Well ID: 37-115-21225 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.798258,"lon":-75.704964,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Susquehanna | |
Municipality: Harford Township | |
Operator Name: CABOT OIL & GAS CORP | |
Well Pad ID: | |
Farm/Lease Name: PRITCHARD D 3 | |
License Status: | |
Spud Date: | |
Permit Date: 2013-04-09 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 41.798258 | |
Longitude: -75.704964 |
Date | Event |
---|---|
2013-04-09 | New Permit Application |
For data sources see[4]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2179926 | Primary Facility | 2013-07-02 | Drilling/Alteration | No Violations Noted | Spudder rig on location |
2180035 | Primary Facility | 2013-06-25 | Routine/Complete Inspection | No Violations Noted | The Department was on site at the D Pritchard Well Site to conduct a Preoperational Inspection. Well permits that have been issued for this pad are the 1H (115-21223), 2H (115-21224), and the 3H (115-21225). Inspection conducted with Eric Griffin of Don Bower Construction and Dillon Otten field tech for Tioga Environmental Consulting. All perimeter BMP’s in place. Red lined diversion berm reconfiguration located on the northeast side of the pad is acceptable. Pad is approximately 80% complete. |
2231988 | Primary Facility | 2013-12-11 | Routine/Complete Inspection | No Violations Noted | Inspection conducted on 12/11/13. Inspection conducted in response to a complaint that pad design and installation is causing increased storm water flow to agricultural field. Ground is frozen and snow covered. Pad placement does not appear as if would increase storm water flow to field in question. |
2262831 | Primary Facility | 2014-04-16 | Routine/Complete Inspection | No Violations Noted | refer to inspection record 2262826 |
2510523 | Primary Facility | 2016-08-11 | Routine/Partial Inspection | No Violations Noted | |
2533889 | Primary Facility | 2016-11-01 | Routine/Complete Inspection | No Violations Noted | On 11/1/16, the Department conducted an inspection of the COG Pritchard D Well Site located in Harford Township, Susquehanna County in response to a nearby malodor complaint. The Department arrived on-site at approximately 12:00 AM. There are 2 wells drilled and in production on this pad, the 1H and 2H. The pad is equipped with the standard equipment associated with steady state production. A water truck was collecting produced fluid from the production tanks during the inspection. No other activity is occurring at this pad. I spent approximately 5 minutes at each corner of the well pad and did not detect any malodors. No E&S issues were observed during this inspection. No violations noted. |