The permit number for the 4H on the entrance sign was incorrect (see photo #2). It was 155-20468 and should be 115-20468. I contacted Jesse Bonnice of BKV to have it corrected. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2851749 Primary Facility 2019-03-11 Routine/Complete Inspection No Violations Noted I performed a Routine Complete (RTNC) inspection of the Baker Well Pad on March 11, 2019. The weather was sunny and relatively warm, around 38 degrees.

The access road was a bit muddy but not unstable. The access road is quite long, passing some small logging operations, as well as a target shooting range situated along its length.

The well pad surface was plowed and mostly wet but stable. The wellheads were encased in a carport structure. They were surrounded by clean gravel and were properly labeled.

The containment surrounding the production tanks and apparatus was mostly empty and had sufficient freeboard.

The cut and fill slopes of the site were rocky and stable. Where there was sufficient soil, there was adequate vegetation. No areas of instability were noted.

The impoundment on site was full to capacity. It would be recommended to draw down the impoundment to prevent overflow and possible resulting E&S issues.

There were no violations noted

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2077194 642166 06/18/2012 2012-06-18 402CSL - Failure to adopt pollution prevention measures required or prescribed by DEP by handling materials that create a danger of pollution. Environmental Health & Safety
2077194 642167 06/18/2012 2012-06-18 102.11 - Failure to design, implement or maintain BMPs to minimize the potential for accelerated erosion and sedimentation. Administrative

For data sources see[8]

References