37-117-21924

Well Details

Well ID: 37-117-21924
Loading map...
Country: United States
State: Pennsylvania
County: Tioga
Municipality: Liberty Township
Operator Name: SWN PROD CO LLC
Well Pad ID: 151565
Farm/Lease Name: MASE MONTE 1H
License Status:
Spud Date:
Permit Date: 2017-10-06
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.558814
Longitude: -77.138853

For data sources see[1][2][3]

Well History

Date Event
2017-10-06 New Permit Application
2017-12-15 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-04-28 2018-05-29 7,251 16,207,100 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 HYDROCHLORIC ACID Halliburton Solvent Listed Below Listed Below 0 0 0
Tributyl tetradecyl phosphonium chloride 81741-28-8 10 0.0027568 4259
Hydroteated light petroleum distillate 64742-47-8 30 0.027888 43072
Non-hazardous food substance Proprietary 100 0.000466191 720
Polyacrylate Proprietary 30 0.027888 43072
Ammonium chloride 12125-02-9 30 0.00795087 12281
Inorganic salt Proprietary 30 0.000281292 435
Fatty acid ester Proprietary 5 0.00929601 14358
Propylene glycol 57-55-6 60 0.00213395 3296
Crystalline silica, quartz 14808-60-7 100 10.6808 16,495,700.0
Sodium chloride 7647-14-5 5 0.004648 7179
Acrylamide acrylate copolymer Proprietary 30 0.000281292 435
Hydrochloric acid 7647-01-0 15 0.2289 353520
Diammonium phosphate 7783-28-0 5 0.000550478 851
Organic phosphonate Proprietary 60 0.00660574 10203
Hydrotreated light petroleum distillate 64742-47-8 30 0.000281292 435
Ethoxyalted fatty acid Proprietary 5 0.004648 7179
SAND-COMMON WHITE-100 MESH, SSA-2, BULK (100003676) Halliburton Proppant Listed Below Listed Below 0 0 0
SAND-PREMIUM WHITE-30/50, BULK Halliburton Proppant Listed Below Listed Below 0 0 0
Fresh Water Operator Base Fluid Water 7732-18-5 100 87.6603 135,385,000.0
BE-9W Halliburton Biocide Listed Below Listed Below 0 0 0
EXCELERATE LX-1 Halliburton Friction Reducer Listed Below Listed Below 0 0 0
HAI-150E Halliburton Corrosion Inhibitor Listed Below Listed Below 0 0 0
Ingredients Listed Above Listed Above Water 7732-18-5 100 1.61651 2,496,590.0
BE-9 Halliburton Biocide Listed Below Listed Below 0 0 0
FR-76 Halliburton Friction Reducer Listed Below Listed Below 0 0 0
LP-65 MC Halliburton Scale Inhibitor Listed Below Listed Below 0 0 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 SWN PROD CO LLC 0.00 0 0.00 0 0.00 0
2018 SWN PROD CO LLC 2,425,768.00 199 0.00 0 0.00 0
2019 SWN PROD CO LLC 2,318,197.00 365 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 SWN PROD CO LLC Produced Fluid 109.34 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 SWN PROD CO LLC Produced Fluid 53,985.34 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2018 SWN PROD CO LLC Soil Contaminated by Oil & Gas Related Spills 0.72 Tons LANDFILL 301358
2018 SWN PROD CO LLC Other Oil & Gas Wastes 67.94 Bbl SURFACE IMPOUNDMENT 826342
2018 SWN PROD CO LLC Unused Fracturing Fluid Waste 9.48 Tons LANDFILL 100933
2018 SWN PROD CO LLC Drilling Fluid Waste 300.00 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Drill Cuttings 1,910.74 Tons LANDFILL 301626
2018 SWN PROD CO LLC Produced Fluid 23,300.00 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Produced Fluid 240.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 SWN PROD CO LLC Other Oil & Gas Wastes 128.30 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2018 SWN PROD CO LLC Other Oil & Gas Wastes 444.67 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Drilling Fluid Waste 10.00 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2018 SWN PROD CO LLC Other Oil & Gas Wastes 134.92 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 SWN PROD CO LLC Synthetic Liner Materials 48.00 Tons LANDFILL 301358
2018 SWN PROD CO LLC Soil Contaminated by Oil 0.72 Tons LANDFILL 301358
2018 SWN PROD CO LLC Drill Cuttings 57.33 Tons LANDFILL 101247
2018 SWN PROD CO LLC Produced Fluid 28,825.00 Bbl SURFACE IMPOUNDMENT 826342
2018 SWN PROD CO LLC Drilling Fluid Waste 2,325.80 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2019 SWN PROD CO LLC Produced Fluid 73.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2019 SWN PROD CO LLC Produced Fluid 2,546.67 Bbl SURFACE IMPOUNDMENT 826342
2019 SWN PROD CO LLC Other Oil & Gas Wastes 106.67 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Produced Fluid 12,466.66 Bbl REUSE (AT WELL PAD)
2019 SWN PROD CO LLC Other Oil & Gas Wastes 33.33 Bbl SURFACE IMPOUNDMENT 826342
2019 SWN PROD CO LLC Produced Fluid 13,118.33 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Produced Fluid 2,706.67 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC035
2019 SWN PROD CO LLC Other Oil & Gas Wastes 66.67 Bbl REUSE (AT WELL PAD)
2019 SWN PROD CO LLC Synthetic Liner Materials 26.59 Tons LANDFILL 301358
2019 SWN PROD CO LLC Waste Water Treatment Sludge 5.55 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2678256 Primary Facility 2018-01-04 Routine/Complete Inspection No Violations Noted Conductor only at time of inspection.

Containment mat over cellar was unable to visually see in the cellar.

Cold/windy at time of inspection.

2691362 Primary Facility 2018-02-06 Routine/Complete Inspection No Violations Noted Weather was 30 degrees f. and cloudy at time of inspection. Met with SWN representative Andrew Griffith on location. While drilling the surface casing, fresh water was encountered. The amount and depths were as follows, approximately 20 bbl/hr at 325 ft. 200 lb/hr 390 ft, 240 Bbl/hr at 430 ft, 250 bbl/hr at 675'. Reviewed the cement job log from the surface casing and no discrepancies were noted. The rig was in the process of running intermediate casing in the hole. Cementing of the intermediate casing was anticipated to happen at approximately 12 pm. Conducted an inspection of the cellars on the other 2 wells on location and the area surrounding the rig. No violations were noted at time of inspection.
2693164 Primary Facility 2018-02-12 Routine/Complete Inspection No Violations Noted Weather was 32° and sunny at time of inspection. Met with SWN representative Andrew Griffith on location. Rig was in the process of drilling the 8 3/4 inch hole for the production casing. Kick off point is estimated to be at 6338'. Reviewed the job log from the intermediate casing cement job and no discrepancies were noted. Discussed the drilling activities the rig was intending to complete in the upcoming week. No violations noted at time of inspection.
2695788 Primary Facility 2018-02-20 Routine/Complete Inspection No Violations Noted Weather was 45° and cloudy at time of inspection. Met with SWN representative Johnathan Woodburn on location. Rig was in the process of drilling the 8 1/2 inch hole for the production casing. Kick off point was at 6293' and the landing point was 7795'. Mud weight was 14.1 ppg. Discussed the drilling activities the rig was intending to complete in the upcoming week. No violations noted at time of inspection.
2698147 Primary Facility 2018-02-26 Routine/Complete Inspection No Violations Noted Weather was 40° and sunny at time of inspection. Met with SWN representative Johnathan Woodburn on location. Rig was in the process of preparing to move to the 2H well on the pad. Cementing of the production string on the 1H well was completed at 9:30 pm on 02/25/2018. The estimated top of cement was 3203'. The cement company had some mechanical issues during the cement job but cement density was maintained and they bumped the plug. Discussed the drilling activities the rig was intending to complete in the upcoming week on the 2H well. Drilling on the 2H was estimated to be commencing on 2/27/18. No violations noted at time of inspection.
2699542 Primary Facility 2018-02-28 Routine/Complete Inspection No Violations Noted I met Andrew Griffith, SWN company man, when I arrived. SWN 45 rig onsite, currently drilling the 2H well. Depth was 701', and Andrew informed me they would begin to run surface casing at 762'. Andrew accompanied me on the inspection. Containment was in good condition, with very little accumulated stormwater. Housekeeping was also good. Ramps run over the berm in traffic areas seem to be keeping the berms and containment from damage.
2702041 Primary Facility 2018-03-07 Routine/Complete Inspection No Violations Noted Weather was 30° and snowing at time of inspection. Well has recently been cemented to TD and is now covered by the cat-walk while the rig completes drilling and cementing the 2H and the 3H. No violations noted at time of inspection.
2703824 Primary Facility 2018-03-12 Routine/Complete Inspection No Violations Noted Weather was 30° and cloudy at time of inspection. Well has recently been cemented to TD and is now covered by the cat-walk while the rig completes drilling and cementing the 2H and the 3H. No violations noted at time of inspection.
2707315 Primary Facility 2018-03-15 Routine/Complete Inspection No Violations Noted Weather was 35° and cloudy at time of inspection. Met with SWN representative Johnathan Woodburn. Well has recently been cemented to TD and is now covered by the cat-walk while the rig completes drilling and cementing the 2H and the 3H. No violations noted at time of inspection.
2709819 Primary Facility 2018-03-22 Routine/Complete Inspection No Violations Noted Weather was 34° and cloudy at time of inspection. Met with SWN representative Johnathan Woodburn. Well has recently been cemented to TD and is now covered by the cat-walk while the rig completes drilling and cementing the 2H and the 3H. There has been no visible change in cellar conditions during completions of the other 2 wells on site. No violations noted at time of inspection.
2714774 Primary Facility 2018-04-05 Routine/Complete Inspection No Violations Noted Weather was 34° and cloudy at time of inspection. Met with SWN representative Andrew Griffith on location. Well was shut in at time of inspection. There has been no visible change in cellar conditions during completions of the other 2 wells on site. No violations noted at time of inspection.
2716528 Primary Facility 2018-04-10 Routine/Complete Inspection No Violations Noted Weather was 33° and cloudy at time of inspection. No SWN representatives were on location at time of inspection. Rig has recently moved off location to the Connolly pad. Well is shut in and has 3 analog pressure gauges attached. Needle valves to pressure gauges were all closed at time of inspection. No combustible gas was detected in the cellar or in the area around the well head at time of inspection. No violations noted at time of inspection.
2725494 Primary Facility 2018-05-01 Routine/Complete Inspection No Violations Noted I met John Cave of SWN logistics when I arrived. Frac was active and pressured up. Both the sitewide and individual secondary containments appeared to be in good shape. Two tanker trailers were on their own containment near the sand boxes, but the containment had been twisted and folded; I recommended that this containment be addressed. After my inspection, I met SWN company man Donnie Torres. Donnie told me the frac started Friday (4/27), and they are zipper fracing the three wells. They are getting through 4 stages a day, but had trouble initially getting the wells to open up, and are only 8 stages in.
2775140 Primary Facility 2018-09-11 Routine/Complete Inspection No Violations Noted Southwestern Energy (SWN) submitted a well site restoration report to the Department for the SWN TI-01-Mase Monte Pad on 8/29/18.

Three SWN employees remained in their vehicles during the inspection.

Due to recent rainfall water puddles had formed on the pad. The conductivity of one of these puddles was 167.1 µS/cm.

Three Marcellus wells are staged for production (1H, 2H, & 3H) and properly tagged. There are also 3 GPUs, 1 produced water tank, and 2 batteries of flowback tanks onsite. GPUs, storage tanks, and wells were in secondary containment. Standing water in the produced water tank secondary storage had a conductivity of 152.6 µS/cm. Standing water in the flowback tank/well secondary containment had a conductivity of 52.3 µS/cm.

The first PCSM BMP is a rock sump infiltration area on the N edge of the pad; conductivity of water retained by the infiltration area was 92.7 µS/cm. The second PCSM BMP is a rock sump infiltration area on the S edge of the pad. At the time of inspection both PCSM BMPs app

2837869 Primary Facility 2019-02-06 Routine/Complete Inspection No Violations Noted Inspection conducted in response to a spill of produced water reported to the Department by the operator on February 6, 2019. The report from the operator stated that the spillI was estimated at 20 gallons and occurred on the access road to the pad. I was met on location by Dillion Otten, regulatory analyst for SWN, upon my arrival. He told me that they had already finished excavating the area impacted by the spill and all of the excavated material was present in a roll-off container that was present on the pad within secondary containment. He stated that the container was filled entirely with material from the excavation. He also stated that the excavation was completed visually and aided by a soil conductivity meter.

Three GPUs and sand separators are present on the pad within secondary containment. The GPUs and containment are in good condition. Two batteries of frac tanks are present within secondary containment. The tanks and containment are in good condition. Mr. Otten of SWN said that these tanks ar