{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.573133,"lon":-77.0514,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Tioga | |
Municipality: Liberty Township | |
Operator Name: ROCKDALE MARCELLUS LLC | |
Well Pad ID: 148455 | |
Farm/Lease Name: GUILLAUME M 714E 5H | |
License Status: Inactive | |
Spud Date: 2012-08-04 | |
Permit Date: 2012-07-20 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 41.573133 | |
Longitude: -77.0514 |
Date | Event |
---|---|
Deviated | |
2012-07-20 | New Permit Application |
2012-08-08 | Performed Spud Operation |
2012-11-04 | Drilling Completion |
2014-01-30 | New Permit Application |
2017-03-15 | Inactive Well Request Granted |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2012 | SWEPI LP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2013 | SWEPI LP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2014 | SWEPI LP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2015 | SWEPI LP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2016 | SWEPI LP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2017 | SWEPI LP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2018 | ROCKDALE MARCELLUS LLC | 26,735.00 | 31 | 0.00 | 0 | 0.00 | 0 |
2019 | ROCKDALE MARCELLUS LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2012 | SWEPI LP | Produced Fluid | 559.52 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123 |
2012 | SWEPI LP | Drill Cuttings | 2,085.84 Tons | LANDFILL | 301358 |
2012 | SWEPI LP | Fracing Fluid Waste | 354.76 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2012 | SWEPI LP | Fracing Fluid Waste | 590.43 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123 |
2012 | SWEPI LP | Drilling Fluid Waste | 300.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123 |
2013 | SWEPI LP | Fracing Fluid Waste | 300.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | SWEPI LP | Fracing Fluid Waste | 0.65 Bbl | STORAGE PENDING DISPOSAL OR REUSE | 7-3115-00193 |
2014 | SWEPI LP | Fracing Fluid Waste | 438.76 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | SWEPI LP | Produced Fluid | 8.67 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NC010 |
2014 | SWEPI LP | Produced Fluid | 4,474.08 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2014 | SWEPI LP | Produced Fluid | 163.75 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123 |
2017 | SWEPI LP | Produced Fluid | 74.99 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC022 |
2017 | SWEPI LP | Drilling Fluid Waste | 1.31 Bbl | RESIDUAL WASTE TRANSFER FACILITY | 7-3115-00193 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2100572 | Primary Facility | 2012-08-23 | Routine/Complete Inspection | No Violations Noted | Pre-operational insp. |
2123760 | Primary Facility | 2012-12-13 | Routine/Complete Inspection | No Violations Noted | |
2265201 | Primary Facility | 2014-04-23 | Routine/Complete Inspection | No Violations Noted | 5H well has been drilled. TLT |
2463128 | Primary Facility | 2016-03-09 | Routine/Complete Inspection | No Violations Noted | Site is well vegetated with >70% cover of perenial vegetation. No evidence of accelerated erosion or sedimentation was observed.
No restoration activities have occurred on this site. According to the Department's records, a restoration extension request was approved by the Department on 04/15/2015, which extends the deadline for restoration until 04/15/2017. No violations were cited during this inspection. |
2522757 | Primary Facility | 2016-09-26 | Routine/Complete Inspection | No Violations Noted | |
2545948 | Primary Facility | 2016-12-19 | Routine/Complete Inspection | No Violations Noted | |
2562131 | Primary Facility | 2017-02-16 | Routine/Complete Inspection | No Violations Noted | No violations cited. This pad has not been partially restored. No producing wells. |
2750186 | Primary Facility | 2018-07-10 | Routine/Complete Inspection | No Violations Noted | The weather is 85 Deg. F and sunny at the time of inspection. Routine inspection of Rockdale Marcellus LLC., Harer 713 Pad, well # 5H on July 10, 2018.
Well is temporary shut in due to drilling operation on site. No violations are noted at time of inspection. Wellsite looks neat and well organized. DEP Representative - Ulyana Trynovich, Richard Becher, Oil and Gas Inspectors. Rockdale Marcellus LLC. Representative ¿ Danny Brooks, Wellsite Supervisor. |
2752935 | Primary Facility | 2018-07-16 | Routine/Complete Inspection | No Violations Noted | Weather was 88° and sunny at time of inspection. Well is shut in with no production equipment attached to it. Well had 4 annulus vents plumbed to surface at time of inspection. The was 0% combustible gas was detected on the vents or in the area around the well at time of inspection. No conditions with the well appeared to have changed since last inspected. No violations were noted at time of inspection. |
2760466 | Primary Facility | 2018-08-06 | Routine/Complete Inspection | No Violations Noted | Weather was 74° and sunny at time of inspection. Met with Rockdale Marcellus representative Danny Brooks on location. Well was shut in with no production equipment attached to it. Well had 4 annulus vents plumbed to surface at time of inspection. There was 0% combustible gas was detected on the vents or in the area around the well at time of inspection. No conditions with the well appeared to have changed since last inspected. No violations were noted at time of inspection. |
2762767 | Primary Facility | 2018-08-13 | Routine/Complete Inspection | No Violations Noted | Weather was 68° and raining at time of inspection. Met with Rockdale Marcellus representative Danny Brooks on location. Well was shut in with no production equipment attached to it. Well had 4 annulus vents plumbed to surface at time of inspection. There was 0% combustible gas was detected on the vents or in the area around the well at time of inspection. No conditions with the well appeared to have changed since last inspected. No violations were noted at time of inspection. |
2763031 | Primary Facility | 2018-08-01 | Routine/Complete Inspection | No Violations Noted | Routine Inspection; 8/1/2018.
I entered the site at 10:30 and inspected the stormwater controls along the access road. The area is well vegetated and temporary E&S controls are in the process of being removed. On the well pad, I talked to Mr. Carrasco (rig manager) from Patterson -UTI and we walked the site. At the time of the inspection, the BOP stack was installed on the Guillaume 6H (117-22003) but flow line was not yet connected. The derrick was up but cuttings management/backyard is still being rigged-up. Containment is in good condition and the wooden rig mats are also in good condition. Drilling additives and potential contaminants are stored in containment or have additional individual containment/cover. After walking the site, I talked to Danny Brooks (company man) and discussed the containment, maintenance, and the other two wells planned for the site. Overall, the site is in good condition. No violations noted. |
2765038 | Primary Facility | 2018-08-20 | Routine/Complete Inspection | No Violations Noted | Weather was 66° and cloudy at time of inspection. Met with Rockdale Marcellus representative Jim Tracey on location. Well was shut in with no production equipment attached to it. Well had 4 annulus vents plumbed to surface at time of inspection. There was 0% combustible gas was detected on the vents or in the area around the well at time of inspection. No conditions with the well appeared to have changed since last inspected. No violations were noted at time of inspection. |
2771407 | Primary Facility | 2018-09-06 | Routine/Complete Inspection | No Violations Noted | Weather was 77° and sunny at time of inspection. Met with Rockdale Marcellus representative Levi Lee on location. Well was shut in with no production equipment attached to it. Well had 4 annulus vents plumbed to surface at time of inspection. There was 0% combustible gas was detected on the vents or in the area around the well at time of inspection. No violations were noted at time of inspection. |
2778823 | Primary Facility | 2018-09-24 | Routine/Complete Inspection | No Violations Noted | Weather was 62° and partly sunny at time of inspection. Met with Rockdale Marcellus representative Luke on location. Well was shut in with no production equipment attached to it. Well had 4 annulus vents plumbed to surface at time of inspection. There was 0% combustible gas was detected on the vents or in the area around the well at time of inspection. No violations were noted at time of inspection. |
For data sources see[7]