Well Details

Well ID: 37-115-22215
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Jackson Township
Operator Name: SWN PROD CO LLC
Well Pad ID: 146202
Farm/Lease Name: BOMAN 3H
License Status: UNDEFINED
Spud Date:
Permit Date: 2016-09-23
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.853719
Longitude: -75.5962

For data sources see[1][2][3]

Well History

Date Event
2016-09-23 New Permit Application
2017-05-14 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-11-23 2017-11-27 6,670 8,278,430 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 SI-1200 U.S. Well Services, LLC Scale Inhibitor Ethylene Glycol 107-21-1 40 0.00692 5681.64
Ammonia 7664-41-7 0.5 0.00009000 75.987
CPS 500 U.S. Well Services, LLC Fluid Loss Additive Ceramic Microspheres 66402-68-4 65 2.6076 2,142,380.0
Glutaraldehyde 111-30-8 1 0.02798 22985
Sand U.S. Well Services, LLC Proppant Crystalline Silica, quartz 14808-60-7 100 12.753 10,477,800.0
AI-303 U.S. Well Services, LLC Acid Corrosion Inhibitors Cinnamaldehyde 104-55-2 20 0.00006000 48.2919
Ethylene glycol 107-21-1 40 0.00016 133.573
Acetophenone,thiourea,formaldehyde polymer 68527-49-1 5 0.00001000 11.676
Formic acid 64-18-6 20 0.00006000 46.704
Butyl cellosolve 111-76-2 20 0.00005000 42.0803
Polyether 60828-78-6 10 0.00003000 23.352
K-BAC 1005 U.S. Well Services, LLC Anti-Bacterial Agent Water 7732-18-5 44.3 0.00568 4666.31
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 5.76 0.00181 1487.08
Polyethylene Glycol 25322-68-3 50 0.00718 5898.72
HCL Acid (12.6%-17.5%) U.S. Well Services, LLC Bulk Acid Water 7732-18-5 87.4 0.382 313849
Hydrogen Chloride 7647-01-0 17.5 0.08881 72969.2
WFRA-2000 U.S. Well Services, LLC Friction Reducer 2-Propenoic acid, polymer with 2 propenamide 9003-06-9 30 0.022 18071.9
Hydrated light distillate (petroleum) 64742-47-8 30 0.01804 14819
Water 7732-18-5 60 0.04399 36143.9
Water Southwestern Energy Carrier/Base Fluid Water 7732-18-5 100 84.0345 69,042,100.0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 SWN PROD CO LLC 0.00 0 0.00 0 0.00 0
2018 SWN PROD CO LLC 2,589,674.00 364 0.00 0 0.00 0
2019 SWN PROD CO LLC 1,020,866.00 358 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 SWN PROD CO LLC Other Oil & Gas Wastes 16.00 Bbl REUSE (AT WELL PAD)
2017 SWN PROD CO LLC Synthetic Liner Materials 8.05 Tons LANDFILL 101247
2017 SWN PROD CO LLC Produced Fluid 370.83 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2017 SWN PROD CO LLC Unused Fracturing Fluid Waste 2.57 Tons LANDFILL 301358
2017 SWN PROD CO LLC Unused Fracturing Fluid Waste 32.00 Tons RESIDUAL WASTE PROCESSING FACILITY WMGR123
2017 SWN PROD CO LLC Other Oil & Gas Wastes 490.17 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2017 SWN PROD CO LLC Drill Cuttings 1,147.19 Tons LANDFILL 101247
2018 SWN PROD CO LLC Produced Fluid 5,204.66 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2018 SWN PROD CO LLC Other Oil & Gas Wastes 18.33 Bbl SURFACE IMPOUNDMENT 826342
2018 SWN PROD CO LLC Produced Fluid 77.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 SWN PROD CO LLC Produced Fluid 11.14 Tons LANDFILL 301358
2018 SWN PROD CO LLC Produced Fluid 151.33 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Other Oil & Gas Wastes 162.56 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2018 SWN PROD CO LLC Other Oil & Gas Wastes 18.33 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Filter Socks 0.04 Tons RESIDUAL WASTE PROCESSING FACILITY 301280
2018 SWN PROD CO LLC Produced Fluid 539.50 Bbl SURFACE IMPOUNDMENT 826342
2019 SWN PROD CO LLC Other Oil & Gas Wastes 57.54 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Produced Fluid 401.33 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Produced Fluid 107.49 Bbl SURFACE IMPOUNDMENT 826342
2019 SWN PROD CO LLC Produced Fluid 18.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC035

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2593815 Primary Facility 2017-05-15 Drilling/Alteration No Violations Noted At time of inspection, arrived on site at 8:45a.m. for a new spud inspection.

Minichi Contracting Group was on site and putting in the cellars. Minichi Contracting Group drilled the holes and ran the conductor pipe with a dual rotary rig on the 2H, 3H, 4H, 5H, and 6H wells. I spoke with driller Keith Bowman of Minichi, all the conductors were drilled and set at 88'. The drill cuttings were put into a sealed role off container and hauled to the Keystone Landfill. I took a walk around the location and there were no obvious concerns noticed. I left the site at 9:05a.m.

2605595 Primary Facility 2017-06-19 Drilling/Alteration No Violations Noted At time of inspection, arrived on site at 9:10a.m.

I met with company man Tony Anthony. Falcon Rig 25 was on site and pulling drill pipe. They will pull up 2000' and start loading the hole with OBM. I took a walk around the location and there were no obvious concerns noticed. Depth at time of inspection was 5650'. The projected TD for the top hole section of the well is 5650'. I left the site at 10:20a.m.

2639066 Primary Facility 2017-08-15 Routine/Complete Inspection No Violations Noted
2659189 Primary Facility 2017-11-02 Routine/Complete Inspection No Violations Noted I arrived at the site at 11:22. I met with Mike Deming, Senior Regulatory Analyst and Frank Kelly Containment Coordinator both of SWNPC and Chris Anderson of Well Water Solutions. Mr. Anderson and Mr. Deming informed me the following. "Construction of the tank started yesterday. The inner tank is completed. The are (2) liners on the inner tank and (1) on the outer. Geotextile felt, (8) ounces, is on the seam of the tank walls. Geotextile felt is also on the pad surface at the bottom of the tanks, with (3) liners set in place on top of it. We still have to finish pulling the liner over the outer tank yet. The water will go from a valve cellar on the pad through a (12) inch high density polyethylene line made of plastic material and then will be pumped into the tank. The water transferred into the tank is pumped from nearby well development impoundments and the nearby Zeffer centralized wastewater impoundment through underground pipelines to the valve cellar in the corner of the pad at the base of the cut slop
2665864 Primary Facility 2017-11-28 Routine/Complete Inspection No Violations Noted At time of inspection.

I met with company man Chris Henry. USWS (U. S. Well Services) was on site to frac the 2H, 3H, 4H, 5H, and 6H wells. They finished running the plug and perf after stage 2 and were preparing to frac stage 3 out of 24 stages on the 2H. The 3H was completed with 26 stages. The 4H was completed with 22 stages. The 5H was completed with 21 stages. The 6H was completed with 28 stages. The water was being pumped to the location from the Young fresh water impoundment. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2676328 Primary Facility 2017-12-27 Routine/Complete Inspection No Violations Noted Today's inspection was conducted as a routine inspection. Crews on-site installing new containment. Good well pad stabilization. No violations were noted.
2688023 Primary Facility 2018-01-23 Incident- Response to Accident or Event No Violations Noted Today's inspection was conducted as an incident inspection. At approximately noon today, Mike Deming, SWN Senior Regulatory Analyst contacted the Department to inform the Department that SWN had identified stormwater discharges off of secondary containment on 3 of their pads, of which this pad is one. Present during the inspection was Dillon Otten, SWN Regulatory Analyst. The Department metered for conductivity on the outside of the containment and had readings ranging from 40 uS to 255 uS. Standing water inside containment was read at 60 uS at the lowest point of containment where a discharge had occurred. 6 empty water tanks located on containment. No E&S violations were noted. No violations were observed.
2722771 Primary Facility 2018-04-23 Routine/Complete Inspection No Violations Noted At time of inspection.

The well was recently completed and put in production. The well tag was on the well and correct. The cellar was set up with a corrugated pipe around the well for inspection access. The (20x13) and (13x9) annuli were below the water level and there was no bubbling noticed. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2824287 Primary Facility 2019-01-09 Routine/Complete Inspection No Violations Noted At time of inspection.

The well was in production. The cellar was set up with a plastic corrugated pipe around the well for inspection access. The cellar was full of water and there was no bubbling noticed. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

For data sources see[8]