37-117-20288

Well Details

Well ID: 37-117-20288
Loading map...
Country: United States
State: Pennsylvania
County: Tioga
Municipality: Ward Township
Operator Name: REPSOL OIL & GAS USA LLC
Well Pad ID: 148190
Farm/Lease Name: DCNR 587 02 002 03
License Status: INACTIVE
Spud Date:
Permit Date: 2009-06-30
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.698044
Longitude: -76.965122

For data sources see[1][2][3]

Well History

Date Event
2009-06-30 New Permit Application
2009-09-12 Performed Spud Operation
2010-03-10 Drilling Completion
2010-05-11 Perforation
2010-05-18 Perforation
2010-08-16 DEVIATED
2011-04-28 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2009 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0
2010 REPSOL OIL & GAS USA LLC 919,009.00 154 0.00 0 0.00 0
2011 REPSOL OIL & GAS USA LLC 1,354,422.00 363 0.00 0 0.00 0
2012 REPSOL OIL & GAS USA LLC 50,899.00 21 0.00 0 0.00 0
2013 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0
2014 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0
2015 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0
2016 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0
2017 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0
2019 REPSOL OIL & GAS USA LLC 0.00 0 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 REPSOL OIL & GAS USA LLC Produced Fluid 110.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0102784
2010 REPSOL OIL & GAS USA LLC Produced Fluid 1,869.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW018
2010 REPSOL OIL & GAS USA LLC Drilling Fluid Waste 312.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW018
2011 REPSOL OIL & GAS USA LLC Drill Cuttings 54.00 Tons LANDFILL NY # 02S17
2011 REPSOL OIL & GAS USA LLC Produced Fluid 356.99 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123
2011 REPSOL OIL & GAS USA LLC Fracing Fluid Waste 399.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW018
2011 REPSOL OIL & GAS USA LLC Produced Fluid 12.53 Bbl REUSE OTHER THAN ROAD SPREADING
2011 REPSOL OIL & GAS USA LLC Drill Cuttings 83.00 Tons LANDFILL NY31346244
2011 REPSOL OIL & GAS USA LLC Produced Fluid 112.97 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW018

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1823448 Primary Facility 2009-08-25 Routine/Complete Inspection Violation(s) Noted Inspection report and 3rd page NOV sent 8/27/2009 to Eric Potter. Picture of Silt fence included. VIOLS 102.49(b) and 102.4(b)(5) 117-20317,117-202316, &117-20289 same well pad dulpicate inspections. 8/27/2009 MAB
1852929 Primary Facility 2009-12-28 Routine/Complete Inspection No Violations Noted
1919364 Primary Facility 2010-10-12 Follow-up Inspection No Violations Noted Follow-up inspection to correct August 25, 2009 violations
2378410 Primary Facility 2015-06-05 Routine/Complete Inspection No Violations Noted
2464228 Primary Facility 2016-03-10 Routine/Partial Inspection No Violations Noted 4 Marcellus Shale wells producing natural gas from this pad
2596678 Primary Facility 2017-05-19 Routine/Partial Inspection No Violations Noted An inspection was conducted of the DCNR 02–002 and compressor station site on May 19, 2017 from approximately 10 AM to approximately 11 AM. Repsol is reminded that weekly inspections are to be conducted until such time as the notice of termination has been approved for the erosion and sedimentation control general permit. No violations were cited during this inspection. The area of the compressor station was not inspected although the surrounding area appears to be stabilized
2600315 Primary Facility 2017-06-02 Administrative/File Review No Violations Noted And administrative inspection was completed to document the fact that in a previous inspection report, due to a typographical error in department records, it was incorrectly noted the erosion and sedimentation control general permit (ESCGP)h had expired. The ESCGP for this site actually expires on 10/9/2019.
2605078 Primary Facility 2017-06-14 Site Restoration No Violations Noted EC readings (mS/cm) w Oakton PCSTestr 35: separator containment--0.24, production tank containment--0.16, pad--0.33
2650640 Primary Facility 2017-10-23 Routine/Complete Inspection No Violations Noted Well producing.

Cool/windy at time of inspection.

One 2" annulus vent.

2790048 Primary Facility 2018-10-10 Routine/Partial Inspection No Violations Noted ~20' onto the pad from the access gate, gravel has dark staining, and a puddle has a cream color substance floating on it (photo 3). I used a MiniRAE 3000 Photo Ionization Detector (PID) and got readings of 3.0-6.0 ppm (photo 2) from above the stained area, indicating that volatile gas is present. Apparently, there is some residual hydraulic oil on the pad surface, which is a violation of SWMA 301.

I spoke with Ben Younkin & Kris Perritt (both Repsol) by telephone; they explained that a hydraulic oil release (~1 gallon) happened in the area that is stained, which Repsol reported on September 20, 2018. They planned to apply absorbents and cover the area with plastic tomorrow, then excavate to remove the affected pad material in 2 days (Friday October 12, 2018). I used an Oakton PCSTestr 35 to get readings from pooled liquid on site. A puddle on the pad surface near the production tanks returned a 0.35 mS/cm reading. Golder documented the excavation cleanup on Friday October 12, 2018 (email & photos atta

2790562 Primary Facility 2018-10-17 Follow-up Inspection No Violations Noted Repsol excavated to remove some of the pad surface that was stained by a reported hydraulic oil spill. I used a MiniRAE 3000 PID to check for volatile gases above the excavated area; it did not detect any.

I got a 0.13 mS/cm fro a water puddle near the center of the pad using an Oakton PCSTestr 35 today. JLP

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
1823448 570104 08/25/2009 2009-08-25 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) Environmental Health & Safety silt fence maintainence and improper installation of diversion ditch and sediment traps
1823448 570105 08/25/2009 2009-08-25 102.4INADPLN - E&S Plan not adequate Administrative E & S plan not reflective of site conditions

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
570104 249922 NOV - Notice of Violation Comply/Closed 2010-10-12
570105 249922 NOV - Notice of Violation Comply/Closed 2010-10-12

For data sources see[7]

References