Well ID: 37-115-22493
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Harford Township
Operator Name: CABOT OIL & GAS CORP
Well Pad ID: 147696
Farm/Lease Name: ADAMS J 003
License Status:
Spud Date: 2018-07-02
Permit Date: 2018-03-22
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.771378
Longitude: -75.700072

For data sources see[1][2][3]

Well History

Date Event
Deviated
2018-03-22 New Permit Application
2018-07-02 Performed Spud Operation
2018-11-06 Drilling Completion

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-12-21 2019-02-05 7,412 21,295,700 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Acid Inhibitor, KAI-12 Keane Acid Inhibitor Ethylene glycol 107-21-1 40 0.000302638 614.459
isoproyl alcohol 67-63-0 5 0.00003783 76.807
Tar bases, quinoline derivs., benzyl chloride-quaternized 72480-70-7 10 0.00007566 153.615
formic acid 64-18-6 10 0.00007566 153.615
Cinnamaldehyde 104-55-2 10 0.00007566 153.615
Ethoxylated alcohol 68131-39-5 10 0.00007566 153.615
dipropylene gylcol, monomethyl ether 34590-94-8 20 0.000151319 307.23
Biocide, MBC-516 Keane Biocide quaternary ammonium compounds,
benzyl-C12-16-alkyldimethyl, chlorides
68424-85-1 5.3 0.00048101 976.613
Water 7732-18-5 56.7 0.00513802 10431.9
Glutaral 111-30-8 26.7 0.00241864 4910.65
ethanal 64-17-5 2.8 0.00025364 514.975
didecyldimethylammonium chloride 7173-51-5 8 0.000721967 1465.84
Iron Control, KFEAC-20/30 Keane Iron Control Acetic acid 64-19-7 5 0.000107119 217.487
Citric acid 77-92-9 30 0.000642712 1304.92
Sand (Proppant) Keane Proppant Crystalline silica: Quartz (SiO2) 14808-60-7 100 12.1012 24,569,500.0
Scale Inhibitor, KSI-19 Keane Scale Inhibitor Water 7732-18-5 65 0.0111726 22684.2
Methanol 67-56-1 20 0.00343773 6979.76
organic phosphonic salts 15827-60-8 15 0.0025783 5234.82
Other Chemical(s) Listed Above See Trade Name(s) List Citric acid 77-92-9 30 0.000642712 1304.92
quaternary ammonium compounds,
benzyl-C12-16-alkyldimethyl, chlorides
68424-85-1 5.3 0.00048101 976.613
organic phosphonic salts 15827-60-8 15 0.0025783 5234.82
alcohols, C 12-16, ethoxylated 68551-12-2 1 0.00108715 2207.29
ethanal 64-17-5 2.8 0.00025364 514.975
isoproyl alcohol 67-63-0 5 0.00003783 76.807
Glutaral 111-30-8 26.7 0.00241864 4910.65
Ammonium Chloride 12125-02-9 1.5 0.00163073 3310.93
Cinnamaldehyde 104-55-2 10 0.00007566 153.615
Petroleum distillate, Hydrotreated Light 64742-47-8 20 0.021743 44145.7
oleic acid diethanolamide 93-83-4 1.5 0.00163073 3310.93
Methanol 67-56-1 20 0.00343773 6979.76
didecyldimethylammonium chloride 7173-51-5 8 0.000721967 1465.84
Water 7732-18-5 7.5 0.0174278 35384.4
Ethoxylated alcohol 68131-39-5 10 0.00007566 153.615
dipropylene gylcol, monomethyl ether 34590-94-8 20 0.000151319 307.23
Tar bases, quinoline derivs., benzyl chloride-quaternized 72480-70-7 10 0.00007566 153.615
formic acid 64-18-6 10 0.00007566 153.615
Hydrochloric Acid (15%) Keane Acidizing Water 7732-18-5 7.5 0.0174278 35384.4
Hydrochloric Acid 7647-01-0 15 0.0348556 70768.7
Friction Reducer, KFR-16FW Keane Friction Reducer Water 7732-18-5 60 0.0652291 132437
Petroleum distillate, Hydrotreated Light 64742-47-8 20 0.021743 44145.7
oleic acid diethanolamide 93-83-4 1.5 0.00163073 3310.93
Ammonium Chloride 12125-02-9 1.5 0.00163073 3310.93
alcohols, C 12-16, ethoxylated 68551-12-2 1 0.00108715 2207.29
Water Cabot Carrier/Base Fluid Water 7732-18-5 100 87.5286 177,713,000.0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 CABOT OIL & GAS CORP 6,774,724.00 298 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 CABOT OIL & GAS CORP Synthetic Liner Materials 12.13 Tons LANDFILL 101247
2018 CABOT OIL & GAS CORP Produced Fluid 58.57 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Drill Cuttings 1,568.89 Tons LANDFILL 101247
2018 CABOT OIL & GAS CORP Produced Fluid 90.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE004
2019 CABOT OIL & GAS CORP Waste Water Treatment Sludge 94.88 Tons REUSE (AT WELL PAD)
2019 CABOT OIL & GAS CORP Synthetic Liner Materials 22.46 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Produced Fluid 17,509.08 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE004
2019 CABOT OIL & GAS CORP Unused Fracturing Fluid Waste 2.83 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Produced Fluid 8,433.98 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2019 CABOT OIL & GAS CORP Other Oil & Gas Wastes 0.12 Tons RESIDUAL WASTE PROCESSING FACILITY 301333
2019 CABOT OIL & GAS CORP Synthetic Liner Materials 0.06 Tons RESIDUAL WASTE TRANSFER FACILITY 101714

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2748421 Primary Facility 2018-07-03 Drilling/Alteration No Violations Noted At time of inspection.

On site for a new spud inspection. Met with company man David Dewberry. United Drilling was on site to drill and run the conductor pipe for the 1H, 2H,3H, 5H, 7H, 8H and 10H wells. There was one auger rig and two air rigs running when I arrived on site. There was an air rig on the 1H at a depth of 7.5'. The 2H was drilled to a depth of 105' and the auger rig was going in to clean out to bottom and run the conductor pipe. The 3H was completed and the conductor pipe was in the hole at a depth of 105'. The 5H was at a depth of 8'. The 7H was at a depth of 6.5'. The second air rig was rigging up on the 8H which was at a depth of 8.5'. The 10H was drilled to a depth of 105'. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2750993 Primary Facility 2018-07-09 Routine/Complete Inspection No Violations Noted Today's inspection was conducted as part of an investigation into a nearby water supply complaint in which the water well was impacted by a heavy sediment load on 7/3/18. As Photo #2 shows, new wells have recently been spud on this pad. A review of the most recent Department Drilling Inspection, Inspection Record No. 2748434 found that conductor pipe was installed on 7/3/18 for 7 wells, the 1H, 2H, 3H, 5H, 7H, 8H, and the 10H. The conductors were all drilled to a depth of approximately 105'. During the 7/3/18 inspection, the inspector noted that 3 Rigs were being operated, one auger rig and two air rigs. No E&S issues were identified. No violations noted.
2758175 Primary Facility 2018-07-31 Drilling/Alteration No Violations Noted At time of inspection.

Met with company man William Smith. PD 181 was on site to drill and set the surface and intermediate casings. There are two existing wells on site that are temporarily plugged and there are seven new wells on site to be drilled. They are on the first of the seven wells. They are drilling with WBM. They were running the last of there intermediate casing when I arrived on site. Schlumberger was setting up to run cement when it was noticed the threads on the landing joint were bad. The cementing is on hold until the landing joint is replaced. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2830126 Primary Facility 2019-01-22 Routine/Complete Inspection No Violations Noted At time of inspection.

Met with company man Andy Rodriguez. Keane was on site to frac the 1H, 2H, 3H, 5H, 7H, 8H and 10H wells. They were stimulating stage 10 out of 50 stages on the 10H and running a plug and perf in the 2H when I arrived on site. The 1H was completed with 51 stages. There were 20 stages completed out of 58 on the 2H. There were 49 stages completed out of 50 on the 3H. There were 49 stages completed out of 51 on the 5H. There were 21 stages completed out of 23 on the 7H. The 8H wasn't started but will have 30 stages. The water was being trucked to the site. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2850446 Primary Facility 2019-03-07 Routine/Complete Inspection No Violations Noted Today's inspection was conducted as a routine inspection. Present during the inspection was Cabot Site Supervisor Steve Gillman. Stimulation activities have been completed and site is currently being demobilized. Production equipment installation is also occurring. Overall the site appears to have good stabilization. No E&S issues identified. No violations noted.

For data sources see[8]